SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Ori) 42

IN THE HIGH COURT OF ORISSA AT CUTTACK
SANJEEB K. PANIGRAHI, J.
M/s. Bridge and Roof Company (India) Ltd. Kolkata – Appellant
Versus
State of Orissa and Others – Respondents 
W.P. (C) No. 31365 of 2025
Decided On : 09-01-2026

Advocates Appeared:
For the Appellant : H. Gupta
For the Respondents: Rajdeep Pradhan, Gouri Mohan Rath, Sidharth Shankar Padhy

Works contracts cannot invoke the jurisdiction of MSEFC under the MSMED Act, necessitating arbitration under the Arbitration and Conciliation Act, thereby rendering MSEFC proceedings void.

Headnote:(A) Micro, Small and Medium Enterprises Development Act, 2006 - Section 18 - Writ petition filed to quash proceedings initiated by MSEFC under alleged lack of jurisdiction - M/s. Bridge and Roof Company (India) Limited contends that the underlying contract is a works contract and cannot be classified under MSMED Act - It is held that the MSEFC lacks jurisdiction to entertain claims arising from works contracts, reinforcing that such disputes should be resolved via conventional arbitration as per the Arbitration and Conciliation Act, 1996. (Paras 29, 30)

(B) Jurisdiction - Writ jurisdiction under Article 226 of the Constitution of India can be invoked when an order is passed without inherent jurisdiction - The Court exercises its discretion to intervene in such cases to uphold the rule of law. (Paras 26, 28)

Facts of the case:
The petitioner, a government undertaking, contests the MSEFC's jurisdiction in a case arising from a works contract for a power plant project, alleging that the council's order failed to address jurisdictional claims. The petitioner sought to set aside the order rejecting its challenge to the MSEFC's jurisdiction, asserting rights to arbitration under the original contract framework.

Findings of Court:
The proceedings of MSEFC concerning works contracts are held outside its jurisdiction, thus declaring the MSEFC's order without jurisdiction.

Issues: (A) Whether a works contract exists under the MSMED Act?

(B) Is a writ petition maintainable against MSEFC orders alleged to have originated without jurisdiction?

Ratio Decidendi: The Court determined that the nature of works contracts exceeds the jurisdiction of MSEFC, which is designed for simple supply-related disputes, mandating that such disputes be resolved through established arbitration mechanisms, establishing that inherent jurisdiction issues warrant intervention.

Result: Writ Petition allowed; MSEFC's order quashed.

Table of Content
1. petition seeks to quash earlier proceedings. (Para 2)
2. petitioner claims lack of jurisdiction of the msefc. (Para 3 , 4)
3. issues surround jurisdiction and nature of works contracts. (Para 5 , 6 , 7 , 8 , 9)
4. judicial interpretations limit msmed act to specific contracts. (Para 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18)
5. court holds works contracts outside msmed act. (Para 20 , 21 , 22)
6. writ jurisdiction invoked due to inherent jurisdictional issue. (Para 24 , 25 , 26 , 27 , 28)
7. writ petition allowed, previous order quashed. (Para 29 , 30 , 31)

JUDGMENT :

SANJEEB K. PANIGRAHI, J.

1. The present Writ Petition has been preferred seeking setting aside of order dated 30.8.2025, passed by the Directorate of Industries, Cuttack in MSEFC Case No. 68 of 2021.

I. FACTUAL MATRIX OF THE CASE:

2. The brief facts of the case are as follows:

(i) The Petitioner has filed the present Petition to correct a jurisdictional error committed by the MSEF Council, vide its order dated 30.8.2025 and has challenged the impugned order on the ground of lack of inherent jurisdiction by the Council.

(ii) The petitioner, M/s Bridge and Roof Company (India) Limited, is a Government of India undertaking incorporated under the Indian Companies Act, 1913, having its registered office at Kolkata. The petitioner was engaged as the principal contractor for execution of works relating to a power plant project of M/s Bhushan Energy Limited at Dhenkanal, Odisha. In furtherance of the said project, the petitioner issued a work order dated 11.6.2010 in favour of M/s Adarsh Corporation Private Limited, the predecessor-in-interest of Opposite Party No. 3, for execution of structural steel works at the project site.

(iii) The work order dated 11.6.2010 pertained to “Fabrication, Erection and Painting of Structural Steel Work” in connection with the power plant area. The contract is allegedly composite in nature, involving labour, material, design coordination, erection, and site execution. The contract value at the inception stood at approximately Rs. 14.14 crores, subject to revisions. The terms of the work order incorporated the Notice Inviting Tender and Record Notes of Discussion as integral parts of the contractual framework.

(iv) Subsequently, on 19.9.2012, a formal amendment to the work order was issued, recording the change in the name of the contractor from M/s Adarsh Corporation Private Limited to M/s Adarsh Noble Corporation Limited. This amendment did not alter thescope of work but merely acknowledged the corporate name change at the request of the contractor.

(v) A second amendment followed on 29.6.2013, whereby the rates were revised for quantities executed or to be executed after 30.9.2012. Notably, the scope of work remained unchanged, and the contractual obligations continued to be governed by the original terms. Over time, the cumulative value of the contract increased to approximately Rs. 24.50 crores.

(vi) On 28.10.2014, the petitioner addressed correspondence to Opposite Party No. 3 requesting deputation of an authorised representative to discuss the progress and execution of the balance work at site. Records of discussions held thereafter reflected assurances by Opposite Party No. 3 to continue execution and complete pending works within stipulated timelines.

(vii) A third and final amendment to the work order was issued on 25.6.2015, whereby Opposite Party No. 3 undertook to complete the entire scope of work on or before 31.5.2016. This amendment did not enhance rates or expand scope but sought to bring finality to execution timelines.

(viii) In the interregnum, Opposite Party No. 3 applied for Udyog Aadhaar registration on 18.12.2015 under the provisions of the Micro, Small and Medium Enterprises Development Act, 2006. The registration was subsequent to the issuance of the work order and its amendments but prior to certain later events forming part of the dispute.

(ix) On 10.5.2018, the petitioner issued a Mechanical Completion Certifi

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top