2026 Supreme(Mad) 312
IN THE HIGH COURT OF JUDICATURE AT MADRAS
S.M.SUBRAMANIAM, C.KUMARAPPAN, JJ.
State Industries Promotion Corporation of Tamil Nadu Limited – Appellant
Versus
M/s. A.S. Carriers Private Limited – Respondent
W.A. Nos. 920, 2043 of 2023, C.M.P. Nos. 9197, 17339 of 2023
Decided On : 06-02-2026
Important Points
Subject
Administrative Law - Writ Appeal
Act Referred
Headnote
(B) Lease Agreement - Enforcement of terms; violations of lease conditions allow for recovery of charges; the agreement’s clear provisions should be observed in enforcing contract obligations. Recovery of sub-leasing charges is justified based on established terms. (Paras 8, 19, 21)
Facts of the case:
SIPCOT challenges a Writ Court order, arguing a lessee violated lease terms by sub-leasing properties resulting in demands for sub-leasing charges denied by the respondent.
Findings of Court:
SIPCOT is entitled to recover sub-leasing charges under clause 39 of the lease agreement due to conditions allowing for stipulated enforcement actions. Public interest considerations reinforce this recovery.
Issues: Whether SIPCOT can recover sub-leasing charges from the lessee based on stipulated lease violations.
Ratio Decidendi: The Court finds that the terms of the lease adequately enable SIPCOT to claim sub-leasing charges as public interest must supersede private contracts, ensuring no unfair advantage results against state resources.
Result: W.A.No.2043 of 2023 is allowed; the writ order is set aside.
For the Appellants : R. Viduthalai, K. Palaniappan
For the Respondent: J.V. Niranjan
JUDGMENT :
S.M. SUBRAMANIAM, J.
1. Under assail is the Writ Order dated 26.08.2022 passed in W.P.No.5446 of 2016. State Industries Promotion Corporation of Tamil Nadu Limited (hereinafter referred as “SIPCOT”) is the appellant before this Court.The respondent / Company instituted writ proceedings, challenging the demand made by the appellant vide Demand Letter dated 28.04.2014 to pay sub-leasing charges in respect of sub-leases made by the respondent / Company with third parties.
2. Facts in brief:
2.1. Vast extent of private lands admeasuring 17 acres and 64 cents (more than 7 lakhs sq.ft.) from various land owners were acquired for developing Industrial Park by Government of Tamil Nadu and it was allotted to SIPCOT for developing Industrial Establishments. Industrial plots are allotted to persons aspiring to develop industries and allotment orders were issued and such allotments culminated into lease agreement.
2.2. In the present case, order of allotment was passed in favour of the respondent / Company on 15.03.2005 by SIPCOT, allotting 17.64 acres for a period of 99 yeas for an annual rent of Rs.1 agreed. Pursuant to allotment, a Lease Deed was entered into between the parties on 08.07.2005. As per the terms and conditions, respondent / Company was permitted to establish modern warehousing, logistic facilities and value added services. respondent / Company constructed industrial sheds or buildings and thereupon executed sub-lease agreement in favour of third parties to utilize buildings or sheds for the purpose of warehousing, logistic and value added services.
2.3. SIPCOT found that respondent / Company committed certain violations of terms and conditions of lease agreement, by sub-letting the premises for developing industrial or manufacturing unit or for other purposes, which is impermissible in terms of the lease agreement. SIPCOT demanded sub-leasing charges from the respondent / Company, since sub-leasing charges are being recovered from other lessees in the Industrial Park. Near about 50 Lessees are paying sub-leasing charges to SIPCOT and the respondent / Company, since disputed, a Demand Letter was issued, which came to be challenged in a writ proceedings.
2.4. Writ Court allowed the writ petition mainly on the ground that there is no specific clause to demand or recover sub-leasing charges. Therefore, the impugned Demand Letter is untenable. Writ Court held that in the absence of any specific agreement between the parties in the Lease Deed, SIPCOT / appellant herein is not empowered to recover sub-leasing charges. Other facts regarding usage of warehouse by the respondent / Company are not seriously contested between the parties. Though certain violations are brought to the notice of this Court on behalf of the appellant, since they have not initiated any action against those violations, if any committed by the respondent / Company, it is unnecessary for this Court to consider those issues or violations in the present writ appeal.
3. Submission of SIPCOT / Appellant :
3.1. Mr.R.Viduthalai, learned Senior Counsel assisted by Mr.K.Palaniappan, learned counsel for the appellant would mainly rely on the terms and conditions agreed between the parties in the lease agreement. Learned Senior Counsel, by relying on Clauses 11, 15, 27, 31, 39 and 42(b) in the agreement, would urge this Court that SIPCOT is entitled to recover sub-leasing charges. Though SIPCOT reserves its right to initiate action in respect of other violations committed by the respondent / Company, at present, SIPCOT is claiming only sub-leasing charges in terms of the lease agreement. 50 other Lessees are regularly paying sub-leasing charges. While so, respondent / Company alone is refusing to pay by wrongly stating that there is no specific clause in the agreement.
3.2. Learned Senior Counsel drew the attention of this Court with reference to the sub-lease agreement entered into between the respondent / Company and third parties, which would show that it is only