SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(MP) 376

IN THE HIGH COURT OF MADHYA PRADESH
Vivek Rusia and Amar Nath (Kesharwani), JJ.
Vidyawati Construction Company (M/s.) v. Municipal Corporation
Arbitration Revision No. 1 of 2011 (I); Decided on 19.12.2022

Headnote:

(1) Madhyastham Adhikaran Adhiniyam, 1983 (M.P.) -- Ss. 7B (1) (a) and 7B (2A) -- works contract for construction -- terminated after dispute -- dispute not referred to final authority under terms and conditions of contract -- raised before tribunal within three years of termination -- maintainable as per non-obstante clause used in S. 7B (2A). (2012) 4 MPLJ 212 relied on. (1996) 3 SCC 690 and 2006 (2) Arb. LR 305 discussed. [Para 7]

(2) Madhyastham Adhikaran Adhiniyam, 1983 (M.P.) -- S. 16 -- interest -- every claimant entitled to interest under three heads, namely, pre-reference, pendente lite and future reference. (2009) 10 SCC 187 followed. [Para 9]

¼1½ ekè;LFke~ vfèkdj.k vfèkfu;e] 1983 ¼eŒçŒ½ & èkkjk 7[k ¼1½ ¼d½ rFkk 7[k ¼2d½ & lfUuekZ.k d¢ fy, ladeZ lafonk & fookn d¢ i'pkr~ lekIr dh xbZ & lafonk dh 'kr¨Z rFkk fucaèku¨a d¢ vèkhu fookn vafre çkfèkdkjh d¨ fufnZ"V ugha & lekfIr d¢ rhu o"kZ d¢ Òhrj vfèkdj.k d¢ le{k mBk;k x;k & èkkjk 7[k ¼2d½ esa ç;qDr lo¨Zifj [kaM d¢ vuqlkj pyus ;¨X;A ¼2012½ 4 ,e ih ,y ts 212 voyafcrA ¼1996½ 3 ,l lh lh 690 rFkk 2006 ¼2½ vkfcZŒ ,y vkj 305 foosfprA ¼iSjk 7½

¼2½ ekè;LFke~ vfèkdj.k vfèkfu;e] 1983 ¼eŒçŒ½ & èkkjk 16 & C;kt & çR;sd nkosnkj rhu 'kh"k¨Z vFkkZr~ funsZ'k&iwoZ] okndkyhu rFkk Òkoh funsZ'k d¢ vèkhu C;kt dk gdnkjA ¼2009½ 10 ,l lh lh 187 vuqlfjrA ¼iSjk 9½

ORDER

1. Petitioner has filed this Arbitration Revision under section 19 of Madhyastam Adhikaran Adhiniyam, 1983 (Adhiniyam, 1983) whereby the Reference Case No.71/20098 has been dismissed in view of the judgment passed in the State of M.P. v. Kamal Kishore Sharma, 2006 (2) Arb. L.R. 305.

2. The facts of the case in short are as under:

2.1 The respondent Municipal Corporation, Ujjain invited tender for the construction of a Wrestling Arena in Sheer Sagar Stadium, Ujjain. The petitioner submitted a bid which was accepted on 11.3.2003. An agreement was executed between the parties on 22.4.2003 for the total amount of the contract of Rs.90,00,000/-. The petitioner was served with the work order dated 19.5.2003 with the direction to complete the work within 11 months. Vide letter dated 10.3.2006, the petitioner informed the respondent that it will not be possible to make any progress in the work for want of payment/running bill. The respondent vide letter dated 24.3.2006 directed the petitioner to complete the work otherwise same would be completed by some other agency at the risk and cost of the petitioner. The petitioner replied to the aforesaid letter by submitting that he is ready to start the work if outstanding payments are made.

2.2 Vide letter dated 8.8.2006, the Executing Engineer of the respondent terminated the agreement of the petitioner which was served upon the petitioner on 7.9.2006. The petitioner submitted a reply to the notice vide letter dated 8.9.2006 but the respondent issued a tender for the rest of the work to some other agency without making a final measurement of the work done by the petitioner. Being aggrieved by the aforesaid action the petitioner approached the Madhya Pradesh Arbitration Tribunal by filing a reference case on 7.3.2008 claiming the amount of Rs.35,37,945/- along with an interest at the rate of 18% per annum from the date of presentation of reference till payment. The aforesaid amount was claimed on the following counts:

Claim No. 1

Remaining amount of 4th running bill and full amount of 5th running bill

Rs. 10,31,862/-

Claim No. 2

Disallowed amount of 5th running bill and amount of work of which measurement was not taken

Rs. 4,82,310/-

Claim No. 3

 

Loss because of idle labour, machinery and other material for about 16 months

Rs. 10,00,000/-

Claim No. 4

Loss of interest @ 10% p.a. On amount of remaining work which the petitioner could not execute as the contract was rescinded

Rs. 4,51,657/-

Claim No. 5

Amount of labour cess illegally deducted from the bills

Rs. 40,011/-

Claim No. 6(A)

Interest on the amount paid belatedly

Rs. 42,000/-

Claim No. 6(B)

Interest @ 12% p.a. For 32 months on Rs. 10,31,862/- (Amount of Claim No. 1)

Rs. 3,30,196/-

Claim No. 6(C)

Interest @ 12% p.a. On Rs. 4,82,310/- (Amount of final bill) for 30.5 months

Rs. 1,47,105/-

Claim No. 6(D)

Interest @ 12% p.a. On Rs. 40,011/- (Amount of illegally deducted labour cess) for 32 months

Rs. 12,804/-

 

Total

Rs. 35,37,945/-

2.3 After notice respondent filed a written statement denying all the claims of the petitioner alleging breach of terms and conditions of the agreement. According to the respondent, the petitioner himself abandoned the work on 25.6.2004 and the balance of work got to be executed by a debitable agency. It has further been alleged that the petitioner did not submit a bank guarantee for three years as per Clause 67(2) and 67(10) of the agreement. The bank guarantee so submitted by the petitioner was valid for one year which came to an end on 27.10.2004, therefore, the amount payable vide the fourth bill, running bill has been adjusted against the bank guarantee. However, the respondent did not submit any counterclaim before the tribunal. The respondent has raised an objection that the refe

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top