2019 Supreme(Mad) 2645
IN THE HIGH COURT OF JUDICATURE AT MADRAS
SENTHILKUMAR RAMAMOORTHY, J.
The Chief Engineer (Construction), Gauge Conversion, Southern Railway, Chennai & Another - Petitioners
Versus
Sri Swarna & Co., Represented by its Managing Partner, B. Venugopal Reddy & Another - Respondents
O.P. Nos. 87 & 88 of 2014 & 168 of 2015 & 446 of 2016
Decided On : 10-12-2019
Important Points
Subject
Arbitration Law - Contract Disputes
Act Referred
CONTRACT ACT : S.73
GENERAL CONDITIONS OF CONTRACT ACT : Cl.17(2)
Headnote
Arbitration and Conciliation Act - Disputes arising from Railway Contracts - Section 34
Fact of the Case:
Disputes arose between the Contractor and the Railways in relation to the execution of works in connection with the doubling of track between Shoranur and Mangalore and Cannanore-Uppala sections. The Contractor made claims for final bill, refund of security deposit, loss of profit, idle labor, idle machinery, overheads, increased rates for extended work, and labor amenities. The Railways made counter claims in one arbitration. The challenge is limited to the Award in respect of idling of men and machinery, overheads, increased rates for work done during the extended period, loss of profits, and interest.
Finding of the Court:
The court found that the claims for idling of men and materials, overheads, enhanced rates during the extended period, loss of profits, and pre-reference and pendente lite interest were not sustainable. The court set aside the Arbitral Awards partly as regards the amounts awarded against these claims.
Issues: The main issues were the validity of the claims made by the Contractor and the interpretation of the relevant clauses in the General Conditions of Contract (GCC) regarding the submission of claims and the prohibition of interest claims.
Ratio Decidendi: The court held that the claims for idling of men and materials, overheads, enhanced rates during the extended period, loss of profits, and pre-reference and pendente lite interest were not sustainable based on the evidence and the law laid down in previous judgments. The court also interpreted the relevant clauses in the GCC and considered the conflicting judgments on the prohibition of interest claims.
Final Decision: The court allowed the Petitions and set aside the Arbitral Awards partly as regards the amounts awarded against the claims for idling of men and materials, overheads, enhanced rate of 20% during the extended period, loss of profits, and pre-reference and pendente lite interest. No costs were awarded.
For the Petitioners: P.T. Ramkumar (SC), Railways
For the Respondents:S. Raghavan, M. Balakrishna, Advocates
JUDGMENT :
(Prayer in O.P.No.87 of 2014: Original Petition is filed under Section 34 of the Arbitration and Conciliation Act, 1996 to set aside the Award of the second respondent dated 07.03.2013 as amended by further Award dated 25.04.2013 made in relation to disputes arising out of Agreement No.359/CN/1998, dated 08.09.1998 insofar as claims 4 to 7 and pre-reference and pendente lite interest for claim Nos.2, 4 to 7 are concerned.
O.P.No.88 of 2014: Original Petition is filed under Section 34 of the Arbitration and Conciliation Act, 1996 to set aside the Award of the second respondent dated 07.03.2013 as amended by further Award dated 25.04.2013 made in relation to disputes arising out of Agreement No.83/CN/2001, dated 14.03.2001 insofar as claims 3 to 7 and pre-reference and pendente lite interest for claim Nos.2 to 7 are concerned.
O.P.No.168 of 2015: Original Petition is filed under Section 34 of the Arbitration and Conciliation Act, 1996 to set aside the Award of the second respondent dated 07.03.2013 made in relation to disputes arising out of Agreement No.414/CN/1998, dated 16.10.1998 insofar as claims 3 to 7 and pre-reference and pendente lite interest for claim Nos.2 to 7 are concerned.
O.P.No.446 of 2016: Original Petition is filed under Section 34 of the Arbitration and Conciliation Act, 1996 to set aside the Award of the second respondent dated 07.03.2013 made in relation to disputes arising out of Agreement No.106/CN/2001, dated 03.04.2001 insofar as claims 3 to 7 and pre-reference and pendente lite interest for claim Nos.2 to 7 are concerned.)
1. The respondent in all four arbitrations, which were initiated by the first Respondent herein, is the Petitioner herein. For the sake of convenience, the Petitioner herein is referred to as the Railways and the first Respondent as the Contractor in this order. The Railways accepted the bid of the Contractor and issued the respective Letter of Acceptance to the Contractor in respect of 4 related works in connection with the doubling of track between Shoranur and Mangalore and Cannanore-Uppala sections and the scope of work, as between these 4 work orders, was similar but not identical. Disputes arose between the Contractor and the Railways in relation to the execution of these works, which were the subject matter of separate arbitrations before a common Arbitrator, namely, the second Respondent. In each of the arbitrations, the Contractor made claims in respect of the following:
(i) final bill
(ii) refund of security deposit with interest
(iii) loss of profit with interest
(iv) idle labour
(v) idle machinery and equipment
(vi) overheads
(vii) 20% increase in rates for the work that was completed during the extended period
(viii) labour amenities
(ix) costs
2. The Railways made counter claims in O.P. No.87 of 2014 but not in the other arbitrations. Each arbitration was disposed of by a separate Arbitral Award (the Award/s), which is challenged herein. The award of the final bill dues and refund of security deposit (except as regards interest thereon) by the learned Arbitrator is not challenged in any of these Petitions and the challenge is limited to the Award in respect of idling of men and machinery, overheads, 20% increase in rates for work done during the extended period, loss of profits and pre-reference and pendente lite interest. All these petitions were presented in the year 2013, i.e., before the entry into force of the Arbitration and Conciliation (Amendment) Act, 2015. In view of the fact that common issues arise in all these Petitions, they are disposed of by a common order.
3. I heard the learned counsel for the Railways, Mr P.T. Ramkumar, and the learned counsel for the Contractor, Mr. Suryanarayanan. The learned counsel for the Railways commenced his submissions by providing an overview of the nature and scope of the Contracts, which are substantially similar. He pointed out that these Contracts were originally intended to be executed in three months, whereas they were subs