SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Mad) 247

IN THE HIGH COURT OF JUDICATURE AT MADRAS
N. Anand Venkatesh, J.
Brandavan Food Products - Applicant
Versus
Southern Railway, through its General Manager - Respondent
Arbitration Application No. 1296 of 2025 and Original Application Nos.907, 908 and 909 of 2025
Decided On : 10-02-2026

Advocates Appeared:
For the Applicant : Mr.D.Jasmeet Singh, Mr.T.N.C.Kaushik
For the Respondent: Mr.Ar.L.Sundaresan, Additional Solicitor General of India, assisted by Mr.V.Chandrasekaran, Senior Panel Counsel – UOI

The court upheld that ongoing arbitration processes require interim protections for a contractor against adverse actions by the railway, emphasizing the importance of contractual compliance and existing precedent.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 9(2)

(D) and (E), Order XIV Rule 8 of O.S. Rules - Interim injunction sought by a railway contractor against termination notice by Southern Railway - Court addresses previous litigations and ongoing arbitration process, emphasizing the arbitration clause and granting interim relief to the applicant. (Paras 2, 12, 15)

(B) Arbitration - Parties agreed to refer disputes to a Sole Arbitrator allowing consolidation of claims. (Paras 12, 14, 16)

Facts of the case:
The applicant, a railway contractor, sought an injunction against termination of their contract for Yatri Seva services, alleging violations of contract terms by the Southern Railway.

Issues: The primary issue was whether the respondent's actions violated the terms of the contract and whether interim relief was warranted pending arbitration.

Findings of Court:
The Court found that a prima facie case for interim relief existed and the applicant had historically maintained satisfactory service that exceeded contractual thresholds.

Ratio Decidendi: The court determined that ongoing arbitration processes necessitated protection of the applicant's interests through an interim injunction prohibiting adverse actions by the Southern Railway.

Result: Applications disposed of with the dispute referred to a Sole Arbitrator for resolution.

Table of Content
1. dispute arises from compliance with interim orders. (Para 9)
2. dispute referred to sole arbitrator following parties' consent. (Para 12 , 13)
3. interim orders continue pending arbitration outcome. (Para 16)

ORDER :

N. Anand Venkatesh, J.

When these applications came up for hearing on 20.08.2025, the following order came to be passed by this Court:

“These applications have been filed seeking for the following reliefs :

(a) seeking for an order of interim injunction to restrain the respondent from taking any adverse action against the applicant pursuant to the notice dated 30.05.2025 issued by the respondent;

(b) seeking for an order of interim injunction to restrain the respondent from taking any steps which would be prejudicial to the rights and interest of the applicant flowing from the Standard Bid Document of Tender No.SR/YSA/02/2024 for provision of Yatri Seva Anubanth (YSA) services for 6 pairs of Vande Bharat Trains of the Southern Railway pursuant to the letter of acceptance dated 15.04.2024 issued by the respondent in faovur of the applicant;

(c) seeking for an order of interim stay of operation of the impugned notice dated 30.05.2025 bearing No.SRHQ0COMM/32/2025 (E.544143) issued by the respondent.

2. The applicant is a railway contractor and engaged in the business of providing YSA services for six Vande Bharat trains operated by the respondent. According to the applicant, arbitrarily and in violation of the terms and conditions of the contract, the respondent has issued notice dated 30.05.2025 to the applicant threatening to terminate the contract on the ground that services provided by the applicant to the six Vande Bharat trains are unsatisfactory. The applicant claims that only in accordance with the terms and conditions of the contract, they have been providing services to the six Vande Bharat trains and also claims that the passenger feedback given in respect of their services has been impeccable. In support of the applicant's contention, the learned Senior Counsel appearing for the applicant drew the attention of this Court to the passenger feedback recorded by the respondent with regard to the services rendered by the applicant for the six Vande Bharat trains and would submit that the applicant's performance has exceeded the threshold limit fixed by the respondent under the contract awarded to the applicant. The tabular column relied upon by the learned Senior Counsel for the applicant with regard to the applicant's performance is reproduced hereunder :

3. The threshold limit prescribed under the contract awarded to the applicant is 2.00. As seen from the tabular column, the applicant has exceeded the threshold limit. Relying upon the same, the applicant categorically contends that arbitrarily and in violation of the terms and conditions of the contract, the respondent issued the notice dated 30.05.2025 to the applicant threatening to terminate the contract. The learned Senior Counsel for the applicant also submits that earlier, the applicant had approached this Court by filing applications under Section 9 of the Arbitration and Conciliation Act , 1996, seeking to protect their interest pending arbitration when the respondent had threatened to terminate the contract on the ground that the applicant did not disclose the pending criminal cases while submitting their tender application to the respondent. In the said applications, earlier, this Court had granted an order of interim injunction in favour of the applicant restraining the respondent from blacklisting the applicant and subsequent to which, the parties have already gone for arbitration in accordance with the arbitration clause contained in the general conditions of the contract applicable to the railway and the arbitral Tribunal has already been constituted and the arbitration is in progress.

4. The learned Senior Counsel for the applicant would submit that since the respondent may contend that the cause of action for filing these applications

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top