IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
G.S.Sandhawalia, Lapita Banerji, JJ.
OMML-SPML (JV) through Sh. Deepak Kumar Jain - Appellant
Versus
NHPC Limited - Respondent
FAO-CARB-5-2024 (O&M)
Decided On : 23-01-2024
(A) Arbitration and Conciliation Act, 1996 – Section 34 – Appeal against arbitral award – The learned Additional District Judge upheld the majority award of the Arbitral Tribunal, finding no public policy violation or patent illegality – The court emphasized that the arbitrator is the sole judge of evidence and the award cannot be interfered with unless it is arbitrary or capricious. (Paras 1, 2, 3, 4, 24)
(B) Curable Defects – The court ruled that procedural defects must be rectified; failure to do so renders the Statement of Claim non-maintainable. (Paras 10, 12, 23)
Facts of the case: The appeal arose from a dispute regarding an arbitration award related to a construction contract for a hydroelectric project, where the claimant's Statement of Claim was deemed improperly filed due to lack of proper authorization. (Paras 7, 10)
Findings of Court: The court found that the claimant failed to cure the procedural defects in the Statement of Claim, leading to its dismissal. (Paras 23, 24)
Issues: The main issues included the legality of the arbitral composition, disclosure of relationships, and the maintainability of the Statement of Claim. (Paras 4, 5)
Ratio Decidendi: The court held that the arbitrator's decision is final unless it is shown to be arbitrary or against public policy, and procedural defects must be rectified to maintain the validity of claims. (Paras 2, 10)
Result: Appeal dismissed.
JUDGMENT :
LAPITA BANERJI, J.
1. In the present appeal, the appellant has prayed for setting aside of the impugned order dated December 16, 2023 passed by the learned Additional District Judge, Faridabad in CIS No. ARB-63-2020. The learned Additional District Judge relied on the decision reported in 2009 (5) SCC 142 Kwality Mfg. Corpn. Vs. Central Warehousing Corpn. to come to the finding that the Arbitral Tribunal dated 29.02.2020 by way of majority award took a plausible view which did not merit any interference. The majority award being neither against the public policy of India nor being vitiated by patent illegality or error appearing on the face of the award, on the ground of erroneous application of law and re-appreciation of the evidence, whether oral or documentary, was the reason the award was not interfered with. The relevant portion relied on by the learned Additional District Judge in Central Warehousing Corpn. (supra) is reproduced herein below:-
2. The learned Additional District Judge also relied on the case of Associate Builders Vs. Delhi Development Authority reported in (2015) 3 SCC 49 and Saanggyong Engineering and Construction Company Limited Vs. National Highways Authority of India reported in 2019 (15) SCC 131 to come to the finding that neither any public policy of India has been violated nor has any patent illegality been caused by the Arbitral Tribunal in terms of the Section 34 of the Arbitration and Conciliation Act, 1996. Relevant portion of Associate Builders (supra) relied upon by him is reproduced herein below:-
3. The relevant extract from Saanggyong Engineering and Construction Company Limited (supra) is reproduced herein below:-
“36. Thus, it is clear that public policy of India is now constricted to mean firstly, that a domestic award is contrary to the fundamental policy of Indian law, as understood in paras 18 and 27 of Associate Builders, or secondly, that such award is against basic notions of justice or morality as understood in paras 36 to 39 of Asso
New Horizons Limited and another Vs Union Of India and others (1995) 1 SCC 478
Uday Shankar Triyar Vs. Ram Kalewar Singh and others 2006 (1) SCC 75
SREI Infrastructure Finance Ltd. Vs. Tuff Drilling
Associate Builders Vs. Delhi Development Authority (2015) 3 SCC 49
The court affirmed that an arbitrator's award is final unless proven arbitrary or against public policy, emphasizing the necessity of rectifying procedural defects in claims.
The scope of enquiry under Section 11 of the Arbitration and Conciliation Act, 1996, is restricted to the examination of the existence of the arbitration agreement. The burden lies on the party resis....
Arbitral awards may be composite if the issues relate closely, but interest must adhere to contractual terms.
The arbitration agreement's validity is independent of stamp duty on the substantive contract, and courts have limited grounds for interfering with arbitral awards under Section 34 of the Arbitration....
The court ruled that partnerships cannot be dissolved without proper evidence and consent, emphasizing the need for independent arbitration for distinct entities.
A non-signatory party could be subjected to arbitration provided these transactions were with group of companies and there was a clear intention of the parties to bind both, the signatory as well as ....
The arbitration agreement's validity is independent of stamp duty on the substantive contract, and courts have limited grounds for interfering with arbitral awards.
Section 34 of the Arbitration and Conciliation Act provides a limited window of challenge to an arbitral award, and a violation of a statute, not tied to public policy or public interest, cannot serv....
The arbitration agreement's validity is independent of stamp duty issues, and courts have limited grounds for interfering with arbitral awards.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.