IN THE HIGH COURT OF ORISSA AT CUTTACK
K.R.MOHAPATRA, SANJAY KUMAR MISHRA, JJ.
Sarat Mohanty – Appellant
Versus
State Of Odisha – Respondent
W.P. (C) No. 33970 of 2025
Decided On : 11-02-2026
| Table of Content |
|---|
| 1. petitioner seeks enhancement of compensation under the act. (Para 2) |
| 2. arguments regarding jurisdiction and necessary adjudication. (Para 3 , 4) |
| 3. court's analysis on procedural compliance under the act. (Para 5 , 6 , 7 , 8) |
| 4. court's directive for reconsideration of the matter by the authority. (Para 9) |
JUDGMENT :
1. This matter is taken up through hybrid mode.
2. Petitioner in this writ petition seeks to assail the order dated 17th February, 2025 (Annexure-5) passed by the Zone Officer-cum-L.A. Collector, Subarnarekha Irrigation Project, Laxmiposi Zone, Baripada (Opposite Party No.2) in not entertaining an application filed under Section 73(1) of Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (for brevity ‘the Act’) and referring the matter back to the Authority for adjudication.
3. Mr. Nayak, learned counsel for the Petitioner submits that for acquisition of land of the Petitioner pertaining to Plot No.638 (Sarad-III) measuring an area of Ac.1.13 dec. under Khata No.137/34 of Mauza Nalagaja sand Plot No.606 measuring an area of Ac 0.09 dec, Plot No.607 measuring an area of AC 0.08 Dec, under khata no.18 of Mauza Nalagaja under Tahasil-Rasgobindpur in the district of Mayurbhanj (for brevity, ‘the case land’), compensation was also awarded in favour of the Petitioner. Some of the co-villagers being not satisfied with the quantum of compensation in their favour filed an application before the Collector, Mayurbhanj to refer the matter to the Authority. Accordingly, their applications were referred to the Authority under Section 64 of the Act and compensation awarded in their favour was enhanced. The Petitioner stating that the land of Sribatatsha Mohanty of village- Nalagaja, P.S.-Morada in the district of Mayurbhanj acquired under the same notification was enhanced by the LAR&R Authority, Cuttack in L.A.R. Case No.185 of 2022 vide judgment dated 11th April, 2023, filed an application under Section 73(1) of the Act for enhancement of the compensation.
3.1. It is submitted by Mr. Nayak, learned counsel for the Petitioner that the Land Acquisition Collector should have adjudicated the matter on merit and passed an award under Section 73(2) of the Act. Instead, he referred the matter to the Authority under Section 73(3) of the Act for adjudication. Hence, this writ petition has been filed challenging the said order under Annexure-5.
3.2. Mr. Nayak, learned counsel for the Petitioner further submits that on an application filed under Section 73(1) of the Act, the Land Acquisition Collector is required to pass an award under Section 73(2) of the said Act. Any person, if aggrieved by such award may file an application to refer the matter to the Authority and in that event the Land Acquisition Collector could have referred the matter under Section 73 (3) of the Act. In the instant case, neither award under Section 73(2) was passed nor was any application filed to refer the matter to the Authority. Thus, there was no occasion on the part of the Land Acquisition Collector to refer the matter to the Authority for adjudication. He, therefore, submits that the impugned order under Annexure- 5 is without jurisdiction. Hence, he prays for setting aside the impugned order under Annexure-5 and to remit the matter to the Land Acquisition Collector for fresh adjudication of the petition under Section 73(1) of the Act.
4. Mr. Nayak, learned Additional Government Advocate, on instruction, submits that the kisam of the case land of the petitioner and the award of the Authority relied upon by him did not tally as observed in the impugned order under Annexure-5. Thus, the same requires adjudication of the Authority. Accordingly, the Land Acquisition Collector referred the matter to the Authority for adjudication.
5. Considering the submissions made by learned counsel for the parties, this Court finds that an application under Section 73(1) of the Act was filed by the Petitioner fo
The Collector must adjudicate claims under the Right to Fair Compensation and Transparency in Land Acquisition Act before referring matters for enhancement, ensuring all procedural requirements are m....
COVID-19 guidelines allow exclusion of limitation periods when determining the validity of petitions under section 73 of the 2013 Land Acquisition Act.
Acquisition of land – Where no award under Section 11 of Act of 1894 has been made, then, all provisions of new Act of 2013 relating to determination of compensation would apply.
Proper compensation assessment procedures under Section 64 of the 2013 Act must be followed, allowing the authority to consider referral and potential delays for justifiable reasons.
The Reference Court in land acquisition matters lacks the authority to set aside a Collector's award and remand for fresh determination, functioning instead to affirm or enhance the award according t....
Determination of amount of compensation – Reference to appropriate authority – Collector has no jurisdiction to go into such question.
The court affirmed that disputes regarding compensation inadequacy must be referred to the appropriate authority under the Act, underscoring the Collector's duty to comply with statutory timelines.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.