IN THE HIGH COURT OF ORISSA AT CUTTACK
A.C. BEHERA, J.
Santosh Kumar Naik – Appellant
Versus
State of Orissa and Others – Respondents
R.S.A. No. 69 of 2022
Decided On : 20-02-2026
| Table of Content |
|---|
| 1. introduction of appeal and parties involved. (Para 1 , 2) |
| 2. background of the contractor's claims. (Para 3) |
| 3. defendants' counterarguments and positions. (Para 4 , 5) |
| 4. issues framed and trial court's judgment. (Para 8 , 10) |
| 5. legal question regarding impossibility of contract. (Para 13 , 14) |
| 6. citations about force majeure and impossibility. (Para 15 , 16) |
| 7. consolidated court reasoning and legal standards. (Para 18 , 19 , 20) |
| 8. court's reaffirmation of lower courts' decisions. (Para 21) |
| 9. final adjudication and disposition of appeal. (Para 22 , 23) |
JUDGMENT :
A.C. BEHERA, J.
1. This 2nd Appeal has been preferred against the confirming judgment.
2. The appellant in this 2nd appeal was the plaintiff before the learned trial court in the suit vide C.S. No.184 of 2013 and appellant before the learned 1st appellate court in the 1st appeal vide R.F.A. No.46/20 of 2018-21.
The respondents in this 2nd appeal were the defendants before the learned trial court in the suit vide C.S. No.184 of 2013 and the respondents before the learned 1st appellate court in the 1st appeal vide R.F.A. No.46/20 of 2018-21.
3. The suit of the plaintiff (appellant in this 2nd appeal) against the defendants (respondents in this 2nd appeal) vide C.S. No.184 of 2013 was a suit for declaration and mandatory injunction.
As per the case of the plaintiff, he (plaintiff) is an A-Class Contractor and he being the highest bidder of a tender in respect of the Government works indicated in Schedule-A of the plaint under Subdega Block in the district of Sundargarh, a work order in respect of the said works was issued by the defendant nos.1 and 2 in his favour. Then, as per the agreement, the defendant nos.1 and 2 received security money from the plaintiff for such work order in the form of original Bank guarantee described in Schedule-C of the plaint for completion of the said works within the period indicated in the work order and agreement.
On the basis of that work order and agreement, he (plaintiff-Contractor) started its works at the work site and the said work site is under Subdega Block of Sundargarh district was within two to five kilometers distance from Jharkhand border. While, works at the work site by the plaintiff was under progress, some anti-socials of Jharkhand province interfered with his works at the work site and demanded crores of rupees as chanda/dadabati from the plaintiff or else they will not allow him (plaintiff) to continue with the works there. As such, the Maoists as well as Pahadi Chita Group anti-socials created disturbances at the work site coming to the work site physically on being armed with weapons and threatened to the engaged workers of the plaintiff to stop the works expressing that, unless the plaintiff comply their demand of money, they will not allow them to work at the work site. They also threatened to the workers of the plaintiff at the work site to commit murder, if they will proceed with the works. One day, in the year 2009, the Maoists kidnapped to the nephew of the plaintiff, namely, Jatin Naik from the work site during the course of his supervision to the works and demanded lakhs of rupees from the plaintiff for his release. For which, the plaintiff lodged an F.I.R. on dated 27.08.2009 at Talasara Police Station and on the basis of such F.I.R. of the plaintiff, a case vide Talasara P.S. Case No.70 of 2009 was registered, but, the police could not able to rescue the nephew of the plaintiff from the clutches of the Maoists. Therefore, the plaintiff was compelled to satisfy the demand of the Maoists for the release of his nephew from their clutches and on payment of rupees ten lakhs to the Maoists, he (plaintiff) could able to release his nephew from the clutches of Maoists. Due to the above continuous interference of the Maoists and anti-socials in the work site of the plaintiff, the works of the plaintiff could not progress, which ultimately made the said works at the work site impossible/impracticable to perf
The burden of proving impossibility under Section 56 of the Indian Contract Act rests on the asserting party; failure to provide such evidence results in dismissal of claims.
A contracting party must prove the impossibility of performance to invoke Section 56 of the Indian Contract Act, 1872; self-induced inability does not excuse breach.
A party alleging impossibility under Section 56 of the Indian Contract Act must substantiate claims with evidence; self-induced circumstances do not qualify for relief.
The burden of proving impossibility under Section 56 of the Indian Contract Act lies with the party asserting it, and self-induced inability does not justify non-performance.
A contract can be frustrated by an event that makes it impossible for the parties to perform their obligations under the contract.
Non-service of statutory notice under Section 80 of the C.P.C. is waivable if no objection is raised in the defendants' written statement, allowing the suit to be maintained.
The plaintiff must establish a prima facie case and show irreparable loss to obtain an injunction. The court will consider the balance of convenience and the nature of the suit in reaching its decisi....
The court reinforced that under the Arbitration and Conciliation Act, 1996, the scope for judicial interference with arbitral awards is limited, particularly regarding factual findings.
Breach of contract – Award of damages—Work schedule is required for progressive payment and target and it is sine qua non for execution of contracted work.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.