PUNJAB AND HARYANA HIGH COURT AT CHANDIGARH
Nidhi Gupta, J.
Tej Singh - Appellant
Versus
Trilok Chand – Respondent
RSA-4204-2013 (O&M)
Decided on : 18-03-2025
JUDGMENT :
Nidhi Gupta, J.
The defendant is in second appeal against the concurrent judgments and decrees of the learned Courts below, whereby the suit for possession by way of specific performance of the Agreement to Sell dated 23.11.2005 filed by the plaintiff/ respondent herein, has been decreed by the learned trial Court vide judgment and decree dated 25.04.2012 holding the plaintiff entitled to money decree for return of earnest money of Rs. 8 lacs from the defendant with interest @ 6% per annum from the date of institution of suit till the realization of the amount. The Civil Appeal No. 66 dated 25.05.2012 filed by the defendant against the said judgment and decree dated 25.04.2012 was dismissed by the learned Additional District Judge, Faridabad vide judgment and decree dated 26.04.2013; and the cross-objections filed by the plaintiff were allowed with costs decreeing the suit of the plaintiff; and the defendant was directed to clear the mortgage with the Syndicate Bank, Seekri, within 15 days of the passing of the said judgment and thereafter, he shall be liable to get the sale deed executed in favour of the plaintiff within 30 days thereof on payment of balance sale consideration by the plaintiff.
2. The parties shall hereinafter be referred to as per their status before the learned trial Court i.e. the appellant is the defendant'; and the respondent is the plaintiff'.
3. The brief facts of the case as set out in the plaint are that on 23.11.2005, the defendant entered into contract with the plaintiff to sell his agricultural land as detailed in para 1 of the plaint, situated within the revenue estate of Vill. Piala, Teh. Ballabgarh, Distt. Faridabad total measuring 8 kanal 13 marla for a sum of Rs.28,32,875/-. The defendant received a sum of Rs. 3 lacs on 23.11.2005 as part payment from the plaintiff and he executed an Agreement to Sell and receipt on the said date. The defendant on 25.11.2005 further received a part payment of Rs. 5 lacs from the plaintiff in which Rs. 4 lacs was paid in cash and Rs. 1 lac through cheque No. 051910 dated 25.11.2005. So the defendant received a total sum of Rs. 8 lacs from the plaintiff and he also executed a separate receipt on 25.11.2005 in favour of the plaintiff. The land in dispute was under mortgage with the Syndicate Bank, Seekri and as per terms and conditions of the Agreement, it was for the defendant to get the land free from all kinds of encumbrances. The plaintiff was always ready and willing to perform his part of contract and is still ready and willing to perform his part of contract but the defendant did not perform his obligation despite repeated requests of the plaintiff. The sale deed was agreed to be executed and got registered on or before 30.05.2006 but the said day was a public holiday and so the plaintiff went in the office of Sub Registrar, Ballabgarh on 31.5.2006 along with balance sale consideration amount and miscellaneous expenses but the defendant did not turn up to perform his part of agreement. On 29.05.2006, the plaintiff had also obtained a copy of jamabandi and found that the land was still having lien of the bank and was not got released by the defendant. Thereafter a legal notice dated 30.5.2006, was also served upon the defendant to get the land released from the lien of the bank and execute the sale deed in favour of the plaintiff but in vain forcing the plaintiff to file the present suit.
4. Upon notice, the defendant appeared and filed written statement contesting the suit on various grounds inter alia stating that the target date of 30.05.2006 being public holiday, the defendant had duly reached the office of Sub Registrar for execution of sale deed on 31.05.2006 but the plaintiff did not reach the office of Sub-Registrar along with balance sale consideration amount and other miscellaneous expenses. It was further stated in the written statement that the defendant had received a notice dated 30.5.2006 through counsel of the plaintiff which was duly
The obligation to clear a mortgage lies with the seller, and the buyer's readiness to perform arises only after the seller fulfills this condition.
A plaintiff seeking specific performance must prove continuous readiness and willingness to perform their contractual obligations; failure to do so bars relief.
Plaintiff's failure to prove continuous readiness and willingness to perform contract negates entitlement to specific performance under Specific Relief Act.
Specific performance – Relief of specific performance is equitable remedy – Plaintiff have to necessarily show their readiness and willingness in performing their part of contract from date of agreem....
The plaintiff's failure to demonstrate readiness and willingness to perform the contract led to the dismissal of the appeal for specific performance.
Time is of the essence of a contract if the parties have agreed that it is or if the circumstances of the case show that it is.
The plaintiff's failure to prove readiness and willingness to perform his part of the contract within the stipulated time precluded him from obtaining the relief of specific performance.
Proof of continuous readiness and willingness is essential for specific performance; failure to demonstrate such readiness undermines entitlement to equitable relief.
(1) Suit for Specific Performance – Plaintiff must establish that he was ready and willing to perform contract – In this regard, conduct of plaintiff must be consistent.(2) Generally, time is not of ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.