SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Telangana) 1999

IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD
K.SUJANA, J.
Rajesh Agarwal & Another – Petitioners
Versus
The State of Telangana, Through P.S. Central Bureau of Investigation – Respondent 
Criminal Revision Case No.522 of 2022 
Decided On : 22-12-2025

Advocates:
Advocate Appeared:
For the Appellant : Chandrasen Law Offices
For the Respondent: T Srujan Kumar Reddy Sc For Cbi

The court ruled that a contractor cannot be criminally liable for the actions of a subcontractor without credible evidence of conspiracy or wrongdoing, leading to the discharge of the accused.

Headnote:(A) Criminal Procedure Code, 1973 - Section 239 - Discharge of accused - The petitioners challenged the trial court's refusal to discharge them from a criminal case regarding a Bank Guarantee fraud which they were alleged to have participated in - The nature of contractor-subcontractor relationship defended, highlighting non-culpability in actions of subcontractor and absence of malafide intent - Allegation of conspiracy dismissed based on lack of direct involvement and evidence - Discharge ordered due to insufficient grounds for framing charges under Sections 120B, 420, and 471 IPC. (Paras 2, 21)

Facts of the case:
The petitioners, as Managing Director and Company of a contractor, were implicated in a fraud concerning a Bank Guarantee for Rs. 5 Crores, which was invoked based on alleged poor performance of a subcontractor, resulting in accusations of cheating against them. (Paras 1, 2)

Findings of Court:
The trial court's order dismissing the application for discharge is erroneous as the material did not establish prima facie evidence of conspiracy or criminal intent on part of the petitioners. Therefore, they are entitled to discharge from the criminal charges. (Paras 20, 21)

Issues: The main issue revolved around the legality of invoking the Bank Guarantee and the nature of the petitioners' involvement in the alleged conspiracy and fraud. (Paras 3, 12)

Ratio Decidendi: The court reasoned that the relationship between the petitioners and the subcontractor could not attract criminal liability, as the evidence indicated failures predominantly resided with the subcontractor, not the petitioners, reaffirming the statutory principle of requiring credible evidence of conspiracy to justify charges. (Paras 11, 21)

Result: Petitioners discharged from the criminal case.

Table of Content
1. overview of the case and parties (Para 1 , 2)
2. arguments relating to subcontracting and mobilization advance (Para 3 , 4 , 5 , 6 , 7)
3. claim of innocence and false allegations (Para 8 , 12 , 13 , 14)
4. court's recognition of prima facie evidence (Para 9 , 10)
5. further evidence and counterarguments from respondents (Para 15 , 16 , 18 , 20)
6. discussion on financial liabilities and bank guarantees (Para 17)
7. final ruling on discharge of petitioners (Para 21)

ORDER :

This criminal revision case is filed by the petitioners/A.14 and A.15 aggrieved by the order dated 04.08.2022 in Crl.M.P.No.59 of 2022 in C.C.No.28 of 2015 on the file of III Additional Special Judge for Trial of CBI Cases, Hyderabad. The petitioners herein have filed Crl.M.P.No.59 of 2022 under Section 239 Cr.P.C, praying the trial Court to discharge them from the above criminal case.

2. The facts of the case are that the 1stpetitioner was arrayed as A.14 in his individual capacity, as he was the Managing Director of 2nd petitioner-Company, which was arrayed as A.15 and represented by its Managing Director in C.C.28 of 2015. The petitioners alleged that based on a complaint given by the Zonal Manager of UCO Bank, Hyderabad to the DIG of Police, ACB, CBI, Hyderabad, a crime was registered in RC.15(A)/2013- CBI/Hyderabad. The CBI investigated the matter and filed a charge sheet against 15 accused attributing specific roles to each of them. The 1stpetitioner, Managing Director of M/s.ARSS Infrastructure Projects Limited, Bhubaneswar, and the 2ndpetitioner- M/s. ARSS Bhubaneswar represented by its Managing Director, entered into a criminal conspiracy with A.2, Managing Director of M/s.SSVG Engineering Projects Pvt. Ltd.- A.3 (for short ‘SSVG’), to cheat UCO Bank, Banjara Hills Branch, Hyderabad. In pursuance of the conspiracy, A.2 obtained a fake Bank Guarantee for Rs.5 Crores in the name of A.15 Company. The 1st petitioner/A.14 dishonestly invoked the Bank Guarantee and fraudulently received Rs.5 Crores. The investigation revealed that the 2nd petitioner entered into a contract on 21.02.2009 with M/s. SSVG Hyderabad. In this connection, they submitted the Bank Guarantee format, a copy of Civil Contract Volume-1 between the Government of Odisha and Som Datt ARSS J.V. dated 03.11.2008, and other documents such as the Special Power of Attorney given by H.G. Advani dated 13.11.2008 in favour of S.P. Dash, the lawful attorney holder, and the Letter of Acceptance dated 27.09.2008. These documents were made available to M/s. SSVG, which in turn submitted them to UCO Bank, Banjara Hills Branch, Hyderabad. After receiving the Performance Bank Guarantee (PERFORMANCE BANK GUARANTEE) for Rs.5 Crores, M/s. ARSS Infrastructure Projects Limited, Bhubaneswar, and M/s. SSVG, Hyderabad, scrapped the sub-contract dated 10.03.2009 and entered into another sub-contract dated 09.04.2009.Under this contract, M/s. ARSS Infrastructure Projects Limited offered the work of widening and strengthening the existing carriageway to two lanes for Bhadrak–Chandbali part of package No. P02, from 0 to 45 km in SH-9 of the Government of Odisha worth Rs.100 Crores to M/s. SSVG, Hyderabad. The investigation further revealed that M/s. ARSS Bhubaneswar had not obtained permission from the employer, Government of Odisha, or from the Chief Engineer of the Project, SMEC International Pvt. Ltd. Thus, M/s. ARSS Bhubaneswar violated the special and general conditions of the main contract.The petitioners further stated that they were innocent of the offences alleged against them and that a false case had been foisted. They argued that the allegation regarding the absence of a provision for mobilization advance was incorrect. From the contract agreements dated 21.02.2009 and 10.03.2009, there was a separate head titled "Mobilization Advance." In fact, the works contract entered into between the J.V. Company and the Government of Odisha contained Clause 14.2 under the heading "Advance Payment," w

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top