SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Jhk) 1308

IN THE HIGH COURT OF JHARKHAND AT RANCHI 
Gautam Kumar Choudhary, J.
N.R. Construction Private Limited - Appellant
Versus
The State of Jharkhand through the Secretary Road Construction Department (N.H Wing) - Respondents
Arbitration Appeal No. 16 of 2009
Decided On : 14-02-2025


Advocate Appeared:
For the Appellant :M/s Indrajit Sinha & Puja Agarwal, Advocates
For the Respondent: Mr. Ashok Kr. Yadav, Sr. SC-I

The court clarified that payment for additional work must be recognized if verified, irrespective of lack of written order, reinforcing the limited grounds for setting aside arbitral awards under the Arbitration and Conciliation Act.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34(1)(b) - Appeal against arbitral award being set aside - Contractor entitled to payment for additional work performed despite no written order, as assessment was verified and communicated by department officers - Court reaffirmed that arbitral awards can be interfered with only on limited statutory grounds. (Paras 1, 19, 20)

(B) Misinterpretation of contractual obligations - Misapplication of clause preventing payment for additional work noted by court; denied interpretation that would restrict legitimate claims. (Paras 19, 20)

Facts of the case:
Appellant awarded contract for bridge construction; disputed amount for additional work claimed, which was verified by departmental supervision. Initial arbitral award was in favor of the appellant but was set aside, citing lack of written approval for extra work. (Paras 1, 2)

Findings of Court:
Court held that the additional work done cannot be denied merely based on technical grounds without prior written orders, affirming the necessity of recognizing actual work completed and verified. The arbitral award restoring the payment was reinstated. (Paras 20)

Issues: Whether the appellant is entitled to charges for additional work done despite contractual clause; whether the court exceeded its jurisdiction in setting aside the arbitral award. (Paras 11)

Ratio Decidendi: The court emphasized judicial restraint in arbitration matters, underscoring that arbitrator's awards should not be interfered with unless they contravene public policy or fundamental legal principles; simplistic interpretations should not deny rightful claims for completed additional work. (Paras 12, 20)

Result: Arbitration Appeal allowed; arbitral award restored.

Table of Content
1. contract ambiguities regarding additional work (Para 1 , 2 , 3 , 4 , 5 , 6)
2. judicial standards for arbitral awards (Para 7 , 8 , 9)
3. requirements for payment on additional work (Para 10 , 16 , 17)
4. scope of judicial interference under arbitration act (Para 12 , 13 , 14 , 15)
5. the court emphasized the requirement of follow-through by the department in regard to additional work. (Para 19)
6. restoration of arbitral award upheld (Para 20)

JUDGMENT :

Gautam Kumar Choudhary, J.

1. This appeal is preferred under Section 37 (1)(b) of the Arbitration and Conciliation Act, 1996 against the order dated 29.08.2009 passed under Section 34 of Arbitration and Conciliation Act, whereby and whereunder the arbitral award made by the sole arbitrator has been set aside.

2. Admitted fact leading to the present appeal can be summed up as under:

i. Appellant Company was awarded a contract for construction of minor bridge by the Executive Engineer, Road Construction Division, National Highway No. 2 (respondent no. 4) for a total value of Rs.28,86,371/- vide agreement dated 22.06.1992.

ii. Dispute is with regard to extra work done by the appellant for which a demand was raised for a sum of Rs.30,79,375/- with interest at the rate of 18% per annum on the said amount from 01.07.1999. The appellant invoked the arbitral clause and the matter was referred to the sole arbitrator. The sole arbitrator vide award dated 17.07.2007 awarded the claim for extra work to the tune of Rs.30,79,375/- with @ 8% interest with cost of arbitration of Rs.40,000/- and Rs.32,400/- as respondent’s share of arbitrator’s fees deposited by them.

iii. Respondent preferred Misc. Case No. 56 of 2007 under Section 34 of the Arbitration and Conciliation Act, 1996 in which the award was set aside on the ground that learned arbitrator overlooked the proviso of Clause 11 of the Agreement No. 02/F2/1992-93 dated 22.06.1992 wherein it had been clearly laid down that the contractor shall not be entitled to any payment for any additional work done unless he had received an order in writing from the In-charge for the additional work done.

3. It is argued by learned counsel for the appellant that the State is acting unfairly in the present case by denying the genuine admitted claim of the Appellant for the additional work done, taking shelter under a clause of the agreement. It has not been disputed at any stage that the additional work had not been done.

4. It is further argued that the Superintending Engineer after due examination and verification, forwarded the claim to the Chief Engineer for sanction of the fund to make payment to the claimant. However, the fund was not sanctioned nor any payment was made to the claimant.

5. The rate prescribed was of the year 1986 and the work was completed in the year 1998 i.e. after 12 years from the preparation of the chart of schedule rates, the cost was calculated at an escalated rate and approved by the officer of the Respondent. Annexure-2 is a copy of letter No. 547WE dated 01.07.1999 of the Executive Engineer, N.H No. 2, Dhanbad addressed to the Superintending Engineer enclosing a detailed chart mentioning the additional work with cost. This chart was prepared by the Junior Engineer, Section Gola-2. It also contains the comments and recommendation of the Sub-Divisional Officer, N.H. Division No. 1, Chas and the Executive Engineer, R.C.D.N.H Sub-Division-II, Dhanbad. This chart shows the total cost as Rs. 30,79,375.65. Annexure-3 is the copy of the letter of the Superintending Engineer bearing No. 760(A 90) dated 28.07.2002 addressed to the Chief Engineer recommending the extra costs recommended by the J.E. Asst. Engineer and the Executive Engineer for sanction and payment.

6. It is argued that where the arbitral award is for admitted additional work, the same is not amenable to interference under Section 34 of the 1996 Act.

7. Reliance is placed on the following authorities:

i. (2016) 4 SCC 119 wherein it has been held that absence of

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top