IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD
Surepalli Nanda, J.
M/s Suryodaya Infra Projects (I) Pvt. Ltd. - Petitioner
Versus
Union of India and others - Respondents
W.P. No. 21417 of 2023
Decided On : 11-09-2023
| Table of Content |
|---|
| 1. overview of the substantive case facts (Para 2 , 3) |
| 2. contentions of the parties regarding obligations (Para 4 , 5 , 6 , 8) |
| 3. court's reasoning related to jurisdiction and remedies (Para 9 , 10 , 12 , 13) |
| 4. final dismissal of the writ petition with no merit (Para 14 , 24) |
| 5. critical examination of alternative remedies and legal rights (Para 15 , 16 , 17 , 18 , 20 , 21 , 22 , 23) |
ORDER :
Heard Dr Anurag Kumar Agarwal, Senior counsel appearing on behalf of Mr. Pasham Mohit, Learned Counsel representing the petitioner, Mr. Damodar Mundra, learned Counsel appearing for Respondent No.3. Sri Gadi Praveen Kumar, Deputy Solicitor General of India, learned Counsel appearing for Respondent No.1 and Sri R.Raghava Chary, learned counsel appearing for Respondent No.2.
2. This Writ Petition is filed praying to issue a Writ of Mandamus, declaring the actions of the 2nd Respondent in releasing and making payments to the 3rd Respondent in spite of being aware of the actions of the 3rd Respondent in not making payments to the Petitioner, i.e. the authorized subcontractor contrary to the terms of the Work Order dated 06.12.2018 as illegal, arbitrary and unconstitutional and consequently direct the 2nd Respondent to make payments to the tune of IN 2,90,00,000/- to the Petitioner directly towards the outstanding amounts under the Work Order dated 06.12.2018 arising out of Contract dated 10.11.2016 vide Agreement No. ED/(E&P)/ SP-III/RWLS/PKG-10/132.
3. The case of the Petitioner, in brief, is as follows:
b) While so, the 2nd Respondent has awarded Contract dated 10.11.2016 vide Agreement No. ED/(E&P)/ SPIII/RWLS/PKG-10/132 for establishment of Rapid Wagon Loading System (RWLS) in the state of Chhattisgarh in favour of the 3rd Respondent on EPC basis. However, as the 3rd Respondent did not possess necessary credentials and experience to execute civil works components and had sub-contracted all civil works to one M/s. K.A. Pappachan Constructions on back-to-back sub-contract basis.
c) However, due to non-payment of outstanding dues against work done by the M/s. K.A. Pappachan Constructions and Petro (P), Kirandul, the said subcontractor left the project midway without finishing the work assigned and thus, the 3rd Respondent had approached the Petitioner and requested the Petitioner to carry out civil works for establishment of RWLS and feeding conveyer systems.
d) Pursuant to mutual discussion and deliberation, the 3rd Respondent issued a Work Order dated 06.12.2018 for construction of civil works at NMDC project for establishment of RWLS and feeding conveyer systems in favour of the Petitioner. Thereafter, the Petitioner had issued a letter dated 15.12.2018 to the 3rd Respondent communicating its acceptance of the Work Order dated 06.12.2018 subject to the conditions mentioned in the letter.
e) Subsequently, the Petitioner had commenced its works under Work Order dated 06.12.2018 and had further executed a Corporate Guarantee dated 26.03.2019 towards advance payment of amount IN 20,00,000/- in favour of the 3rd Respondent. Therefore, the Petitioner has at all times acted in a bonafide manner and performed its contractual obligations in a timely manner.
f) The Petitioner had immediately commenced the initial work at project site and raised R.A. Bill No. 1 with regard to the initial work executed by the Petitioner. Accordingly, the Petitioner had issued letter dated 29.04.2019 requesting the 3rd Respondent to release amounts to the tune of IN 59,63,8
C.V. Rao & Ors v. Strategic Port Investment
Lanco Infratech Ltd. v. HCC Ltd. (2016) 234 DLT 175
M/s. Radhakrishan Industries vs. State of Himachal Pradesh
Oil & Natural Gas Commission Vs. Utpal Kumar Vasu & Others
Ramantech & Proceess Engineering Company & Another Vs. Solanki Traders
Rite Approach Group Ltd. v. Rosoboronexport
Satyapal Anand Vs. State of Madhya Pradesh & Others
Silppi Constructions Contractors vs. Union of India & Another
State of Bihar vs. Jain Plastics & Chemicals Ltd.
The extraordinary jurisdiction of this Court can be exercised in view of the admission made by the 3rd respondent regarding payments to be payable to the petitioner.
Contractual agreement - Whether existence of arbitral agreement between parties that High Court of Delhi alone will have jurisdiction to try dispute arising out of contract is enforceable in law - Un....
The High Court has the jurisdiction to entertain a writ petition involving disputed questions of fact in contractual matters with the State and its instrumentalities.
The significance of admitted liabilities, conflicting stands, and serious disputed questions of fact in contractual matters, and the discretion of the court in exercising jurisdiction.
(1) Disputes arising out of purely contractual obligations cannot be entertained by High Court in exercise of extra-ordinary writ jurisdiction.(2) A wrong doer ought not to be permitted to make profi....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.