SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Jhk) 114

IN THE HIGH COURT OF JHARKHAND AT RANCHI
Rajesh Kumar, J.
Vanshidhar Electric Private Limited – Petitioner
Versus
State of Jharkhand, through Principal Secretary, Road Construction Department - Respondent
W.P.(C) No. 5863 of 2025
Decided On : 06-01-2026

Advocates Appeared:
For the Petitioner:Mr. Sumeet Gadodia, Advocate, Mrs. Shilpi Sandil Gadodia, Advocate, Mr. Anish Lal, Advocate
For the Respondent: Mr. Mohan Kumar Dubey, AC to AG

The absence of FASTag systems at toll plazas absolves the toll collector from penalties for non-collection of tolls, and compensation for losses due to Force Majeure events must be determined by the authorities.

Headnote:(A) Indian Contract Act, 1872 - Sections 23 and 56 - Writ of Mandamus - Non-payment of toll due to absence of FASTag system at toll plaza and unilateral extension of contract duration - Petitioner claims for reduction of user fee, compensation for Force Majeure event, and asserts status as agent post-contract period. Court found that non-collection was due to statutory non-compliance, thus not penalizing the petitioner for loss. (Paras 5-10)

(B) Force Majeure - Definition and application - Strike by transporters acknowledged as Force Majeure event affecting toll collection. Compensation for losses incurred during this period must be determined by authorities. (Paras 26-29)

Facts of the case:
Petitioner, appointed as toll collector, faced inability to collect toll due to non-installation of electronic FASTag system, compounded by a transport strike. Despite repetitively raising concerns to authorities, no action was taken to rectify the situation, resulting in substantial financial losses for the petitioner.

Findings of Court:
The petitioner is entitled to compensation for non-collection of toll from vehicles equipped with FASTag as well as for losses incurred due to the transport strike. This matter is remitted to the appropriate authority for detailed calculation and determination of losses.

Issues: The main issues include responsibility for toll plaza construction, authority of petitioner to collect toll from FASTag-fitted vehicles, liability for non-collection due to absence of FASTag, and consequences of the transport strike.

Ratio Decidendi: The court held that the inability to collect toll was a result of operational legal requirements, thus the petitioner should not be penalized; further compensation is due for losses sustained during the strike. Respondent authorities are required to conduct an assessment of the losses incurred.

Result: Writ petition disposed of, with directions for determination of compensation.

Table of Content
1. writ petition details and relief sought. (Para 1 , 2)
2. claims made by petitioner regarding fastag and toll collection. (Para 3)
3. court's analysis of contractual obligations and statutory provisions. (Para 4 , 10 , 12)
4. court's perspective on compensation and procedural requirements. (Para 5)
5. respondents' acknowledgment of issues with fastag installation. (Para 6 , 9 , 11)
6. final order regarding authority's action and timeline. (Para 8 , 13)

JUDGMENT :

RAJESH KUMAR, J.

The present writ petition has been filed for the following relief(s):

(i) For issuance of an appropriate writ/order/direction,including Writ of Mandamus, directing Respondent- authorities to pay admitted due and payable amount in respect of Agreement No. 01 RFP of 2023-24 dated 15th September, 2023 (Annexure-3) entered by and between Petitioner and Respondents, after taking into consideration Force Majeure claim of Petitioner in terms of Clause 25 of the Agreement.

(ii) For issuance of further appropriate writ/order/direction, including Writ of Declaration, declaring that action of Respondent on one hand in not making payment of admitted due amount and on the other hand unilaterally extending the tenure of the Agreement is void ab initio; and status of Petitioner after expiry of the tenure of the Agreement is only that of an Agent of Respondent- authority.

2. Arguments of the petitioner on the factual matrix reads as under:

“1. Respondent-Executive Engineer, Road Division, Saraikela published a Notice Inviting Tender dated 03.01.2023 for appointment of User Fee Collection Agency in respect of Adityapur-Kandra Road Section (0.000 to 15,100), 2. Petitioner was declared as the highest bidder and vide Letter No. 798 dated 07.08.2023, it was appointed as User Fee Collection Agency for Kandra Junction Toll Plaza at Adityapur-Kandra Road Section of State Highway No.5.

3. An agreement dated 15th September, 2003 was entered into between Petitioner and Respondent-Executive Engineer, wherein the contract entered with the Petitioner was for a period of two years and was expiring on 03.10.2025.

4. Despite the fact that agreement was expiring on 03.10.2025 and Petitioner, on several occasions, wrote to Executive Engineer for taking over the Toll Plaza, Respondent-Executive Engineer, vide Letter No. 1089 dated 27.09.2025, extended the tenure of the agreement up to 03.04.2026.

5. Petitioner objected to said unilateral extension of tenure, which was contrary to Clause 2(ii) of the Agreement dated 15th September, 2023, which reads as under "-

"(ii) The period of contract shall be Two years. However, in case of urgency, the Authority reserves the right to increase the contract period mutually agreed upon but limited to 6 months."

6. It is an admitted fact that in Adityapur-Kandra Section of State Highway No. 5, there is no facility installed for collection of toll through FASTag.

7. The Toll Plaza, which was handed-over to Petitioner, was not having FASTag system which is compulsory as per Ministry of Road Transport and Highways and Petitioner, immediately upon taking over of Toll Plaza, requested Respondent-State of Jharkhand vide its Letter dated 17th October, 2023, to install FASTag system for toll collection.

8. Again on 25th October, 2023, Petitioner filed reminder representation for installation of FASTag system and it even obtained a tentative quotation for installation of FASTag from a vendor, costing about Rs. 72.00 Lakhs, and requested Respondent-authorities to grant necessary approval of installation of FASTag, but no approval was granted.

9. Ministry of Road Transport and Highways, vide Notification dated 2nd November, 2017 issued under Central Motor Vehicles Rules, 1989, amended Rule 138A of Central Motor Vehicles Rules, 1989, which reads as under:-

"138 A. Fitment of FASTag,-- Categories M and N motor vehicles sold on and after the 1st December, 2017, shall be fitted with FASTag as may be specified by the Central Government, from time to time, by the manufact

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top