SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Ori) 499

IN THE HIGH COURT OF ORISSA AT CUTTACK
A.C. BEHERA, J.
Santosh Kumar Naik – Appellant
Versus
State of Orissa and Others – Respondents
R.S.A. No. 69 of 2022
Decided On : 20-02-2026

Advocates Appeared:
For the Appellant : P. Mukherji
For the Respondent: Gyanaloka Mohanty

A contracting party must prove the impossibility of performance to invoke Section 56 of the Indian Contract Act, 1872; self-induced inability does not excuse breach.

Headnote:(A) Indian Contract Act, 1872 - Section 56 - Contractual obligations - Impossibility of performance - The appellant, a contractor, claimed non-fulfillment of contract due to interference from Maoists, invoking Section 56 - Courts found lack of evidence for such interference and upheld contract termination. (Paras 18-20)

(B) Findings of law - The courts established that the burden to prove impossibility lies with the party claiming it, and self-induced impossibility does not apply under Section 56.

Facts of the case:
The appellant, while undertaking government works, faced threats from Maoists demanding bribes, which he claimed made contract performance impossible. He failed to provide evidence of notifying this to the defendants.

Findings of Court:
The appellant did not prove interference leading to non-performance, and the demands of Maoists did not legally justify contract breach.

Issues: Main issues included the lawfulness of contract termination and whether the contract became impossible to perform.

Ratio Decidendi: Courts concluded that the plaintiff did not discharge the burden of proof to claim impossibility of performance, hence the contract termination was lawful.

Result: Appeal dismissed, confirming lower court rulings.

Table of Content
1. plaintiff's claim based on contract and interference. (Para 3)
2. defendants deny allegations of interference. (Para 4 , 5)
3. trial court dismissed the suit due to lack of evidence. (Para 7 , 9)
4. plaintiff's plea of impossibility under section 56 of contract act. (Para 16)
5. burden of proof lies with the plaintiff; must prove impossibility. (Para 19 , 20)
6. 2nd appeal dismissed; lower court decisions upheld. (Para 22 , 23)

JUDGMENT :

A.C. BEHERA, J.

1. This 2nd Appeal has been preferred against the confirming judgment.

2. The appellant in this 2nd appeal was the plaintiff before the learned trial court in the suit vide C.S. No.184 of 2013 and appellant before the learned 1st appellate court in the 1st appeal vide R.F.A. No.46/20 of 2018-21.

The respondents in this 2nd appeal were the defendants before the learned trial court in the suit vide C.S. No.184 of 2013 and the respondents before the learned 1st appellate court in the 1st appeal vide R.F.A. No.46/20 of 2018-21.

3. The suit of the plaintiff (appellant in this 2nd appeal) against the defendants(respondents in this 2nd appeal) vide C.S. No.184 of 2013 was a suit for declaration and mandatory injunction.

As per the case of the plaintiff, he(plaintiff) is an A-Class Contractor and he being the highest bidder of a tender in respect of the Government works indicated in Schedule-A of the plaint under Subdega Block in the district of Sundargarh, a work order in respect of the said works was issued by the defendant nos.1 and 2 in his favour. Then, as per the agreement, the defendant nos.1 and 2 received security money from the plaintiff for such work order in the form of original Bank guarantee described in Schedule-C of the plaint for completion of the said works within the period indicated in the work order and agreement.

On the basis of that work order and agreement, he(plaintiff-Contractor) started its works at the work site and the said work site is under Subdega Block of Sundargarh district was within two to five kilometers distance from Jharkhand border. While, works at the work site by the plaintiff was under progress, some anti-socials of Jharkhand province interfered with his works at the work site and demanded crores of rupees as chanda/dadabati from the plaintiff or else they will not allow him(plaintiff) to continue with the works there. As such, the Maoists as well as Pahadi Chita Group anti-socials created disturbances at the work site coming to the work site physically on being armed with weapons and threatened to the engaged workers of the plaintiff to stop the works expressing that, unless the plaintiff comply their demand of money, they will not allow them to work at the work site. They also threatened to the workers of the plaintiff at the work site to commit murder, if they will proceed with the works. One day, in the year 2009, the Maoists kidnapped to the nephew of the plaintiff, namely, Jatin Naik from the work site during the course of his supervision to the works and demanded lakhs of rupees from the plaintiff for his release. For which, the plaintiff lodged an F.I.R. on dated 27.08.2009 at Talasara Police Station and on the basis of such F.I.R. of the plaintiff, a case vide Talasara P.S. Case No.70 of 2009 was registered, but, the police could not able to rescue the nephew of the plaintiff from the clutches of the Maoists. Therefore, the plaintiff was compelled to satisfy the demand of the Maoists for the release of his nephew from their clutches and on payment of rupees ten lakhs to the Maoists, he(plaintiff) could able to release his nephew from the clutches of Maoists. Due to the above continuous interference of the Maoists and anti-socials in the work site of the plaintiff, the works of the plaintiff could not progress, which ultimately made the said works at the work site impossible/impracticable to perform. As such, he(plaintiff) was prevented from performing the contract works at the work site.

When, due to the above impossibility/impr

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top