ALLAHABAD HIGH COURT
BEFORE : SUNIL AMBWANI AND ADITYA NATH MITTAL, JJ.
GODREJ AND BOYCE MANUFACTURING COMPANY LIMITED .....Appellant
Versus
SECUR INDUSTRIES LIMITED AND ANOTHER .....Respondents
(First Appeal From Order No. 2485 of 2009, decided on 24th January, 2013)

Subject

Arbitration Law - AWARD

Act Referred

ARBITRATION AND CONCILIATION ACT : S.37, S.34
INTEREST ON DELAYED PAYMENTS TO SMALL SCALE AND ANCILLARY UNDERTAKINGS ACT : S.6(2), S.4, S.5
LIMITATION ACT : Art.14, Art.113
MICRO SMALL AND MEDIUM ENTERPRISES DEVELOPMENT ACT : S.12

Headnote

Arbitration and Conciliation Act, 1996—Sections 37 and 34—Limitation Act, 1963—Articles 14 and 113—Interest on Delayed Payments to Small Scale and Ancillary Undertakings Act, 1993—Sections 6(2), 4 and 5—Micro, Small and Medium Enterprises Development Act, 2006—Section 12—Arbitration award—Setting aside of—Scope—Application under Section 34 moved by appellant dismissed—Arbitration award passed by U.P. State Facilitation Council (old Council) subsequently established under the new Act as U.P. State Micro and Small Enterprises Facilitation Council—Supply of goods—Arbitration agreement—Limitation for the price of goods agreed to be supplied and for which the agreement dated 12.8.1994 was terminated on 9.10.1998, would start from the day, when the last of the supplies were made and received by appellant—Since the limitation is specifically provided for the price of goods supplied under Article 14, the supplier cannot take benefit of Article 113—Claim was thus beyond the limitation prescribed under Article 14, Limitation Act, 1963 and could not be entertained by Council—District Judge also erred in relying upon Article 113, Limitation Act—Notification of New Council was not made upto the date of award—Claim of respondent barred by limitation—Award also found defective—Impugned order of District Judge set aside. [Paras 21 to 53]

       

Advocates:
Counsel :
Yaswant Verma, S.P. Gupta and Shashi Nandan for the Petitioner; R.P. Agarwal, Atul Dayal, Girish Singh and K.N. Tripathi for the Respondents.

JUDGMENT

By the Court.—This First Appeal From Order under Section 37 of the Arbitration & Conciliation Act, 1996 (for short, the Act of 1996) arises out of judgment and order dated 28.7.2009 passed by the District Judge, Kanpur Nagar in Arbitration Case No. 36/70 (Godrej and Boyce Manufacturing Company Limited v. Secur Industries Limited) by which he dismissed the application under Section 34 of the Act of 1996, moved by Godrej & Boyce Manufacturing Company Limited to set aside the award dated 19.6.2007 made by the U.P. State Facilitation Council (for short, the old Council) subsequently established under the new Act as U.P. State Micro and Small Enterprises Facilitation Council (for short, the Council). The Council awarded a total amount of Rs. 16,75,24,654.29 including, (i) claims made in various debit notes of Rs. 4,72,88,000/- and interest @ one and a half time of the prime lending rate charged by the State Bank of India compounded with monthly rests on the principal amount from 2.10.1999, till the date of the award under Sections 4 and 5 of the Act of 1993 of Rs. 12,02,36,654.29.

2. We have heard Shri Shashi Nandan, Senior Counsel assisted by Shri Yashwant Verma for Godrej and Boyce Manufacturing Company Limited-the objector-appellant; and Shri K.N. Tripathi, Senior Counsel assisted by Shri Atul Dayal for the respondent.

3. M/s Secur Industries Limited Ghaziabad-the claimant-respondent filed a Claim No. IFC 40 of 2001, before the U.P. State Facilitation Council (old Council) under Section 6 (2) of the Interest on Delayed Payments to Small Scale and Ancillary Undertakings Act, 1993 (for short, the Act of 1993) with the averments that the parties had entered into an agreement on 12.8.1994 for supply of various items; the terms and conditions of supply, determination of price and other terms and conditions were mentioned in the agreement. The agreement was prematurely terminated on 9.10.1998 before the stipulated period of five years. Some disputes arose between the parties regarding payment of the price of goods supplied under the agreement. A note of demand was sent but that the applicant did not make any payment. The claim was filed in October, 2001.

4. The claim was forwarded by the Council to Godrej & Boyce Manufacturing Co. Ltd. on 27.12.2001, asking it to respond. After seeking extension of time to reply without prejudice to its legal rights and contentions, the Godrej & Boyce Manufacturing Co. Ltd filed a suit in City Civil Court at Bombay for declaration that reference of the claim to the Council was ultra vires the provisions of the Act and therefore illegal, null and void. The City Civil Court, Bombay granted interim injunction on 5.2.2002 which was ultimately rejected on 28.11.2002, on the ground that in view of Section 5 of the Act of 1996, no Court could interfere in arbitration proceedings. An appeal was filed in Bombay High Court, which stayed the proceedings on 21.1.2003 before the Council, on the ground that no notice was served on the appellant company by Secur Industries Ltd. The application of Secur Industries Ltd for expediting the proceedings was rejected. Secur Industries Ltd filed a Civil Appeal No. 1417 of 2004 in the Supreme Court, which was allowed on 26.2.2004. The Supreme Court in the judgment reported in (2004) 3 SCC 447 held that the High Court erred in staying proceedings before the Council. It had no jurisdiction to do so. In para 12 of judgment it was held :

“12. The arguments which have been raised before us by the learned counsel on behalf of the respondent to a large extent related to the merits of the appellant’s claim before the Council. Having regard to the scope of the authority of the Arbitral Tribunal under Section 16, this is not a matter which the Court can adjudicate upon. Indeed it is incumbent on the Court to refer the parties to arbitration under Section 8(1) of the 1996 Act if a suit is filed in a matter which is the subject matter of an arbitration agreement. Furthermore, eve