IN THE HIGH COURT OF DELHI
Siddharth Mridul, Anup Jairam Bhambhani, JJ.
Union of India - Appellant
Versus
Annavaram Concrete Pvt. Ltd. - Respondent
FAO(OS) (COMM) 96 of 2020 & CM. Appl. 18980 of 2020
Decided On : 31-08-2021
| Table of Content |
|---|
| 1. arbitral award upheld by court (Para 1 , 2 , 3 , 4 , 5) |
| 2. arguments on contractual obligations (Para 6 , 7 , 8) |
| 3. court’s reasoning on verification of award (Para 9 , 10 , 11 , 12 , 13 , 14 , 15) |
| 4. conclusion on appeal and directions given (Para 16 , 17 , 18 , 19 , 20) |
JUDGMENT
Anup Jairam Bhambhani, J. The present appeal under section 13 of the Commercial Courts Act 2015 read with section 10 the Delhi High Court Act 1966 and section 37 of the Arbitration & Conciliation Act 1996 (`A&C Act') has been filed by the Union of India, Ministry of Railways and North Eastern Railways (`Railways') impugning judgment dated 27.02.2020 rendered by the learned single Judge of this court in O.M.P. (COMM) No. 112/2020 (`impugned judgment'), whereby the learned single Judge has upheld arbitral award dated 08.02.2011 (`arbitral award') made by the learned Sole Arbitrator in arbitral proceedings between the Railways and M/s Annavaram Concrete Pvt Ltd., Hyderabad (`Annavaram').
2. The Railways had filed a petition under section 34 of the A&C Act challenging arbitral award dated 08.02.2011; in which award the learned Sole Arbitrator had directed the Railways to refund to Annavaram the sum of Rs.1,22,38,125/-, which had been deducted/withheld by the Railways as `liquidated damages' imposed upon Annavaram for alleged breach of the terms and conditions of a tender bearing No. CS 160/2007, pursuant to which a Letter of Acceptance dated 15.09.2008 (`1st LoA') was issued by the Railways to Annavaram for supply of 10000 Pre-Stressed Concrete Sleepers (`sleepers') by 14.01.2009.
3. By the impugned judgment, the learned single Judge has upheld the arbitral award and has also awarded interest for the delay in payment of the awarded sum.
4. Briefly, disputes arose between the Railways and Annavaram in relation to alleged non-performance and non-compliance by Annavaram with the terms of the 1st LoA. As per the record, after issuance of the 1st LoA, vidi its letter dated 22.12.2008 Annavaram requested the Railways for an additional order, representing that their capacity was to manufacture 25000 sleepers per month; whereupon vidi a Second Letter of Acceptance dated 27.01.2009 (`2nd LoA') the Railways ordered an increased quantity of 150000 (one lac fifty thousand) sleepers to be supplied by Annavaram by 14.07.2009, which order was accepted by Annavaram. It is the Railways' contention that Annavaram failed to supply even a single sleeper within the stipulated time; nor did they obtain any extension of time for making such supply; whereupon, the contract comprised in the 1st LoA and 2nd LoA lapsed by efflux of time on 14.07.2009. Consequently, it is the contention of the Railways, that as per IRS Condition 0702, the Railways imposed liquidated damages to the tune of Rs.1,22,38,125/- (Rupees One Crore Twenty-two Lacs Thirty-eight Thousand One Hundred and Twenty-five Only) upon Annavaram on 27.05.2009. It is further contended that on grounds of non-performance, on 08.04.2010 the Railways also terminated the contract with Annavaram.
5. Disputes having arisen between the parties, on 21.06.2010 the learned Sole Arbitrator came to be appointed and entered upon reference. Subsequently he rendered the arbitral award awarding Rs.1,22,38,125/- (Rupees One Crore Twenty-two Lacs Thirty-eight Thousand One Hundred and Twenty-five Only) in favour of Annavaram and against the Railways, which sum was directed to be refunded within 03 months from the date of the award. For completeness, it may be mentioned that the Railways had also preferred a counter-claim in the sum of Rs.10,00,000/- (Rupees Ten Lac Only) against Annavaram in the arbitral proceedings.
6. It is the contention of the Railways that the 1st LoA was amended by the 2nd LoA, whereby, apart from increasing the quantity of sleepers to be supplied by Annavaram, clause 1.0 and clause 1.1 were amended and a new clause 1.2 was inserted in the terms and conditions of the contract. Clauses 1.1 and
The court upheld the arbitral award allowing refund of liquidated damages due to the interpretation of contract clauses, confirming limited grounds for interference under arbitration law.
Point of Law : Arbitration - Arbitral award - It is evident that in case an arbitral award has been confirmed by court under Section 34 and by the court in an appeal under Section 37, this Court must....
The limited scope of interference under Section 34 of the A&C Act of 1996 and the requirement for an arbitral award to be suffering from patent illegality for it to be set aside.
The court affirmed that an Arbitrator retains authority to grant damages despite contractual clauses seeming to prohibit such claims, provided the termination of the contract is deemed illegal.
The court upheld the learned Single Judge's ruling that claims not disclosed under the contract clauses and issues related to 'No Claim' certificates are non-recoverable, emphasizing the importance o....
The court emphasized the limited grounds for setting aside an arbitral award under Section 34 of the A&C Act and the lack of power to modify, revise, or vary the terms of an award under this section.
An arbitral tribunal cannot adjudicate on claims outside the scope of the arbitration agreement, and awards violating explicit contractual terms are subject to being set aside under Section 34 of the....
The courts have a limited scope of interference under Section 34 and 37 of the Arbitration Act, and the Arbitral Tribunal's detailed consideration of evidence and claims is final.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.