SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(Ori) 696

IN THE HIGH COURT OF ORISSA AT CUTTACK
ARINDAM SINHA, J.
Union Of India And Others – Appellant
Versus
Suman Sundar Patra - Respondent
ARBA No.56 of 2018
Decided On : 22-09-2022

Advocates Appeared:
For the Appellant : Mr. P. K. Parhi, Asgi, Mr. P. P. Behera, Cgc
For the Respondent:Mr. N. Jujharsingh, Advocate

The court upheld the arbitration award for refund of earnest money deposit and interest, ruling no illegality in the arbitrator's decisions based on the waiver of objections by the appellant.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 28(3) and Section 31(7) - Appeal against an arbitration award - Court upheld the award on grounds of refund of earnest money deposit and grant of interest, finding no patent illegality in the arbitrator's decision - Appellant's claims were waiver-laden due to late objections regarding excepted matters. (Paras 2-6)

(B) Award of interest - Arbitrator rightly awarded future interest under section 31, not finding contrary provisions in contract - Rate of interest at 15% deemed appropriate for expeditious compliance. (Paras 8)

Facts of the case:
The court examined a dispute over the arbitrator's award concerning claims for refund of earnest money deposit and interest, where the appellant argued that the arbitrator overstepped his mandate, leading to a closure of contract and unjust forfeiture of the security deposit by the respondent. Multiple agreements altered the contract terms with deviations allowed.

Findings of Court:
The arbitrator’s decision found no fault by the contractor, emphasizing that delays were not entirely attributed to him. The award on interest was also found valid as per statutory provisions.

Issues: The court examined whether the arbitrator acted within his powers concerning excepted matters and if the award for interest was justified based on existing contractual obligations.

Ratio Decidendi: The court supported the arbitrator's decisions, stating that the waiver of rights on excepted matters due to late objections invalidated the appellant's claims, and the arbitral tribunal acted within its powers under the law.

Result: Appeal dismissed.

Table of Content
1. challenge to arbitral award on procedural grounds. (Para 1 , 2)
2. support for award based on past contract and cooperation. (Para 3 , 4)
3. importance of jurisdiction and waiver in arbitration. (Para 5 , 6)
4. no illegality in awarding interest. (Para 7 , 8)
5. final dismissal of appeal and confirmation of lower court judgment. (Para 9 , 10)

ORDER :

ARINDAM SINHA, J.

1. Mr. Behera, learned advocate, Central Government Counsel led by Mr. Parhi, learned advocate and Assistant Solicitor General appear on behalf of appellants and submit, impugned is judgment dated 30th August, 2018, whereby three points of challenge to award dated 28th April, 2014 were rejected. He submits, the three points were challenge to the award on excepted matters, directing refund of Earnest Money Deposit (EMD) and grant of future interest.

2. He submits, there can be no dispute regarding award made on matters that were excepted by the contract. In awarding all those items of claim, the arbitrator transgressed terms of the contract and was therefore in violation of mandate in sub-section (3) in section 28, Arbitration and Conciliation Act, 1996. Since his client, employer had given extension of time to do the work without imposing penalty and respondent did not execute it, same resulted in closure of the contract. There could not have been award on claim for refund of EMD. He submits further, by clause 16 (3) of General Conditions of Contract (GCC) there was prohibition on claim of interest. The arbitrator having granted interest at 15% again went beyond terms of the contract and was in violation of aforesaid mandate by sub-section (3) of section 28. He submits, on these three counts the Court below erred in appreciating appellants9 case. In awarding those claims, there was patent illegality.

3. Mr. Jujharsingh, learned advocate appears on behalf of respondent. He supports reasoning given in impugned judgment. He draws attention to paragraph 6 in it to submit, the Court below found that by application dated 4th March, 2013, made at stage of argument in the reference, appellant had taken the point of some matters had been excepted as excluded from arbitration. He relies on judgment of the Supreme Court in Narayan Prasad Lohia vs Nikunj Kumar Lohia , reported in AIR 2002 SC 1139 , paragraph 16. He submits, there was waiver.

4. Regarding award for refund of EMD he submits, original contract was worked out by his client. Deviations were required. Extension of time granted was for purpose of working out the deviation/extra works. The deviations could not be worked out. The contract was closed. He submits, refund of earnest money/security deposit was dealt with under issue no.6 in the reference. The arbitrator found as many as five supplementary agreements were executed containing deviations and extending the time. Delay in completion of work was not entirely attributable to his client. It was also found that claim for escalation was pending before the concerned authority, when there was decision to close the contract on imposing penalty as forfeiture of security deposit. On these facts the arbitrator found the imposition to be unjustified.

5. On grant of interest Mr. Jujharsingh submits, the arbitrator has the power under clause-(b) in sub-section (7) of section 31.

6. Matters excepted by the contract, as not covered by the arbitration agreement, would be a bar on adjudication in respect thereof, in the reference. It would mean that dispute on excepted matters have to be otherwise adjudicated, as may be by proceeding initiated in a civil Court. Section 4 provides for waiver. Clause-(b) says, a party, who knows that any requirement under the arbitration agreement has not been complied with and yet proceeds with the arbitration without stating his objection to such non-compliance without undue delay or, if a time limit provided for stating that objection, within that period of time, said party shall be deemed to have waived his right to so object. Appella

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top