IN THE HIGH COURT OF JUDICATURE AT ALLAHABAD
Ashwani Kumar Mishra, Jayant Banerji, JJ.
Smt. Asha Rani - Petitioner
Vs.
Union Of India And Others - Respondent
WRIT - C No. - 10962 of 2025
Decided On :15-04-2025
| Table of Content |
|---|
| 1. petitioner claims lack of rehabilitation award post land acquisition. (Para 1 , 2) |
| 2. petitioner seeks similar relief as in previous judgments. (Para 3 , 4) |
| 3. competent authority under nh act is responsible for awards. (Para 5 , 6 , 7) |
JUDGMENT :
Jayant Banerji, J.
1. Heard learned counsel for the petitioner, Shri Pranjal Mehrotra, learned counsel for the respondent no.2, NHAI and Shri Rajiv Gupta, learned counsel for the State-respondent. Shri Rajesh Kumar Jaiswal appears for the respondent no.1.
2. The case of the petitioner is that his land was acquired by NHAI and an award was also made. The petitioner has received compensation but the rehabilitation and resettlement award has not been made as per the Second Schedule to the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. It has, therefore, been prayed that the respondents be directed to make rehabilitation and resettlement award as per provisions of the Act, 2013.
3. Learned counsel for the petitioner submits that the claim of the petitioner is similar to the one raised in Writ C No.2782 of 2023 ( Ashok Kumar and 8 others vs. National Highway Authority of India and 3 others ), which was disposed of by this Court, by order dated 24.2.2023 in terms of the order passed in Writ C No.21601 of 2022 ( Ranvir Singh and 35 others vs. National Highway Authority of India and Competent Authority For Land Acquisition and Others ). The operative part of the order passed in Writ C No.2782 of 2023 ( Ashok Kumar and 8 others vs. National Highway Authority of India and 3 others ), dated 24.2.2023 is as follows :-
"9. Lastly the writ petitions have been disposed of with the following directions:-
"For the above, without entering into the merits of the claim of the petitioner, it is directed that the competent authority under the National Highways Act, 1956 shall prepare a proposal for the rehabilitation and resettlement award for affected families, within the meaning of Section 3(c) of the Act, 2013, in terms of the entitlements provided in the Second Schedule, with the assistance of the officers of the NHAI and submit the same before the Collector for making award in accordance with the provisions of Section 31 of the RECTLARR Act, 2013.
For preparation of the said proposal, the competent authority shall make necessary enquiry as per the provisions of the Sections 34, 35 and 36 of the RECTLARR Act, 2013 as contained in Chapter V of the Act, 2013, i.e before preparation of the rehabilitation and resettlement award, in relation to the acquisition in question.
It goes without saying that the representatives of the National Highways Authority and the affected tenure holders are entitled to participate in the proceedings for preparation of the award. The claim of the petitioners herein for the entitlements under the Second Schedule at serial no. (1) for provision of housing unit in case of displacement; serial no. (4) choice of annuity and employment and serial no. (10), one time resettlement allowance, shall be specifically considered by the competent authority in making such an award.
The entire exercise shall be completed, as expeditious as possible, preferably, within a period of six months from the date of receipt of copy of this order.
We may make it clear that, at this stage, no direction has been given for providing benefits of Third Schedule as no such demand has been raised by the petitioners herein.
In any case, while making such an award, independent consideration shall be given to the elements of rehabilitation and resettlement entitlements for the affected families provided in the Second Schedule, without being influenced by any of the observations made hereinabove."
10. The petitioners herein are similarly situated and, therefore, are entitled for the same relief.
11. The present writ petition is, accordingly, disposed of."
4. It is submitted on behalf of the petitioner that the instant petition be also disposed of in
The competent authority under the National Highways Act is responsible for rehabilitation and resettlement awards, as defined by the Right to Fair Compensation and Transparency in Land Acquisition, R....
The competent authority under the National Highways Act, 1956 is responsible for declaring rehabilitation and resettlement awards, not the district Collector, as per the provisions of the Right to Fa....
The competent authority under the National Highways Act is responsible for declaring rehabilitation and resettlement awards, not the district Collector, as per the provisions of the Right to Fair Com....
Petitioners can obtain no cause for concern or apprehension, as impelled by them in this writ petition, because if they are to seek enhancement of the amounts under the Award as per Section 3G of the....
An appeal under Section 74 of the Right to Fair Compensation Act cannot challenge awards issued under the National Highways Act, 1956.
The provisions of the Right to Fair Compensation and Transparency in Land Acquisition Act, 2013, apply to land acquisitions under the National Highways Act, requiring a detailed examination of indivi....
Point of Law – NHAI, or the other competent Authority, is at liberty to act as per Section 3E of the "NH Act" while taking possession of the acquired properties, notwithstanding the pendancy of the a....
The District Collector must specify entitlement under the RFCTLARR Act when denying rehabilitation and resettlement compensation, irrespective of prior compensation under the NH Act.
Denial of rehabilitation and resettlement compensation under RFCTLARR Act was improper as it did not confirm eligibility despite prior compensation under the NH Act.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.