IN THE HIGH COURT OF JUDICATURE AT MADRAS
M. DHANDAPANI, J.
The Chairman-cum-Managing Director Power Grid Corporation of India Ltd. - Petitioner
Versus
The Presiding Officer Central Government Industrial Tribunal -Cum-Labour Court Shastri Bhavan, Chennai and Ors. – Respondents
W.P. No. 1309 Of 2015 And M.P. No. 1 Of 2015
Decided On : 03-04-2025
(A) Industrial Disputes Act, 1947 - Section 10 - Dispute regarding working hours and compensation for extra work - The trial court directed the petitioner to compensate workmen for extra days worked post 20.04.2007, ruling that the 6-day work week for some employees constituted discrimination under Article 14 of the Constitution. (Paras 3, 20, 27)
(B) Limitation - The petitioner argued the claim was time-barred due to a 22-year delay; however, the court found the issue was a continuing wrong and could be raised without limitation. (Paras 4, 24)
(C) Discrimination - The court emphasized that similarly situated employees should not face different working conditions without justification, affirming the need for equitable treatment. (Paras 20, 27)
Facts of the case:
The workmen, previously employed by the petitioner, claimed compensation for additional work done under a 6-day work week system compared to a 5-day work week for others, alleging discrimination. The trial court ruled in favor of the workmen, directing compensation for extra work done after 20.04.2007. (Paras 2, 3)
Findings of Court:
The trial court found that the 6-day work week for some employees was discriminatory and ordered compensation for extra work done, while also considering the delay in raising the issue. (Paras 27, 28)
Issues: The main issues included whether the claim was time-barred and whether the differing work weeks constituted discrimination under Article 14. (Paras 4, 20)
Ratio Decidendi: The court held that the differing work conditions for similarly situated employees violated Article 14, and the claim could be raised despite the delay as it was a continuing wrong. (Paras 20, 27)
Result: Writ petition dismissed, confirming the trial court's order.
ORDER :
(M. DHANDAPANI, J.)
Challenging the award passed by the 1st respondent in and by which amount equal to proportionate pay for the extra days of work done by the workmen was directed to be paid by the petitioner, the present writ petition has been filed.
2. It is the case as evidenced from the chronology of evidence as captured by the trial court that the members of the 2nd respondent Union were employees of the petitioner till 16.08.1991 and, thereafter, their services were transferred to the 3rd respondent and they are working with the 3rd respondent. The working hours of the petitioner was from 0900 to 1730 hours across the country and that the 2nd and last Saturdays were closed holidays along with all Sundays and other notified holidays. In the year 1985, the five day week system was introduced by the Government of India, which was adopted and implemented by the petitioner and all the rules and regulations of the petitioner were followed suit by the 3rd respondent as well. Before following the five day week pattern, the petitioner was following six day week for all its officers, irrespective of the status of the office. Only at the sub-stations, shift duty was followed in order to maintain power generation, transmission and distribution system, which was adopted by the 3rd respondent as well. It is the case of the workmen that the persons, who are employed in a five day work place are working 40 hours a week, while the persons employed in a six day work place are working 48 hours a week, thereby, the employees in a six day week system, do additional 52 days work in a year, which is discriminatory and, therefore, the persons, who are employed in a six day work place, should be compensated for the additional work done by them. Therefore, the industrial dispute was occasioned at the instance of the 2nd respondent herein.
3. Upon reference of the dispute to the trial court, the same was taken up on file and on behalf of the 2nd respondent herein, W.W.1 to 4 were examined and Exs.W-1 to W-24 were marked. On the side of the petitioner herein/1st respondent therein, M.W.1 and 2 were examined and Exs.M-1 to M-23 were marked. On analysing the materials, both oral and documentary, the trial court allowed the dispute and directed the petitioner herein to compensate the workmen employees of the projects and sites, except those working in shifts, who were in service on 2.8.1985 and continued to be in service as on 20.04.2007 by paying the amount equal to proportionate pay for the extra days of work done by them after 20.04.2007, within the time prescribed failing which the amount will carry interest at 9% p.a. Aggrieved by the said order, the present writ petition has been filed.
4. Learned counsel appearing for the petitioner, at the outset submitted that the dispute is hopelessly time barred by limitation, as it has been raised almost after a quarter of a century with no explanation being given for this inordinate delay of 22 years.
5. It is the further submission of the learned counsel that the working hours in the Corporate Office/Regional Officer prior to the issuance of the circular dated 2.8.1985 vis-a-vis the project office is entirely different as the Corporate Office/Regional Officer were working 6 days a week with 2nd and 4th Saturdays as off days every month unlike the project offices, which were functioning six days working without any off days on 2nd and 4th Saturdays. Thus there was a distinct and different working hours between Corporate Office/Regional Office and Project/site Office since inception of the 3rd respondent and, therefore, the inference that the employees at Project/Site Office were having holidays on two Saturdays prior to introduction of 5 day week system is erroneous.
6. It is the further submission of the learned counsel that the Memorandum of Conclusion dated September, 1985, had already concluded the demand between the trade unions and the 3rd respondent and the issue not having been diligently raised
Discrimination in working conditions between similarly situated employees violates Article 14 of the Constitution, and claims regarding continuing wrongs can be raised despite delays.
A workman must demonstrate that an industrial dispute remains alive despite delays; failure to do so renders the dispute stale and unenforceable.
The court established that individuals classified as supervisors under the Factories Act are not entitled to overtime benefits as defined for workers, impacting their claims for such allowances.
Labour Court has held against the workman on the basis that the documents like pay sleep, muster roll etc. are not produced. But, at this juncture, it is require to peruse the oral evidence of the wo....
The interpretation of 'continuous service' under Section 25-F of the Industrial Disputes Act includes all days worked, and any termination without following due process is deemed illegal.
In a case where Section 25-F of the Act applies the workman is bound to prove that he had been in continuous service of 240 days during twelve months preceding the order of termination; in a case whe....
In absence of any evidence produced by the petitioner workman establishing that he had worked under the Respondent continuously for 240 days and, coupled with the fact that the industrial dispute has....
The Civil Court lacks jurisdiction to interpret awards without prior recourse to designated labor tribunals under S.36A of the Industrial Disputes Act.
Section 33C(2) of the Industrial Disputes Act, 1947, permits recovery of money only if the entitlement is pre-existing and previously adjudicated; employees must demonstrate a pre-existing right and....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.