IN THE HIGH COURT OF JUDICATURE AT MADRAS
Krishnan Ramasamy, J.
Anant Mandgi - Petitioner
Versus
Union of India, Ministry of Road Transport and Highways, Rep by its Secretary, No.1, Parliament Street, New Delhi - Respondent
W.P.Nos.29753 & 29755 of 2019 & W.M.P.Nos .29654, 29885, 29886, 29883 of 2019, 7600 & 7592 of 2025
Decided On : 26-02-2026
| Table of Content |
|---|
| 1. petitioner's objections and arguments (Para 3 , 4) |
| 2. legal requirements for environmental clearance (Para 10) |
| 3. final decision and dismissal of petitions (Para 13) |
ORDER :
Krishnan Ramasamy, J.
These writ petitions have been filed challenging the impugned Notification dated 08.03.2019 issued by the 1st respondent and the impugned order dated 25.06.2019 passed by the 2nd respondent.
2.Brief facts of the case:
2.1 In the case on hand, initially, a notification dated 12.07.2018 came to be issued by the 1st respondent for acquisition of subject lands, to an extent of 25941 Hectares, which spread across 25 villages, for public purpose, i.e., formation of the National Highway “NH 948A”. Out of the said total extent, the petitioner's land is about 0.8195 Hectares. Subsequently, the petitioner sent a letter dated 25.07.2018 to the 2nd respondent, whereby he requested for personal hearing and also explained that there were no concrete alignment of proposed ring road and the remaining portion of the land will become redundant after the acquisition. Upon receipt of the said letter, the Surveyors had visited the subject land.
2.2 Thereafter, another letter dated 20.08.2018 was communicated by the petitioner to the respondents 2 & 3, wherein it was stated that the vacant lands towards edge of property could be used instead of petitioner's land for the purpose of forming the proposed road. On 15.10.2018, the 2nd respondent issued notice to call upon the petitioner for enquiry, which was scheduled to be held on 25.10.2018. Purusant to the said notice, the petitioner had filed his objection dated 22.10.2018 before the 2nd & 3rd respondents and thereafter, attended the enquiry on 25.10.2018. However, according to the petitioner, the 2nd respondent had rejected the petitioner's objection vide order dated 12.12.2018, without any proper consideration. Against the said order, a writ petition in WP.No.8186 of 2019 was filed by the petitioner, wherein, this Court, vide order dated 20.03.2019, had stayed the operation of the proceedings of Notification issued by the respondents. Thereafter, the said writ petition was disposed of by this Court vide order dated 18.06.2019 with a direction to conduct joint spot inspection and complete the proceedings.
2.3 During the pendency of the above writ petition, the 1st respondent issued the impugned Notification dated 08.03.2019 by declaring that the subject land should be acquired. Aggrieved over the said notice, one of the present writ petitions, i.e., WP.No.29755 of 2019 came to be filed by the petitioner.
2.4 Pursuant to the order passed in WP.No.8186 of 2019, the said joint spot inspection was conducted on 22.06.2019. The petitioner's wife and son had attended the joint spot inspection and filed the additional objections before the 2nd respondent. However, the 2nd respondent had rejected the additional objections vide impugned order dated 25.06.2019, against which, the writ petition in WP.No.29753 of 2019 came to be filed by the petitioner.
3. Petitioner's submission:
3.1 The learned counsel for the petitioner raised two grounds against the respondents. The 1st ground is pertaining to non-obtaining of Environment clearance prior to declaration under Section 3D of the National Highways Act, 1956 (hereinafter called as "the Act"). The 2nd ground is pertaining to non-consideration of petitioner's objections.
3.2 As far as the 1st ground is concerned, he would submit that in the Clause 7(f) of Schedule to the Environment Impact Assessment Notification dated 14.09.2016, it has been clearly stated that it is mandatory to obtain environment clearance for all projects and activities mentioned under Category A in the nature of expansion of National Highways greater than 100 km. In such case, the declaration under Section 3D of the Act, can be made only after obtaining the environment/forest clearance. To substantiate his submission, he referred to the judgement rendered by the Hon'ble Apex Court in Project D
The issuance of Section 3D Notification does not necessitate prior environmental clearance as it does not signify the commencement of construction activities.
Environmental clearance is required prior to commencing construction work, not before issuing notification under Section 3(1) of the Tamil Nadu Acquisition of Land for Industrial Purposes Act, 1997.
The court clarified that the declaration of land as a National Highway before acquisition and the Competent Authority's order under the 1956 Act do not require strict adherence to judicial procedures....
Compliance with publication and hearing requirements of the National Highways Act is essential, but non-inclusion of landowner names in notifications does not invalidate the process.
Point of law: Land Acquisition - Where in respect of any land, a notification has been published under sub-section (1) of section 3A for its acquisition but no declaration under sub-section (1) has b....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.