IN THE HIGH COURT OF ORISSA AT CUTTACK
SANJEEB K. PANIGRAHI, J.
M/s. Bridge and Roof Company (India) Ltd. Kolkata – Appellant
Versus
State of Orissa and Others – Respondents
W.P. (C) No. 31365 of 2025
Decided On : 09-01-2026
| Table of Content |
|---|
| 1. petition seeks to quash earlier proceedings. (Para 2) |
| 2. petitioner claims lack of jurisdiction of the msefc. (Para 3 , 4) |
| 3. issues surround jurisdiction and nature of works contracts. (Para 5 , 6 , 7 , 8 , 9) |
| 4. judicial interpretations limit msmed act to specific contracts. (Para 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18) |
| 5. court holds works contracts outside msmed act. (Para 20 , 21 , 22) |
| 6. writ jurisdiction invoked due to inherent jurisdictional issue. (Para 24 , 25 , 26 , 27 , 28) |
| 7. writ petition allowed, previous order quashed. (Para 29 , 30 , 31) |
JUDGMENT :
SANJEEB K. PANIGRAHI, J.
1. The present Writ Petition has been preferred seeking setting aside of order dated 30.8.2025, passed by the Directorate of Industries, Cuttack in MSEFC Case No. 68 of 2021.
I. FACTUAL MATRIX OF THE CASE:
2. The brief facts of the case are as follows:
(i) The Petitioner has filed the present Petition to correct a jurisdictional error committed by the MSEF Council, vide its order dated 30.8.2025 and has challenged the impugned order on the ground of lack of inherent jurisdiction by the Council.
(ii) The petitioner, M/s Bridge and Roof Company (India) Limited, is a Government of India undertaking incorporated under the Indian Companies Act, 1913, having its registered office at Kolkata. The petitioner was engaged as the principal contractor for execution of works relating to a power plant project of M/s Bhushan Energy Limited at Dhenkanal, Odisha. In furtherance of the said project, the petitioner issued a work order dated 11.6.2010 in favour of M/s Adarsh Corporation Private Limited, the predecessor-in-interest of Opposite Party No. 3, for execution of structural steel works at the project site.
(iii) The work order dated 11.6.2010 pertained to “Fabrication, Erection and Painting of Structural Steel Work” in connection with the power plant area. The contract is allegedly composite in nature, involving labour, material, design coordination, erection, and site execution. The contract value at the inception stood at approximately Rs. 14.14 crores, subject to revisions. The terms of the work order incorporated the Notice Inviting Tender and Record Notes of Discussion as integral parts of the contractual framework.
(iv) Subsequently, on 19.9.2012, a formal amendment to the work order was issued, recording the change in the name of the contractor from M/s Adarsh Corporation Private Limited to M/s Adarsh Noble Corporation Limited. This amendment did not alter thescope of work but merely acknowledged the corporate name change at the request of the contractor.
(v) A second amendment followed on 29.6.2013, whereby the rates were revised for quantities executed or to be executed after 30.9.2012. Notably, the scope of work remained unchanged, and the contractual obligations continued to be governed by the original terms. Over time, the cumulative value of the contract increased to approximately Rs. 24.50 crores.
(vi) On 28.10.2014, the petitioner addressed correspondence to Opposite Party No. 3 requesting deputation of an authorised representative to discuss the progress and execution of the balance work at site. Records of discussions held thereafter reflected assurances by Opposite Party No. 3 to continue execution and complete pending works within stipulated timelines.
(vii) A third and final amendment to the work order was issued on 25.6.2015, whereby Opposite Party No. 3 undertook to complete the entire scope of work on or before 31.5.2016. This amendment did not enhance rates or expand scope but sought to bring finality to execution timelines.
(viii) In the interregnum, Opposite Party No. 3 applied for Udyog Aadhaar registration on 18.12.2015 under the provisions of the Micro, Small and Medium Enterprises Development Act, 2006. The registration was subsequent to the issuance of the work order and its amendments but prior to certain later events forming part of the dispute.
(ix) On 10.5.2018, the petitioner issued a Mechanical Completion Certifi
K. Raheja Development Corporation v. State of Karnataka
Kone Elevator India Pvt. Ltd. v. State of Tamil Nadu
Ssangyong Engineering & Construction Co. Ltd. v. NHAI
Balvant N. Viswamitra v. Yadav Sadashiv Mule (Dead) through Irs.
Whirlpool Corpn. v. Registrar, Trade Marks
L. Chandra Kumar v. Union of India
Works contracts cannot invoke the jurisdiction of MSEFC under the MSMED Act, necessitating arbitration under the Arbitration and Conciliation Act, thereby rendering MSEFC proceedings void.
The MSEFC lacks jurisdiction to adjudicate disputes arising from works contracts, which necessitate arbitration under traditional frameworks, not the MSMED Act.
The Facilitation Council lacks jurisdiction over disputes arising from works contracts under the MSME Act, and principles of natural justice must be adhered to in adjudicatory processes.
The court upheld that statutory remedies under the MSMED Act take precedence over private arbitration agreements, affirming the Facilitation Council’s jurisdiction in disputes involving MSMEs.
The MSMED Act operates as a special beneficial legislation, overriding the Arbitration Act in cases involving registered MSMEs, emphasizing exclusive jurisdiction of MSEFC for dispute resolution.
The MSMED Act applies to work contracts, and the parties are bound to follow the mechanism provided under Section 18 of the Act, including participation in arbitration and the Tribunal's jurisdiction....
The Act does not apply to works contracts with an element of supply and not mere supply and service contracts. The contractors must file the memorandum under section 8 of the Act to claim the benefit....
The Council has jurisdiction to adjudicate disputes in cases of works contracts, even if there is an arbitration clause in the contract.
The court ruled that a contract involving both supply and installation qualifies as a works contract, which is outside the jurisdiction of MSMED Act, leading to the Arbitrator's award being set aside....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.