SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Mad) 5488

IN THE HIGH COURT OF JUDICATURE AT MADRAS
N.ANAND VENKATESH, J.
M/s. Y.Chinna Reddy, rep.by its Managing Partner Mr.Y.Chinna Reddy – Appellant 
Versus
The Union of India, rep.by the General Manager, Southern Railway – Respondent 
Original Petition No.906 of 2016
Decided On : 24-9-2025

Advocates:
Advocate Appeared:
For the Petitioner: Mr.Amalraj S.Penikilapatti
For the Respondents: Mr.P.T.Ramkumar

Court upheld the Arbitral Tribunal's decision based on the principle that interference is limited to cases of perversity, with findings deemed a plausible view of the evidence.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Challenge against arbitral award - Petitioner entered into a contract for construction with Southern Railway, work halted due to disputed payment issues and alleged lack of funds - Arbitral Tribunal rejected most claims, awarding only claims for certain payments - The Tribunal concluded both parties contributed to the contract's failure - Court upheld Tribunal's findings, stating it did not suffer from perversity or manifest illegality, and the decisions on claims were reasoned and plausible. (Paras 3, 11, 36, 40)

(B) Arbitration - Standard of Review - The court's role is limited to checking for arbitrariness or irrationality in Tribunal's decisions; a possible view taken by the Tribunal must be respected. (Paras 37, 38)

Facts of the case:
The petitioner, awarded a contract for modernization, halted work citing non-payment while the Southern Railway claimed adequate funds were available. Disputes escalated leading to contract termination amidst blame from both sides. Claims made included damages for missed profits, non-fulfilled obligations, and various payments for work done, but were mostly rejected by the Tribunal. (Paras 1, 4, 8)

Findings of Court:
The Tribunal's awards were upheld, concluding inadequate evidence for profit claims, and highlighting responsibility on both parties. The original petition challenging the award did not present grounds for interference. (Paras 32, 46)

Issues: The key issues included determination of liability for contract non-completion and sufficiency of evidence for claims made by the petitioner. (Paras 10, 18, 34)

Ratio Decidendi: The court emphasized the role of the Tribunal in fact-finding and the limited basis for judicial review under Section 34, affirming that where the Tribunal had taken a possible view, the court must defer to that conclusion. (Paras 38, 40)

Result: Original petition dismissed.

Table of Content
1. factual background of the case concerning contract disputes. (Para 1 , 3)
2. arguments regarding the arbitral award and claims raised by the petitioner. (Para 4 , 5)
3. court's analysis of claims and responses from both parties. (Para 6 , 8 , 9)
4. court’s reasoning regarding the arbitral tribunal's findings. (Para 7 , 12 , 24)
5. legal principles regarding loss of anticipated profits and related claims. (Para 28 , 29)
6. final ruling to dismiss the original petition. (Para 46)

ORDER :

This petition has been filed under Section 34 of the Arbitration and Conciliation Act, 1996 (for short, the Act) against the award dated 29.8.2016 passed by the Arbitral Tribunal.

2. Heard both.

3. The case of the petitioner is as follows :

(i) The respondent - Southern Railway called for tenders for modernisation of Perambur Loco Works - proposed construction of bogie repair shop, air brake and miscellaneous shed, service building and allied works. The petitioner participated in the tender and their tender was accepted vide letter of acceptance dated 21.3.2014, pursuant to which, an agreement was executed between the petitioner and the Southern Railway on 12.6.2014 for a total sum of Rs.10.72 Crores with the date of completion as 20.3.2015.

(ii) The petitioner started the work after taking necessary clearance from the workshop authorities. Some new items connected with earth work were also executed by the petitioner though they were not a part of the agreement and it was done purely on the request made by the Southern Railway. Later, the Southern Railway could not pay the money for the work that was done by the petitioner for want of funds. Even though the petitioner repeatedly requested the Southern Railway to arrange for funds and make payment, the same was not done.

(iii) Since this issue was not resolved by the Southern Railway, the petitioner stopped the work and requested the Southern Railway to foreclose the contract and compensate for the losses suffered by the petitioner. Since the Southern Railway denied the claims, the petitioner filed a petition in O.P.No. 809 of 2014 before this Court. Subsequently, the contract was also terminated by the Southern Railway on 24.1.2015 since the petitioner did not restart the work. On 10.4.2015, the said petition was allowed by this Court, pursuant to which, the Arbitral Tribunal was constituted.

(iv) The petitioner made the following claims before the Arbitral Tribunal :

S.No.Description of Claim
Claim 1Declaration that the railway had called for Tenders and awarded the instant contract without ensuring the specific allotment and availability of funds
Claim 2Declaration that the claimant was prevented from executing and completing the contract works due to the railway's inability to pay for the work done.
Claim 3Declaration that the contract must be finalised without any liability (like LD, penalty, forfeiture of SD. Performance Guarantee etc) on the claimant
Claim 4Damages for the loss in anticipated profits @ 15% of the value of unexecuted work (as per Sec-73 of the Indian Contract Act) due to failure of the project on account of railway's latches and failures. (i.e. 15% of unexecuted work for Rs.10,52,00,000/-)
S.No.Description of Claim
Claim 5Damages for loss in turnover and good-will (@5% of the unexecuted contract value).
Claim 6Payment of the bill amount under CC-I & Part.
Claim 7Payment of Final Bill for earthwork with lead and other works (but measurements yet to be recorded).
Claim 8Refund of the Performance Guarantee.
Claim 9Refund of the EMD
Claim 10Payment for the cost of Drawing, Designing, Planning, etc preparation and proof checking as per conditions of the Agreement.
Claim 11Lab Testing charges Aggregate, Cement, RMC Design-Mix etc.
Claim 12Idle payment for the following: (1) Site Engineer (1 No. per month Rs.30,000/- for six months) (2) Site in charge (1 No. per month Rs.25,000/- for 6 months) (3) Supervisor (1 No. per month Rs. 15,000/- for 6 months)
Claim 13Idling of workmen - skilled la

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top