IN THE HIGH COURT OF JUDICATURE AT ALLAHABAD
Shekhar B. Saraf, J.
Union Of India Through Garrison Engineer AF - Appellant
Vs.
M/s Yauk Engineers - Respondent
Appeal Under Section 37 Of Arbitration And Conciliation Act 1996 No.389 of 2023
Decided On : 05-04-2024
JUDGMENT :
1. This is an appeal under Section 37 of the Arbitration & Conciliation Act, 1996 (hereinafter referred to as the ‘Act’) filed by the Union of India through Garrison Engineer AF (hereinafter referred to as the ‘Applicant’) against the order dated January 12, 2012 passed by District Judge, Agra in Arbitration Case No. 406 of 2006 under Section 34 of the Act.
FACTS
2. I have laid down the factual matrix leading to the instant appeal below:
b. As per clause 39 and 39.1 of the Contract between the parties and condition 46 of IAFW 2249 General Conditions of Contract (hereinafter referred to as the ‘GCC’), entire installation was deemed to be guaranteed by the Respondent for efficient performance for 12 months from the date of completion of work. The Respondent had also given specific undertaking in this regard vide its letter dated October 1, 1997.
c. The Transformer provided by the Respondent became defective in June, 1998 and accordingly, the Respondent was asked by the Applicant to rectify the defects. The Respondent rectified the defects, and claimed reimbursement of Rs.6,28,268/-incurred by it in the rectification of defects. Since, the Applicant contended that based on the guarantee provided by the Respondent it was not liable to reimburse any cost incurred towards rectification of defects, disputes arose between the parties which were referred to arbitration.
d. The Arbitrator vide its award dated July 31, 2006, among other things, awarded a sum of Rs.6,22,268/- along with interest at the rate of 12% p.a. from February 2, 1998 to July 31, 2006 and at the rate of 8% p.a. from August 1, 2006 till the date of actual payment in favour of the Respondent.
e. The arbitral award dated July 31, 2006 was challenged by the Applicant under Section 34 of the Act before the District Judge, Agra (Arbitration Case No. 406 of 2006). Vide its order dated January 12, 2012, the District Judge, Agra dismissed the application filed by the Applicant and upheld the arbitral award dated July 31, 2006 in its entirety.
f. Aggrieved by the order dated January 12, 2012 passed by the District Judge, Agra, the Applicant filed the instant appeal under Section 37 of the Act before this Court on May 4, 2012.
CONTENTIONS OF THE APPLICANT
3. Although several claims that were allowed by the Arbitrator and affirmed by the District Judge are under challenge in this appeal, learned ASG of India has confined his arguments to the reimbursement of Rs.6,22,268/-. The other grounds of appeal have not been pressed by him and are accordingly dismissed in limine. With regards to the claim of reimbursement of Rs.6,22,268/-, Sri Gopal Verma, counsel has made the following arguments:
ii. The Arbitrator without considering the oral and written submissions as well as documentary evidence illegally awarded Rs. 6,22,268/- in favour of the Respondent.
iii. The issue regarding the undertaking given by the Respondent for 1 year from August 9, 1996, and further extended vide its letter dated October 1, 1997, in terms of clause 39 of the contract between the parties was specific
Indian Oil Corporation Limited v. M/s Shree Ganesh Petroleum reported in (2022) 4 SCC 463
MMTC Ltd. v. Vedanta Ltd. reported in (2019) 4 SCC 163
Commissioner of Income Tax v. Vatika Township reported in (2015) 1 SCC 1
Union of India v. Parmar Construction reported in (2019) 15 SCC 682
Union of India v. Pradeep Vinod Construction Co. reported in (2020) 2 SCC 464
Ratnam Sudesh Iyer v. Jackie Kakubhai Shroff reported in (2022) 4 SCC 206
BCCI v. Kochi Cricket (P) Ltd.
Ssangyong Engg. & Construction Co. Ltd. V. NHAI
Hindustan Construction Co. Ltd. V. Union of India
Oil & Natural Gas Corporation Ltd. v. Saw Pipes Ltd. reported in (2003) 5 SCC 705
Rattan Chand Hira Chand v. Askar Nawaz Jung (1991) 3 SCC 67
Associate Builders v. DDA reported in (2015) 3 SCC 49
Champsey Bhara Co. v. Jivraj Balloo Spg. and Wvg. Co. Ltd.
Karnail Singh v. State of Haryana
Basant Lal Banarsi Lal v. Bansi Lal Dagdulal
Mc Dermott International Inc. v. Burnt Standard Co. Ltd.
J.G. Engineers (P) Ltd. v. Union of India reported in (2011) 5 SCC 758
Arbitral awards must adhere to contractual terms; deviations render them unsustainable and violate public policy.
The judgment emphasizes the limited grounds for interference with arbitral awards under Section 34 of the Arbitration and Conciliation Act, highlighting the need for restraint by courts while examini....
(1) Appeal against modified arbitral award – Merits of award are only to be gone into, if award is demonstrated to be contrary to public policy of India.(2) Arbitral proceedings are per se not compar....
(1) While exercising power under Section 34 of A & C Act, arbitral award can only be confirmed or set aside, but not modified.(2) Award passed by Arbitral Tribunal cannot be set aside on the ground t....
The court emphasized that judicial interference with arbitral awards is strictly limited, focusing only on issues of public policy or jurisdictional errors and cannot re-evaluate the merits of the aw....
The limited scope of intervention by Courts in arbitral awards under Section 34 of the Arbitration and Conciliation Act, emphasizing the need to satisfy specific grounds for setting aside an arbitral....
The court affirmed that under Section 34 of the Arbitration and Conciliation Act, 1996, it cannot reassess the merits of an arbitral award unless it violates public policy or is patently illegal.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.