IN THE HIGH COURT OF ORISSA AT CUTTACK
R.K. PATTANAIK, J.
M/s. Utkal Realtors Pvt. Ltd. – Appellant
Versus
Akhil Agarwal and Another – Respondents
M.S.A. Nos. 44, 45 of 2024
Decided On : 22-12-2025
| Table of Content |
|---|
| 1. introduction and relevance of completion certificates (Para 1 , 6 , 9 , 12) |
| 2. grounds of appeals based on completion certificate (Para 2 , 3 , 4 , 5) |
| 3. arguments regarding the applicability of the act (Para 8 , 10 , 11) |
| 4. clarification on completion vs occupancy certificates (Para 13 , 14 , 15 , 16 , 18 , 19) |
| 5. legal grounding for project classification (Para 17 , 20) |
| 6. final orders and directives of the court (Para 21 , 22 , 23 , 24) |
JUDGMENT :
R.K. PATTANAIK, J.
1. Both the appeals are clubbed together for hearing and disposed of by the following common judgment.
2. M.S.A. No.44 of 2024: Instant appeal under Section 58 of the Real Estate (Regulation and Development) Act, 2016 (hereinafter referred to as ‘the Act’) is at the behest of the appellant assailing the legality and judicial propriety of the impugned order dated 27th September, 2024 passed in connection with OREAT Appeal No.96 of 2023 as at Annexure-1 confirmed in Review Petition No.15 of 2023 by order dated 13th November, 2024 by the learned Odisha Real Estate Appellate Tribunal at Bhubaneswar (hence called as ‘the OREAT’) on the ground inter alia that the decision vis-à-vis the concerned project in question holding the same to be an ongoing one despite issuance of Completion Certification prior to the commencement of the Act with effect from 1st May, 2017 is erroneous and hence, liable to be interfered with and set at naught.
3. M.S.A. No.45 of 2024: Present appeal is at the instance of the appellant challenging the impugned order dated 27th September, 2024 at Annexure-1 passed in OREAT Appeal No.97 of 2023 by the learned OREAT and thereafter, confirmed in Review Petition No.16 of 2024 by order dated 13th November, 2024 on the self-same ground as in the other appeal with the plea that such decision is culpably wrong and hence, deserves to be set aside in the interest of justice.
4. In both the cases, the learned OREAT considering the complaints received from the private respondents held that the action is maintainable, since, the project is an ongoing project in spite of the fact that the same is shown to have been completed prior to the commencement of the Act. Bereft of unnecessary details, the facts of the case are that the private respondents are the allottees, whereas, the appellant is promoter and the complaints were filed against the latter registered as Complaint Case Nos. 23 and 55 of 2019 received by the learned Odisha Real Estate Regulatory Authority (ORERA) under Section 31 of the Act and therein, the maintainability was challenged, which was raised on the ground that the project had been completed prior to the commencement of the Act, inasmuch as, it had received completion certificate prior to 1st May, 2017 and therefore, in terms of Proviso to Section 3 (2) of the Act, the same was not required to be registered under the Act. The learned ORERA rejected such a plea of the appellant by orders dated 28th December, 2021 with a conclusion that the complaints are in support of an ongoing project, though, completion certificates has been issued by the competent authority on 17th March, 2015 and since BDA issued a revised plan on 5th November, 2019 and the earlier plain having been modified and no fresh completion certificate was issued by the empaneled Architect relating to the completion as per such revised plan dated 5th November, 2019, the construction in respect of the project had not been completed. By separate orders at Annexure-1, the learned ORERA disposed of the objection of the appellant concluding that the complaints are entertainable. Both the orders dated 28th December, 2021 of the learned ORERA were challenged in OREAT Appeal Nos.16 and 15 of 2022 respectively and the learned OREAT by orders dated 13th February, 2023 as at Annexure-1 remitted the matter back with a direction to the learned ORERA to consider the question of maintainability afresh providing opportunity of hearing to both the sides taking into account the report o
Newtech Promotors and Developers Pvt. Ltd. Vs. State of U.P. and others
A project completed before the commencement of the Real Estate Act is not subject to the Act's registration requirements, regardless of later safety certificate issues.
The existence and date of issuance of occupancy certificates are critical in determining whether a real estate project is ongoing under the RERA.
The court clarified that the Completion Certificate's issuance date is crucial in determining a project's ongoing status under RERA, emphasizing the conjunctive reading of statutory provisions.
A project with a completion certificate issued prior to RERA's enactment is not considered ongoing under the RERA Act, thus not subject to its jurisdiction.
RERA applies to ongoing projects regardless of completion status, ensuring consumer protection and allowing for grievances to be raised under its provisions.
The main legal principle established in the judgment is the interpretation and application of the definition of 'ongoing project' under Rule 2(h) of the Uttar Pradesh Real Estate (Regulation and Deve....
The RERA Act applies to ongoing projects regardless of completion dates, ensuring consumer grievances are addressed under its provisions.
The completion certificate issued must be strictly in accordance with the sanctioned plan and specifications, and the responsibilities of the promoter include providing and maintaining essential serv....
The main legal point established in the judgment is the requirement for proper inspection and adherence to legal requirements by the competent authorities in issuing occupancy certificates for real e....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.