SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1998 Supreme(Ori) 44

High Court Of Orissa
S. N. PHUKAN
GRID CORPORATION OF ORISSA LIMITED - Appellant
Versus
INDIAN CHARGE CHROME LTD. - Respondent
Misc. Appeal 599  Of  1997
Decided On : 02/10/1998

Advocates Appeared:
ANURADHA DUTTA, BIKASH MOHANTY, INDIRA JAISINGH, M.KARUNGA, N.C.PANIGRAHI, R.R.Mohanty, S.C.Dash, S.P.Misra, S.R.DAS, S.S.DAS, SAMARESHWAR MOHANTY

THE PROVISIONS OF SECTION 7 OF THE ARBITRATION ACT, 1996 WOULD APPLY TO THE PRESENT CASE IN VIEW OF THE FACT THAT THE SCOPE OF THE ARBITRATION ACT IS VERY WIDE AND IT NOT ONLY CONTAINS ARBITRATION AGREEMENT IN WRITING BUT ALSO OTHER ARBITRATION AGREEMENTS AS MENTIONED IN SUB-SECTION (4).

Headnote:

ARBITRATION - DISPUTE BETWEEN GRID CORPORATION OF ORISSA LTD. AND INDIAN CHARGE CHROMES LTD. - ARBITRABILITY - JURISDICTION OF ORISSA ELECTRICITY REGULATORY COMMISSION - APPOINTMENT OF ARBITRATOR - HELD, DISPUTE IS ARBITRABLE AND WITHIN THE JURISDICTION OF THE REGULATORY COMMISSION - REGULATORY COMMISSION FAILED TO ARBITRATE IN THE MATTER AND/OR FAILED TO APPOINT AN ARBITRATOR - HON'BLE MR. JUSTICE AZIZ MUSHABBER AHMADI, FORMER CHIEF JUSTICE OF INDIA, NOMINATED AS ARBITRATOR.

Fact of the Case:

GRID CORPORATION OF ORISSA LTD. (GRIDCO) ISSUED A NOTICE TO INDIAN CHARGE CHROMES LTD. (ICCL) FOR DISCONNECTION OF POWER SUPPLY DUE TO NON-PAYMENT OF CHARGES. ICCL FILED APPLICATIONS UNDER SECTION 9 OF THE ARBITRATION AND CONCILIATION ACT, 1996 BEFORE THE SECOND ADDITIONAL DISTRICT JUDGE, BHUBANESWAR, WHICH WERE ALLOWED RESTRAINING DISCONNECTION OF POWER SUPPLY TILL DISPOSAL OF CASE NO. 15 OF 1997, PENDING BEFORE THE REGULATORY COMMISSION. THE COURT BELOW PASSED EX PARTE AD INTERIM INJUNCTION RESTRAINING THE GRIDCO FROM DISCONNECTING THE POWER SUPPLY. AGAINST THAT ORDER, A SPECIAL LEAVE PETITION WAS FILED, WHICH WAS MODIFIED BY THE APEX COURT TO THE EXTENT THAT INSTEAD OF DEPOSITING RS. 5 CRORES ON DEPOSITING RS. 2. 5 CRORES, THE ELECTRICITY SUPPLY SHOULD BE RECONNECTED IMMEDIATELY AND THAT THE REST RS. 2. 5 CRORES WOULD BE DEPOSITED SUBSEQUENTLY. ICCL ALLEGED THAT GRIDCO, CONTRARY TO ALL KNOWN PRACTICES OF BILLING AND CONTRARY TO THE AGREEMENT BETWEEN THE PARTIES, BEGAN TO MAKE HALF-AN-HOUR ADJUSTMENTS AND BILLS BEGAN TO BE RAISED ON HALF-AN-HOUR SETTLEMENT BASIS. ICCL FURTHER ALLEGED THAT GRIDCO IS DUTY BOUND UNDER THE INDIAN ELECTRICITY ACT, 1910 AND THE ELECTRICITY (SUPPLY) ACT, 1948 TO MAINTAIN GRID DISCIPLINE AT THE STATUTORY LIMITATIONS, BUT IT STARTED DEFAULTING, AND SINCE JULY, 1996, THE FREQUENCY OF THE GRID HAS BEEN FLUCTUATING BEYOND THE UPPER LIMITS OF THE STATUTORY LEVEL OBSTRUCTING THE STABLE POWER GENERATION BESIDES CAUSING SEVERE DAMAGE TO THE POWER PLANT OF ICCL AT CHOUDWAR. ICCL FILED A PETITION UNDER SECTION 9 OF THE ARBITRATION ACT, 1996 BEFORE THE DISTRICT JUDGE, PURI AND OBTAINED AN EX PARTE AD INTERIM INJUNCTION AGAINST GRIDCO RESTRAINING IT FROM DISCONNECTING BACK-UP POWER SUPPLY TO ICCL, IMFA AND PPL AND GRIDCO WS ACCORDINGLY INFORMED ON 30-4-1997. IT WAS ALLEGED THAT EVEN AFTER RECEIPT OF THE ORDER, POWER SUPPLY TO PPL WAS DISCONNECTED ON 1-5-1997. THERE WERE FURTHER PROCEEDINGS BEFORE THIS COURT AS WELL AS THE APEX COURT, AND ON PAYMENT OF RS. 5 CRORES, AS ORDERED BY THE APEX COURT, ELECTRICITY WAS RECONNECTED. GRIDCO ALSO FILED REPLY BEFORE THE REGULATORY COMMISSION ON 15-4-1997 WITHOUT RAISING ANY OBJECTION AS TO ARBITRATION REFERENCE.

Finding of the Court:

THE COURT HELD THAT THE DISPUTE BETWEEN THE PARTIES IS ARBITRABLE AND IT IS WITHIN THE JURISDICTION OF THE REGULATORY COMMISSION. THE REGULATORY COMMISSION FAILED TO ARBITRATE IN THE MATTER AND/OR FAILED TO APPOINT AN ARBITRATOR. THE COURT FURTHER HELD THAT THE PROVISIONS OF SECTION 7 OF THE ARBITRATION ACT, 1996 WOULD APPLY TO THE PRESENT CASE IN VIEW OF THE FACT THAT THE SCOPE OF THE ARBITRATION ACT IS VERY WIDE AND IT NOT ONLY CONTAINS ARBITRATION AGREEMENT IN WRITING BUT ALSO OTHER ARBITRATION AGREEMENTS AS MENTIONED IN SUB-SECTION (4). IT IS ALSO HELD THAT IF THERE IS ANY ARBITRATION AGREEMENT IN ANY OTHER ENACTMENT FOR THE TIME BEING IN FORCE I.E. STATUTORY AGREEMENT, PROVISIONS OF ARBITRATION ACT, 1996 SHALL APPLY EXCEPT SUB-SECTION (1) OF SECTION 40 AND SECTIONS 41 AND 43.

Issues: 1. WHETHER THE DISPUTE BETWEEN THE PARTIES IS ARBITRABLE? 2. IF ARBITRABLE, WHETHER IT IS WITHIN THE JURISDICTION OF THE REGULATORY COMMISSION? 3. WHETHER THE REGULATORY COMMISSION HAS NEGLECTED TO ARBITRATE INTO THE MATTER/TO APPOINT AN ARBITRATOR?

Ratio Decidendi: 1. SECTION 7 OF THE ARBITRATION ACT, 1996 WOULD APPLY TO THE PRESENT CASE IN VIEW OF THE FACT THAT THE SCOPE OF THE ARBITRATION ACT IS VERY WIDE AND IT NOT ONLY CONTAINS ARBITRATION AGREEMENT IN WRITING BUT ALSO OTHER ARBITRATION AGREEMENTS AS MENTIONED IN SUB-SECTION (4). 2. IF THERE IS ANY ARBITRATION AGREEMENT IN ANY OTHER ENACTMENT FOR THE TIME BEING IN FORCE I.E. STATUTORY AGREEMENT, PROVISIONS OF ARBITRATION ACT, 1996 SHALL APPLY EXCEPT SUB-SECTION (1) OF SECTION 40 AND SECTIONS 41 AND 43. 3. ICCL IS A LICENSEE UNDER THE INDIAN ELECTRICITY ACT, 1910 AND IT CONTINUED TO BE A LICENSEE EVEN AFTER THE REFORMS ACT, 1995 CAME INTO FORCE. 4. SECTION 37 OF THE REFORMS ACT, 1995 PROVIDES THAT ANY DISPUTE ARISING BETWEEN LICENSEES OR IN RESPECT OF MATTERS PROVIDED UNDER S. 33 OF THE ACT SHALL BE REFERRED TO THE COMMISSION, AND THE COMMISSION MAY PROCEED TO ACT AS ARBITRATOR OR NOMINATE ARBITRATORS TO ADJUDICATE AND SETTLE THE DISPUTE. 5. THE REGULATORY COMMISSION IS A QUASI JUDICIAL BODY AND BEFORE INFORMING THE ICCL THAT THE APPLICATION WAS NOT MAINTAINABLE, BOTH THE PARTIES SHOULD HAVE BEEN HEARD.

Final Decision: THE COURT HELD THAT THE DISPUTE BETWEEN THE PARTIES IS ARBITRABLE AND IT IS WITHIN THE JURISDICTION OF THE REGULATORY COMMISSION. THE REGULATORY COMMISSION FAILED TO ARBITRATE IN THE MATTER AND/OR FAILED TO APPOINT AN ARBITRATOR. THE COURT FURTHER HELD THAT THE PROVISIONS OF SECTION 7 OF THE ARBITRATION ACT, 1996 WOULD APPLY TO THE PRESENT CASE IN VIEW OF THE FACT THAT THE SCOPE OF THE ARBITRATION ACT IS VERY WIDE AND IT NOT ONLY CONTAINS ARBITRATION AGREEMENT IN WRITING BUT ALSO OTHER ARBITRATION AGREEMENTS AS MENTIONED IN SUB-SECTION (4). IT IS ALSO HELD THAT IF THERE IS ANY ARBITRATION AGREEMENT IN ANY OTHER ENACTMENT FOR THE TIME BEING IN FORCE I.E. STATUTORY AGREEMENT, PROVISIONS OF ARBITRATION ACT, 1996 SHALL APPLY EXCEPT SUB-SECTION (1) OF SECTION 40 AND SECTIONS 41 AND 43. THE COURT NOMINATED HON'BLE MR. JUSTICE AZIZ MUSHABBER AHMADI, FORMER CHIEF JUSTICE OF INDIA, AS ARBITRATOR TO DECIDE THE DISPUTE.

S. N. PHUKAN, J.


( 1 ) BY this common judgment and order, two appeals, registered as Misc. Appeal Nos. 599/97 and 600/97 and M. J. C. No. 229/97 are being disposed of.

( 2 ) THE two appeals have been filed by the Grid Corporation of Orissa Ltd. (for short 'gridco') against the judgment and order of the Second Additional District Judge, Bhubaneswar, dated 25-7-1997, passed in Misc. Case No. 219 of 1997 and Misc. Case No. G/195 of 1997. M. J. C. No. 229 of 1997 has been registered on an application filed under Section 11 of the Arbitration and Conciliation Act, 1996 (for short, 'the Arbitration Act, 1996') by the Indian Charge Chroms Ltd. (for short, 'iccl') against the GRIDCO and the Orissa State Electricity Regulatory Commission (for short, 'regulatory Commission' ).

( 3 ) A notice dated 20-6-97 for disconnection of power was issued by the GRIDCO against the ICCL. Against the said notice, two applications were filed under Section 9 of the Arbitration Act, 1996 before the Second Additional District Judge, Bhubaneswar. Both the applications were allowed restraining disconnection of power supply till the disposal of case No. 15 of 1997, which was pending before the Regulatory Commission. It may be stated that the court below passed ex parte ad interim injunction restraining the GRIDCO from disconnecting the power supply. Against the said order, this Court was approached in Misc. Appeal No. 297/97 and this Court directed that on depositing Rs. 5 crores with the GRIDCO power supply shall be restored. Against that order, a special leave petition was filed, which was registered as SLP No. 10969/97 and 11055/97 before the apex Court. The apex Court modified the order of this Court to the extent that instead of depositing Rs. 5 crores on depositing Rs. 2. 5 crores, the electricity supply should be reconnected immediately and that the rest Rs. 2. 5 crores would be deposited subsequently.

( 4 ) IT is necessary to state the facts in dispute beween the parties. The Indian Metals and Ferro Alloys Company (for short 'imfa') a company of ICCL and GRIDCO, a company registered under the Companies Act, 1956 and under the provisions of the Indian Electricity Act, 1910 (for short, 'act of 1910') and Electricity (Supply) Act, 1948 (for short, 'act of 1948') is generating power. Supply and transmission of electricity was earlier done by the Orissa State Electricity Board, within the State of Orissa. But, by the Orissa Electricity Reforms Act, 1995 (for short, 'oer Act, 1995'), the Board was dissolved and the function of transmission of electricity has been vested with GRIDCO, the successor-in-interest of the State Electricity Board. The Regulatory Commission is a statutory Commission set up under the above OER Act. IMFA set up a large Ferro Alloys Complex at Therubali, Rayagada district, Orissa and due to irregular supply of power, which prejudicially affected the functioning of the company, IMFA decided to set up a Captive Power Plant in Orissa in 1982 and it also obtained a licence for charge-chrome manufacturing plant. The ICCL decided to have another manufacturing unit at Choudwar due to proximity of coal and other raw materials. The power plant was set up to provide power to the Charge Chrome Plant of the IMFA and also for the sale of surplus power to Orissa State Electricity Board and for administration convenience ICCL was incorporated. IMFA asked the Government of Orissa and Orissa State Electricity Board to give permission for the project and for transmission of surplus electricity to the IMFA which is at a distance of 350 K. Ms. from Choudwar. As transmission through grid was to be done by the Orissa State Electricity Board, permission was given in writing by the State Government and the Orissa State Electricity Board (for short, 'oseb' ). The Orissa State Electricity Board by letter dt. 10-1-86 specifically represented that the system voltage and frequency variation would be as per Rules 54 and 55 respectively of Indian Electricity Rul





































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top