SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Ori) 545

IN THE HIGH COURT OF ORISSA AT CUTTACK
R.K. PATTANAIK, J.
M/s. Utkal Realtors Pvt. Ltd. – Appellant
Versus
Akhil Agarwal and Another – Respondents
M.S.A. Nos. 44, 45 of 2024
Decided On : 22-12-2025

Advocates Appeared:
For the Appellant : Lalit Kumar Maharana
For the Respondents: Mohit Agarwal, P.S. Nayak

A project completed before the commencement of the Real Estate Act is not subject to the Act's registration requirements, regardless of later safety certificate issues.

Headnote:(A) Real Estate (Regulation and Development) Act, 2016 - Section 3(1) and Proviso - Appeals against maintainability of complaints related to the project described as an ongoing one despite completion prior to the Act - Completion certificate issued prior to Act’s commencement is sufficient for project to be considered complete - Decision of Odisha Real Estate Appellate Tribunal declared erroneous - Complaints held not maintainable. (Paras 6-10, 21-24)

(B) Legal Principles - A project with a valid completion certificate prior to the Act is not subject to the Act’s registration requirements - Distinction between completion and occupancy certificates is essential in determining project status. (Paras 12, 17-20)

Facts of the case:
The appellant challenged the conclusion that their project was ongoing despite having received a completion certificate before the Act's enforcement. Complaints from the respondents led to appellate decisions labeling the project ongoing and thus subject to the Act.

Findings of Court:
The project, having received its completion certificate prior to 1st May 2017, was held to be a completed project, and the maintainability of the complaints was rejected.

Issues: The main issues were whether the OREAT was justified in classifying the project as ongoing despite the completion certificate, and the validity of reliance on fire safety certificate requirements for determining project status.

Ratio Decidendi: The court reinforced that adherence to statutory provisions regarding completion certificates was paramount. The absence of a fire safety certificate did not render the project ongoing when completed beforehand. The ruling clarified that complaints filed against completed projects are not maintainable under the Act.

Result: Appeals allowed; impugned orders set aside.

Table of Content
1. introduction and relevance of completion certificates (Para 1 , 6 , 9 , 12)
2. grounds of appeals based on completion certificate (Para 2 , 3 , 4 , 5)
3. arguments regarding the applicability of the act (Para 8 , 10 , 11)
4. clarification on completion vs occupancy certificates (Para 13 , 14 , 15 , 16 , 18 , 19)
5. legal grounding for project classification (Para 17 , 20)
6. final orders and directives of the court (Para 21 , 22 , 23 , 24)

JUDGMENT :

R.K. PATTANAIK, J.

1. Both the appeals are clubbed together for hearing and disposed of by the following common judgment.

2. M.S.A. No.44 of 2024: Instant appeal under Section 58 of the Real Estate (Regulation and Development) Act, 2016 (hereinafter referred to as ‘the Act’) is at the behest of the appellant assailing the legality and judicial propriety of the impugned order dated 27th September, 2024 passed in connection with OREAT Appeal No.96 of 2023 as at Annexure-1 confirmed in Review Petition No.15 of 2023 by order dated 13th November, 2024 by the learned Odisha Real Estate Appellate Tribunal at Bhubaneswar (hence called as ‘the OREAT’) on the ground inter alia that the decision vis-à-vis the concerned project in question holding the same to be an ongoing one despite issuance of Completion Certification prior to the commencement of the Act with effect from 1st May, 2017 is erroneous and hence, liable to be interfered with and set at naught.

3. M.S.A. No.45 of 2024: Present appeal is at the instance of the appellant challenging the impugned order dated 27th September, 2024 at Annexure-1 passed in OREAT Appeal No.97 of 2023 by the learned OREAT and thereafter, confirmed in Review Petition No.16 of 2024 by order dated 13th November, 2024 on the self-same ground as in the other appeal with the plea that such decision is culpably wrong and hence, deserves to be set aside in the interest of justice.

4. In both the cases, the learned OREAT considering the complaints received from the private respondents held that the action is maintainable, since, the project is an ongoing project in spite of the fact that the same is shown to have been completed prior to the commencement of the Act. Bereft of unnecessary details, the facts of the case are that the private respondents are the allottees, whereas, the appellant is promoter and the complaints were filed against the latter registered as Complaint Case Nos. 23 and 55 of 2019 received by the learned Odisha Real Estate Regulatory Authority (ORERA) under Section 31 of the Act and therein, the maintainability was challenged, which was raised on the ground that the project had been completed prior to the commencement of the Act, inasmuch as, it had received completion certificate prior to 1st May, 2017 and therefore, in terms of Proviso to Section 3 (2) of the Act, the same was not required to be registered under the Act. The learned ORERA rejected such a plea of the appellant by orders dated 28th December, 2021 with a conclusion that the complaints are in support of an ongoing project, though, completion certificates has been issued by the competent authority on 17th March, 2015 and since BDA issued a revised plan on 5th November, 2019 and the earlier plain having been modified and no fresh completion certificate was issued by the empaneled Architect relating to the completion as per such revised plan dated 5th November, 2019, the construction in respect of the project had not been completed. By separate orders at Annexure-1, the learned ORERA disposed of the objection of the appellant concluding that the complaints are entertainable. Both the orders dated 28th December, 2021 of the learned ORERA were challenged in OREAT Appeal Nos.16 and 15 of 2022 respectively and the learned OREAT by orders dated 13th February, 2023 as at Annexure-1 remitted the matter back with a direction to the learned ORERA to consider the question of maintainability afresh providing opportunity of hearing to both the sides taking into account the report o

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top