SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Jhk) 1282

IN THE HIGH COURT OF JHARKHAND AT RANCHI 
M. S. Ramachandra Rao, C.J., Deepak Roshan, J.
The State Highways Authority of Jharkhand through its Chief Executive Officer - Appellant
Versus
Intercontinental Consultants & Technocrats Pvt. Ltd. - Respondent
Commercial Appeal No. 7 of 2024
Decided On : 28-02-2025

Advocates:
Advocate Appeared:
For the Appellant :Mr. Rajiv Ranjan, Advocate General, Mr. Ashutosh Anand, AAG-III, Mr. Sharad Kaushal, A.C. to A.A.G.-III, Mr. Shray Mishra, A.C. to A.G., Ms. Bharti Kumari, A.C. to A.G.
For the Respondent:Mr. Ajit Kumar, Sr. Advocate, Mr. Vikalp Gupta, Advocate

The court emphasized that an application under Section 34 of the Arbitration Act does not allow for a full appeal, restricting re-evaluation of evidence and requiring clear grounds for setting aside an award.

Headnote:(A) Commercial Courts Act, 2015 - Section 13 - Arbitration and Conciliation Act, 1996 - Section 34 - Commercial appeal challenging confirmation of arbitral award - Court affirmed the arbitral tribunal's finding of wrongful contract termination - The application under Section 34 is not an appeal; evidence re-appraisal is not permitted - The Commercial Court's judgment on Claims 2 to 9 deemed inadequate - Initially affirmed only Claim 1. (Paras 1-21)

(B) Terms of Contract - The court recognized the importance of fulfilling contractual deliverables and the obligations outlined in the General Conditions of Contract, noting specific timelines and procedural adherence. (Paras 10-12)

(C) Grounds for Setting Aside Award - Court concluded the Commercial Court did not provide adequate reasoning for dismissing claims 2-9 and has remitted the matter back for further consideration. (Paras 21-22)

Facts of the case:
The appellant, State Highway Authority, entered into a consultation contract with the respondent. The contract was terminated, leading to disputes referred to arbitration, resulting in a contested award.

Findings of Court:
The appellate court upheld the Commercial Court's support of the arbitral tribunal's findings on Claim 1 but set aside the judgment regarding the remaining claims due to insufficient reasoning.

Issues: The main issues included the legality of the contract's termination and the adequacy of the Commercial Court's reasoning related to claims 2-9.

Ratio Decidendi: The court emphasized that the termination was improper, and under Section 34, the review was limited to specific grounds; the appeal did not permit extensive evidence re-evaluation.

Result: Judgment regarding Claims 2 to 9 set aside; matter remitted for fresh judgment.

Table of Content
1. procedural background of the arbitration case (Para 1 , 2 , 3 , 4 , 5 , 6 , 7)
2. consideration of claims and defenses (Para 8 , 10 , 11 , 12 , 16 , 17)
3. court's analytical observations on arbitrator's findings (Para 9 , 13 , 14 , 15 , 18 , 19 , 20)
4. decision to set aside parts of the commercial court judgment (Para 21 , 22)
5. final order and directive for fresh judgment (Para 23 , 24)

JUDGMENT :

M.S. Ramachandra Rao, C.J.

1. This Commercial Appeal is preferred under Section 13 of the COMMERCIAL COURTS ACT , 2015 challenging the judgment dt. 16.03.2024 of Additional Judicial Commissioner-III-cum-Presiding Officer, Commercial Court, Ranchi (for short ‘the Commercial Court’) passed in Commercial Arbitration Case No. 04/2022.

2. By the said judgment the Commercial Court has upheld the Award dt. 14.12.2021 of the Arbitral Tribunal and dismissed the application under Section 34 of the Arbitration and Conciliation Act, 1996 (in short ‘the Act’) filed before the said Court by the appellant/applicant/State Highway Authority of Jharkhand.

3. Admittedly, the appellant had entered into an agreement with the respondent in collaboration with another for providing consultation services relating to the Second Jharkhand State Road Project (ABD Funded). This agreement called the ‘Time-Based Contract Agreement’ was initiated on 02.11.2016 and the contract stipulated a revised price of US$ 29,58,300.00 plus Indian Rs.30,60,60,750.00 for the execution, completion of works, and rectification of defects, inclusive of provisional sum and contingencies but exclusive of local indirect taxes.

4. Following the issuance of a notice to proceed on 16.11.2016, work officially commenced on 01.12.2016. The duration of the contract was set at 50 months including a two month pre-construction period and the subsequent 12 month defects and liabilities period starting from the effective date of the contract.

5. The appellant terminated the contract on 05.06.2018 allegedly due to breach of contract by the respondent.

6. The disputes were referred to an arbitrator. Before the learned arbitrator, the respondent raised 9 claims while the appellant raised counter claims.

7. The decision of the Arbitral Tribunal along with 10 claims passed in the Award is as under:

Claim No.Contractor’s claim AmountRespondent’s Assessment & Counter claimTribunal Assessment
INRUSDINRUSD
SOC 1----Claim RejectedClaimant’s Claim is upheld----
SOC 26,44,67,0314,66,205Claim Rejected6,44,67,0314,66,205
SOC 32,26,49,000Claim Rejected2,26,49,000
SOC 46,27,41,0946,39,208Claim Rejected6,27,41,0946,39,208
SOC 568,00,000Claim RejectedRejected----
SOC 61,03,42,66482,156Claim Rejected1,01,35,81080,500
SOC727,79,5169,11,386Claim Rejected40,68,680--
SOC865,22,00065,22,000
Sub Total16,95,01,30588,98,95517,05,83,61511,85,913
SOC912% interest on the above sum12% interest on the above sum 13Interest for INR=10 % Compounded and for USD=8% compounded per year2,42,04,1771,68,269
Counter claim of the respondentDisallowed
Total19,47,87,9213,54,182

8. The appellant questioned the same before the Commercial Court on several grounds and the respondent refuted the said grounds.

The judgment of the Commercial Court

9. The Commercial Court first considered the scope of Section 34 of the Act and referred to the judgments cited by both the parties on the said aspect. It took the view that an application under Section 34 of the Act is not an appeal and the evidence cannot be re-appreciated as in an appeal. It also recognized that there are limited grounds specified in Section 34 of the Act for setting aside an arbitral Award, and after quoting Section 34 of the Act, framed the question as to “whether the Award given by the Arbitrator is against the Public Policy of India with its explanation or it is hit by the grounds mentioned under Section 34 of the Act?”

10. While dealing with Claim 1 which related to setting aside the illegal termination of contract by the appellant through a letter dt. 05.06.2018, which the Arbitra

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top