IN THE HIGH COURT OF JUDICATURE AT MADRAS
N. Anand Venkatesh, J.
Brandavan Food Products - Applicant
Versus
Southern Railway, through its General Manager - Respondent
Arbitration Application No. 1296 of 2025 and Original Application Nos.907, 908 and 909 of 2025
Decided On : 10-02-2026
| Table of Content |
|---|
| 1. dispute arises from compliance with interim orders. (Para 9) |
| 2. dispute referred to sole arbitrator following parties' consent. (Para 12 , 13) |
| 3. interim orders continue pending arbitration outcome. (Para 16) |
ORDER :
N. Anand Venkatesh, J.
When these applications came up for hearing on 20.08.2025, the following order came to be passed by this Court:
“These applications have been filed seeking for the following reliefs :
(a) seeking for an order of interim injunction to restrain the respondent from taking any adverse action against the applicant pursuant to the notice dated 30.05.2025 issued by the respondent;
(b) seeking for an order of interim injunction to restrain the respondent from taking any steps which would be prejudicial to the rights and interest of the applicant flowing from the Standard Bid Document of Tender No.SR/YSA/02/2024 for provision of Yatri Seva Anubanth (YSA) services for 6 pairs of Vande Bharat Trains of the Southern Railway pursuant to the letter of acceptance dated 15.04.2024 issued by the respondent in faovur of the applicant;
(c) seeking for an order of interim stay of operation of the impugned notice dated 30.05.2025 bearing No.SRHQ0COMM/32/2025 (E.544143) issued by the respondent.
2. The applicant is a railway contractor and engaged in the business of providing YSA services for six Vande Bharat trains operated by the respondent. According to the applicant, arbitrarily and in violation of the terms and conditions of the contract, the respondent has issued notice dated 30.05.2025 to the applicant threatening to terminate the contract on the ground that services provided by the applicant to the six Vande Bharat trains are unsatisfactory. The applicant claims that only in accordance with the terms and conditions of the contract, they have been providing services to the six Vande Bharat trains and also claims that the passenger feedback given in respect of their services has been impeccable. In support of the applicant's contention, the learned Senior Counsel appearing for the applicant drew the attention of this Court to the passenger feedback recorded by the respondent with regard to the services rendered by the applicant for the six Vande Bharat trains and would submit that the applicant's performance has exceeded the threshold limit fixed by the respondent under the contract awarded to the applicant. The tabular column relied upon by the learned Senior Counsel for the applicant with regard to the applicant's performance is reproduced hereunder :

3. The threshold limit prescribed under the contract awarded to the applicant is 2.00. As seen from the tabular column, the applicant has exceeded the threshold limit. Relying upon the same, the applicant categorically contends that arbitrarily and in violation of the terms and conditions of the contract, the respondent issued the notice dated 30.05.2025 to the applicant threatening to terminate the contract. The learned Senior Counsel for the applicant also submits that earlier, the applicant had approached this Court by filing applications under Section 9 of the Arbitration and Conciliation Act , 1996, seeking to protect their interest pending arbitration when the respondent had threatened to terminate the contract on the ground that the applicant did not disclose the pending criminal cases while submitting their tender application to the respondent. In the said applications, earlier, this Court had granted an order of interim injunction in favour of the applicant restraining the respondent from blacklisting the applicant and subsequent to which, the parties have already gone for arbitration in accordance with the arbitration clause contained in the general conditions of the contract applicable to the railway and the arbitral Tribunal has already been constituted and the arbitration is in progress.
4. The learned Senior Counsel for the applicant would submit that since the respondent may contend that the cause of action for filing these applications
The court upheld that ongoing arbitration processes require interim protections for a contractor against adverse actions by the railway, emphasizing the importance of contractual compliance and exist....
The main legal point established in the judgment is the court's authority to appoint a sole arbitrator based on the arbitration clause in the contract and the respondent's failure to send a panel of ....
Court upheld the Arbitral Tribunal's decision based on the principle that interference is limited to cases of perversity, with findings deemed a plausible view of the evidence.
Disputes arising from a construction contract are arbitrable, and failure to follow conciliation procedures does not bar the appointment of an arbitrator.
The court upheld the arbitral award allowing refund of liquidated damages due to the interpretation of contract clauses, confirming limited grounds for interference under arbitration law.
The limited scope of interference under Section 34 of the A&C Act of 1996 and the requirement for an arbitral award to be suffering from patent illegality for it to be set aside.
An Arbitral Tribunal under the Arbitration and Conciliation Act cannot grant interim orders that effectively render final decisions on substantive claims, as this exceeds its jurisdiction.
The main legal point established in the judgment is the wide scope of powers of the court to grant interim measures under Section 9 of the Arbitration and Conciliation Act, 1996, and the strict compl....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.