IN THE HIGH COURT OF JHARKHAND AT RANCHI
DEEPAK ROSHAN, J.
Mandeepa Enterprises - Appellant
Vs.
The State of Jharkhand - Respondent
W.P. (C) No. 6613 of 2024
Decided On : 20-02-2025
(A) Indian Toll (Jharkhand Amendment) Act, 2002 - Section 2 - Jharkhand Highways Fees (Determination of Rate and Collection) Rules, 2011 - Rule 6 - Contract termination - Petitioner challenged unilateral extension of toll collection contract post expiry, claiming violations of Article 14 and terms of agreement. (Paras 1-22)
(B) Contractual obligations - Court emphasized that contract terms, including extension provisions, must be adhered to, and unilateral demands for payment post-contract are arbitrary. (Paras 17-20)
Facts of the case:
The petitioner, appointed as User Fee Collection Agency, sought relief from toll collection duties after the contract expired on 15th July 2023. Despite requests, the respondent did not relieve the petitioner and demanded remittance for alleged shortfalls.
Findings of Court:
The court found the respondent's actions arbitrary and quashed the demand for toll remittance, affirming the petitioner’s entitlement to operational reimbursements.
Issues: The court addressed the legality of the unilateral extension of the contract and the validity of demands for remittance post-expiry.
Ratio Decidendi: The court held that the petitioner’s status post-contract expiry was that of an agent, entitled to remuneration only for actual collections, and the respondent's demands were illegal.
Result: Writ petition allowed; demands quashed and petitioner to be relieved within eight weeks.
JUDGMENT :
DEEPAK ROSHAN, J.
1. Present writ application has been filed by Petitioner praying therein for following reliefs:-
(a) For issuance of an appropriate writ, order or direction, for quashing/setting aside the Letter No.1472 dated 28th November, 2024 (Annexure-12) issued by the respondent no.4-Executive Engineer Road Division, Saraikela wherein for the period 24th September, 2023 to 27th November, 2024, alleged shortage remittance of toll have been determined in respect of Kandra-Chowka Toll Plaza (Gidibera Toll Plaza) despite the fact that the contract period has already expired on15th July, 2023.
(b) For issuance of further appropriate writ, order or direction, including writ of declaration that action of the respondent-State of Jharkhand in unilaterally extending the period of the contract and/or compelling petitioner to continue the work of collection of toll is wholly illegal, arbitrary and violative of Article 14 of the Constitution of India and is even contrary to the terms and conditions of the agreement being Agreement No. 01/RFP/2021-22 dated 15th July, 2021 (Anneuxre-2);
(c) For issuance of further appropriate writ, order or direction including writ of declaration declaring that after expiry of period of contract pursuant to Agreement No.01/RFP/2021-22 dated 15th July, 2021 (Annexure-2) which expired on 15th July, 2023, the status of the petitioner regarding total toll collection is that of an agent of respondent-State of Jharkhand for deploying specified category of personnel and supervising them for collection of user fee;
(d) For issuance of further appropriate writ, order or direction including writ of declaration, declaring that the respondent-State of Jharkhand, post expiry of the period of contract i.e., from 15th July, 2023 till the date of relieving of the petitioner is only entitled to received payment of actual collection of toll less administrative and operational expenses plus supervision and service charges incurred by the petitioner for collection of toll, especially because respondents, contrary to the terms of agreement, have compelled the petitioner without even any extension order to collect toll from the toll plaza.
(e) For issuance of further appropriate writ, order or direction, directing the Respondent authorities to relieve the Petitioner from toll plaza being Kandra-Chowka Toll Plaza (Giddibera Toll Plaza) and to take handover the said toll plaza from the petitioner, and (f) For issuance of any other appropriate writ(s)/order(s)/ direction(s) as Your Lordships may deem fit and proper in the facts and circumstances of the case.
2. Short facts of the case is that Road Construction Department, being an executive authority under Rule 2(f) of Jharkhand Highways Fees (Determination of Rate and Collection), Rules, 2011 published a Notice Inviting Tender for appointment of User Fee Collection Agency for Kandra- Chowka Toll Plaza, situated at Kandra-Chowka Road, vide N.I.T. dated28.05.2021.
3. Petitioner participated in aforesaid tender and, having been declared as Highest Bidder, was awarded the work of User Fee Collection and an agreement being Agreement No.01/RFP/2021-22 dated 15th July, 2021 was executed between Petitioner and Executing Authority (Road Construction Department) which was valid for a period of two years i.e. up to 15.07.2023.
4. Although contract period expired on 16th July, 2023 and, as per agreement and RFP document, contract could have been extended for a further period of maximum six months with mutual consent of both the parties, Petitioner, as yet, has not been relieved from the work of collection of toll as User Fee Agency.
5. Petitioner, immediately prior to expiry of contract, wrote letter to executing authority for taking over of Toll Plaza from it, but no action was taken by executing authority. In fact, Petitioner has been repeatedly requesting Respondent-authorities to relieve it from toll operation, but, on one hand executing authority has not relieved the Petitioner fro
M.P. Power Management Co. Ltd. v. Sky Power Southeast Solar India (P) Ltd.
The court ruled that unilateral extension of a contract post-expiry is arbitrary, emphasizing adherence to contractual terms and the entitlement of the petitioner to operational reimbursements.
Unilateral modifications to contractual agreements without mutual consent are arbitrary and violate contractual obligations and constitutional rights.
Unilateral changes in contract terms by authorities violate constitutional rights and contractual obligations; agents post-contract are liable only for actual collections minus operational expenses.
The absence of FASTag systems at toll plazas absolves the toll collector from penalties for non-collection of tolls, and compensation for losses due to Force Majeure events must be determined by the ....
Parties to a contract must adhere to its terms despite unforeseen circumstances like force majeure, and disputes arising from such a contract should be resolved through contractual mechanisms, not ju....
Point of Law : Commercial Vehicles - Toll plazas/posts/barriers - Collection of Toll Tax – Whether rights of petitioner is violated - Conduct of parties is governed by the Contract Agreement and the ....
Limited judicial review in contractual matters, and the requirement for the decision-making authority to consider all relevant material before passing an order.
The court emphasizes the necessity of considering exceptional circumstances impacting contractual obligations and mandates competent authority decisions on extension requests.
Toll collection by contractor on fixed bid basis is principal-to-principal, not taxable service; covered by negative list S.66D(h).
A concession period extension under a contract requires compliance with specific procedural conditions, and is not automatic despite recommendations from an independent engineer.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.