SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Ker) 1160

IN THE HIGH COURT OF KERALA AT ERNAKULAM
M.A. ABDUL HAKHIM, J.
P.V. Nidhish, S/o. P.V. Chandran & Ors. - Appellants
Versus
Sivaprakash, S/o. Krishnan - Respondent
MSA No. 14 of 2024
Decided On : 24-10-2024

Advocates Appeared:
For the Appellant : Biju Abraham, B.G. Bhaskar.
For the Respondent: V.V. Surendran, P.A. Harish, Dona Paul.

IMPORTANT POINT
The existence and date of issuance of occupancy certificates are critical in determining whether a real estate project is ongoing under the RERA.

Headnote:

(A) Real Estate (Regulation and Development) Act, 2016 – Section 3 – Review of Tribunal's order – The Court recalled its previous judgment allowing the appeal, finding an error in the initial decision regarding the substantial questions of law. The Tribunal remanded the matter back to K-RERA to reconsider whether the project is ongoing and the validity of occupancy certificates. (Paras 1, 10, 34)

(B) Jurisdiction of K-RERA – The K-RERA must determine the existence and date of issuance of occupancy certificates to decide if the project is ongoing. The Tribunal's findings regarding the occupancy certificate's decisiveness were set aside. (Paras 26, 31)

Facts of the case :

The complainant, an Apartment Owners Association, sought a registered conveyance deed for common areas in a project where the respondent allegedly retained possession of part of the land. The K-RERA initially dismissed the complaint, stating the project was not ongoing.

Findings of Court :

The Court found that the Tribunal's remand order was appropriate, allowing K-RERA to consider additional evidence regarding the project's status.

Issues : Whether the project is ongoing under Section 3 of RERA and the relevance of occupancy certificates.

Ratio Decidendi : The Court ruled that the existence of occupancy certificates is crucial for determining if a project is ongoing, and the Tribunal's interpretation of their decisiveness was incorrect.

Result : Appeal allowed in part.

JUDGMENT :

M.A. Abdul Hakhim, J.

1. This Court had disposed of this Miscellaneous Second Appeal as per Judgment dated 30.08.2024, which is reported in Nidhish P.V. V. Sivaprakash 2024 (6) KHC 16. Thereafter, the respondent filed this Review Petition No.1023/2024 to review the judgment dated 30.08.2024. This Court allowed the said Review Petition No.1023/2024 as per judgment dated 03.10.2024, recalling the judgment dated 30.08.2024, finding that this Court committed an error in allowing the appeal in part after framing the Substantial Questions of law at the admission stage itself.

2. Thereafter the Miscellaneous Second Appeal was admitted on the very same substantial questions of law which were considered in the judgment dated 30.08.2024. The Counsel on either side made additional submissions on 15.10.2024. Hence this revised judgment is passed incorporating consideration of the additional contentions made by the respondent.

3. The appellants are the legal heirs of the respondent in Complaint No.17/2020 of the Kerala Real Estate Regulatory Authority (‘the K-RERA’ for short).

4. The complainant is the Apartment Owners Association of the project of the respondent by name ‘Orchid Garden-PVS Park’ located at Govindapuram, Kozhikode. The Complainant/Association sought direction to the respondent to execute a registered conveyance deed in favour of the Association with respect to the undivided proportionate title in the common area in accordance with the Rules and to direct the respondent to handover all the relevant original documents in connection with the entire apartments.

5. The main grievance of the complainant is that the project of the respondent consisted of four blocks namely, A, B, C, and D, having a total number of 64 flats in a total area of 167 cents, that the common area for the above four blocks is included in the 167 cents, but the respondent used only 126 cents for the said blocks and common area and the balance 41 cents are in the possession of the respondent and the respondent is trying to make new construction therein without handing over possession of the common area and without delivering the documents such as Building Permit, Sanctioned Plan, Deeds, Occupancy Certificate, NOC from Pollution Control Board to the complainant.

6. The respondent opposed the prayers in the complaint stating that the complaint is filed under the mistaken impression that the entire 167 cents of land owned by the respondent is intended for the construction of the four blocks that have been built by the respondent; that, in fact, the total land was intended for construction of five blocks as can be seen from the approved plan and permit issued by the local authority; that 41 cents situated at the southern extremity is proposed for future development; that the allottees of units in the four constructed block have no right over the 41 cents which is not the part of the site of their blocks. The complainant has only the right of usage over all the common areas excluding 41 cents demarcated in the approved plan intended for future development.

7. When the complaint was pending enquiry, the K-RERA by its order dt 5.03.2020 prima facie found that the project in question is registrable under Section 3 of the Real Estate (Regulation and Development) Act, 2016 (‘the RERA’ for Short) and thereupon directed the respondent to file an application for registration within two weeks from the date of order. The respondent filed a Statement dt. 19.03.2020 stating that the project is not an ongoing one but a finished project before coming into force of the RERA and that, therefore, the respondent is not liable for registration. The respondent was directed to produce the original Occupancy Certificate which he claimed to have obtained in the year 2009. On 16.10.2020, the respondent filed an Affidavit before the K-RERA affirming that the Occupancy Certificate was issued 12 years ago and, hence, he is not in possession of the same. The K-RERA marked the copies of

        Click Here to Read the rest of this document
        1
        2
        3
        4
        5
        6
        7
        8
        9
        10
        11
        SupremeToday Portrait Ad
        supreme today icon
        logo-black

        An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

        Please visit our Training & Support
        Center or Contact Us for assistance

        qr

        Scan Me!

        India’s Legal research and Law Firm App, Download now!

        For Daily Legal Updates, Join us on :

        whatsapp-icon telegram-icon
        whatsapp-icon Back to top