IN THE HIGH COURT OF JHARKHAND AT RANCHI
Rongon Mukhopadhyay, Deepak Roshan, JJ.
M/s. XIPHIAS Software Technologies Private Limited - Petitioner
Versus
The State of Jharkhand, through the Chief Secretary - Respondent
W.P.(C) No. 2060 of 2023
Decided On : 26-02-2026
| Table of Content |
|---|
| 1. background of the contractual relationship. (Para 3 , 4 , 5) |
| 2. disputes arising from contract transition and security deposit. (Para 6 , 10 , 12) |
| 3. parties' arguments on forfeiture and extension issues. (Para 13 , 14 , 15) |
| 4. legal analysis on mutual consent and contract obligations. (Para 16 , 17 , 18 , 19 , 20 , 21) |
| 5. discussion on section 74 of the indian contract act. (Para 22 , 23 , 24 , 25 , 26) |
| 6. court's observations on administrative fairness and due process. (Para 27 , 28 , 29 , 30) |
| 7. assessment of the decision-making process and possible malice. (Para 31 , 32 , 33) |
| 8. final findings on contract validity and enforcement. (Para 34 , 35 , 36) |
| 9. emphasis on rule of law and the arbitrary nature of the forfeiture. (Para 40 , 41) |
| 10. conclusion directing refund and interest under unlawful retention. (Para 42 , 43) |
JUDGMENT :
The present adjudication arises under the extraordinary writ jurisdiction, wherein M/s. XIPHIAS Software Technologies Private Limited ("Petitioner") is seeking a Writ of Certiorari to quash an order of forfeiture issued by the Jharkhand Bijli Vitran Nigam Limited (referred to as "JBVNL" or "Respondent No. 2").
2. At its core, this case raises the question whether a state instrumentality can invoke the mechanism of security forfeiture to compel a contractor into providing services beyond a mutually agreed contractual term, and whether it is permissible in exceptional circumstances. An offshoot issue involved is whether such action of extension beyond contract tenure and forfeiture of security deposit require adherence to principles of natural justice.
Background Facts:
3. The relationship between the Petitioner and the Respondent State utility is not a transient one; it is a decade-long professional contract. The Petitioner is a manufacturer and provider of “Any Time Payment” (ATP) machines, which serve as the primary interface for utility bill collection without human intervention.
4. The Petitioner’s journey with the Respondent began in 2011- 2012, following NIT No. 591/PR/11-12, where it was declared the successful bidder for the supply and maintenance of ATP machines. The evolution of the contract demonstrates the Petitioner's performance. Initially appointed for 30 machines, the Petitioner’s operations eventually expanded to 254 ATP machines situated throughout the State of Jharkhand, including several Naxal-affected areas where traditional bill collection was unfeasible.
5. To understand the legal basis of the current dispute, we examine the specific instruments that governed the relationship between the parties. The services were facilitated through three distinct work orders and a consolidated agreement, each specifying terms for the contract period and the security for performance.
| Contractual Instrument | Issuance Date | Reference Number | Scope of Work |
| 1st Work Order | 15.02.2016 | No. 01/C&R | Installation of 69 ATP Machines on BOOM basis |
| 2nd Work Order | 25.10.2016 | No. 04/C&R | Additional 65 ATP Machines on repeat order terms |
| 3rd Work Order | 09.08.2018 | No. 02/C.E. (C&R) | Installation of 120 ATP Machines in phases |
| Formal Agreement | 31.10.2018 | Agreement dtd. 31.10.2018 | Consolidation of 120 machine terms under Master Agreement |
The terms governing these instruments were largely consistent, particularly regarding the "Contract Period." Clause 7 of the 1st Work Order and Clause 8 of the 2018 Agreement stipulated a three-year term, which could be extended for a further two years "as per mutual consent". This requirement of mutuality is a significant legal safeguard, ensuring that neither party could be bound to an indefinite or non-consensual extension of liability. Regarding financial securities, the contracts provided for two distinct mechanisms:
i. Security Deposit (SD): 5% of the contract price, intended to be returned after the successful completion of the three-year period.
ii. Performance Bank Guarantee/Cash Guarantee (PBG/PCG): Originally set at 10% in the 2016 orders, later modified in 2018 to 5% Performance Cash Guarant
Indian Railway Construction Co. Ltd. v. National Buildings Construction Corpn. Ltd.
Suresh Kumar Wadhwa v. State of M.P.
Kailash Nath Associates v. Delhi Development Authority v. DDA
Kranti Associates Pvt Ltd. & Anr. v. Masood Ahmed Khan & Others
A state instrumentality cannot extend a contract unilaterally without mutual consent, and forfeiture of security deposits requires proof of loss and compliance with natural justice principles.
The court affirmed that failure to demonstrate actual loss precludes the forfeiture of security deposits, underscoring the principle that a breach must cause substantial damages to warrant penalties.
Point of law: Not only is the writ jurisdiction of this Court invoked in a purely contractual matter, having no colour of public law and the writ remedy is thus not maintainable.
A party's entitlement to damages in breach of contract cases must correlate with actual damages suffered; security deposits can be refunded when no loss is incurred by the other party.
Forfeiture of earnest money is valid before contract execution if tenderer provides false information, without invoking Sections 73 and 74 of the Contract Act.
The authority can forfeit a mining lease security deposit for non-payment of lease installments under the terms established in the lease agreement, affirming contractual obligations.
Blacklisting a contractor without a fair hearing violates principles of natural justice, rendering such actions invalid, while the termination of the contract for non-compliance with security require....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.