IN THE HIGH COURT OF JUDICATURE AT MADRAS
P.T.ASHA, J.
M/s. Progen Renewables Ltd. - Appellant
Vs.
The Power Grid Corporation - Respondent
W.P.No.2278 of 2026 and W.M.P.No.2521 of 2016
Decided On : 09-03-2026
| Table of Content |
|---|
| 1. factual basis for the writ petition. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8) |
| 2. respondents' justification of actions. (Para 9 , 10 , 11 , 12 , 13 , 14) |
| 3. arguments presented by both parties. (Para 15 , 16 , 17 , 18) |
| 4. court's deliberations on applicable law. (Para 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29 , 30) |
| 5. conclusion: writ petition is dismissed. (Para 31) |
ORDER :
P.T.ASHA, J.
The above writ petition is filed seeking a mandamus to forbear the respondents 1 to 3 from erecting Transmission Towers / Lines in the petitioner’s lands bearing S.F.No.351/1 and 353/2A Kasthurirengapuram, Part I Village, Rathapuram Taluk,, Tirunelveli District which is against the 6th respondent’s Load Flow Study dated 27.11.2025 and without following the provisions of the Electricity act, 2003 and the Indian Telegraphic Act, 1885.
Petitioner’s case:
2. It is the contention of the petitioner that they are a Private Limited Company engaged in the production of wind energy and the supply of power to its group captive consumers within the State of Tamil Nadu. As the State of Tamil Nadu has more number of sunny days and is a forerunner in solar power generation and other non- conventional energy source, the petitioner, with a view to generating this green power, had made an application dated 03.05.2025 to the 6th respondent for establishing a 25 MW Solar Power Plant under the preferential tariff scheme for captive consumption. This request was approved by the 6th respondent and the petitioner was directed to pay the applicable charges, which included the registration fee, Load Flow Study Charges, refundable security deposit etc., The petitioner would submit that the security deposit was collected to ensure that a Solar Power Generator (SPG) diligently pursues the project, commissions it within the stipulated time and to eliminate and discourage players who were not serious about the project from blocking the power evacuation facility indefinitely. The petitioner would submit that, in all, a sum of Rs.25,00,000/- was paid.
3. Thereafter, the petitioner-Company had purchased the subject property under a registered Sale Deed dated 23.06.2025. The 6th respondent had conducted a detailed Load Flow Study and issued a report dated 21.11.2025 stating that the petitioner’s proposed 25 MW Solar Power Plant could be connected to the 110/33-11 KV Radhapuram Sub Station. The petitioner has also commenced the construction in full swing.
4. While so, to the absolute shock and surprise of the petitioner, the 3rd respondent had issued a notice dated 17.07.2025 stating that it intends to install 400 KV Transmission Lines in Survey Numbers 351/1 and 353/2 which are patta lands in which 25MW Solar Power Plant is under construction. The officials of the 3rd respondent had started measuring the land, fixed the boundaries in the petitioner’s land and they continued the measurement process for the purpose of stringing 400 KW Transmission lines from one tower to another, thereby marking the entire land not fit for use.
5.The 3rd respondent had proposed to erect 400 KV transmission lines from Kudankulam Nuclear Power Project Units 3 and 4 to Tuticorin GIS. To this, the petitioner had raised his objections on 18.07.2025. However, the same has not been considered by the 3rd respondent either in the form of a reply or by passing any order. The 3rd respondent, without even appreciating the petitioner’s objections, is compelling the petitioner to permit them to install the basement for the HT Towers.
6. Although the petitioner had approached the 3rd respondent in person seeking details of the project and a copy of its original sketch, no response was received from the 3rd respondent. That apart, the 3rd respondent refused to reconsider the decision. The petitioner also reliably understands that the respondents have deviated from the route of the HT lines in order to avoid and accommodate certain other lands and as a result of such deviation, the HT lines are now s
Power Grid Corporation of India Ltd. v. Century Textiles and Industries Ltd.
The statutory framework permits the installation of power transmission lines on private land despite objections, with the authority required primarily to consider compensation rather than block the p....
The court upheld the authority of the licensee to lay transmission lines under public interest, dismissing the petitioner's objections as untimely and unfounded.
The authority under the Indian Telegraph Act has the right to lay transmission lines on private property, prioritizing public interest and following due process, including compensation for any damage....
The court upheld the validity of the District Magistrate's order permitting the laying of a transmission line, affirming that adequate notice and opportunity were provided to affected farmers, thus a....
The court affirmed the legality of the procedures for erecting transmission towers and highlighted public interest in electricity provision over private landowner objections.
The conferment of powers of Telegraph Authority under Section 164 of the Electricity Act does not require a hearing of objections from affected persons before exercising powers under the Telegraph Ac....
The Electricity Act and Indian Telegraph Act authorize the placement of transmission lines without prior notice, as long as procedural fairness is upheld regarding objections and compensation.
Statutory authorities can erect high-tension electricity towers on private land without prior consent, provided they ensure minimal damage and compensate affected parties, in adherence to public inte....
No prior notice required for erecting transmission lines under Electricity Act; compensation is the only remedy for property owners.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.