IN THE HIGH COURT OF DELHI AT NEW DELHI
AVNEESH JHINGAN, J.
Zreyah Semiconductors Pvt. Ltd. – Petitioner
Versus
Oyo Hotels And Homes Pvt. Ltd. – Respondent
O.M.P. (COMM) 249 of 2023 & I.A. 14284 of 2025
Decided On : 02-02-2026
| Table of Content |
|---|
| 1. petitioner's case based on arbitral award. (Para 1 , 2) |
| 2. petitioner's claim of being an assembler. (Para 3) |
| 3. respondent's defense and interpretations. (Para 4) |
| 4. court reviews arguments presented. (Para 5) |
| 5. controversy on advance payment. (Para 6) |
| 6. interpretation of vendor agreement clauses. (Para 7 , 8) |
| 7. acceptance criteria based on contract terms. (Para 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16) |
| 8. standard for judicial review of arbitration awards. (Para 19) |
| 9. conclusion on petition dismissal. (Para 20 , 21) |
JUDGMENT :
AVNEESH JHINGAN, J.
1. M/s Zreyah Semiconductors Private Limited has filed the petition under Section 34 of the Arbitration and Conciliation Act, 1996 (for short 'the Act') aggrieved of the arbitral award dated 03.04.2023.
FACTS
2. The brief facts are that the petitioner is engaged in the business of manufacturing and supply of electronic components. The respondent is a Private Limited Company engaged in the business of managing hospitality establishments. The respondent placed a purchase order dated 26.09.2019 upon the petitioner (hereinafter 'the PO') for supply of 52360 switches valuing Rs.10,34,89,540/-, inclusive of taxes. Subsequent to the placement of the PO, the parties entered into a vendor agreement dated 23.12.2019 (hereinafter 'the VA'). The PO though prior in time was governed by the terms and conditions of the VA. After the placement of the PO the respondent paid an advance of fifty percent of the invoice value.
2.1 Prior to the placing of the PO, the parties had business transactions wherein the petitioner was assembling switches for the respondent and the entire material was being supplied by the respondent. The scenario changed and pursuant to the PO the petitioner had to procure the components for the switches and five major components were to be procured from vendors specified by the respondent in Schedule 'A' to the VA.
2.2 A dispute arose between the parties due to non-delivery of the switches and arbitration proceedings as provided under the VA were initiated at the instance of the respondent. The arbitrator framed the following issues:
(i) Whether the respondent has committed the breach of the Vender Agreement dated 23.12.2019? If so, its effect.
(ii) Whether the respondent has committed the breach of the P.O.s dated 26.09.2019 and 22.09.2020? If so, its effect.
(iii) Whether the claimant is entitled to the reliefs as claimed in the SOC?
2.3 The arbitrator after considering the pleadings and appreciating the evidence adduced directed the petitioner to deliver 11000 switches claimed to be ready and to pay Rs.2,84,00,000/- along with interest at the rate of nine percent per annum.
CONTENTIONS
3. Learned counsel for the petitioner relies upon clauses 2.1, 2.3 and 3.1 of the VA to contend that the petitioner was an assembler and not a manufacturer, the arbitrator erred in holding that the petitioner was a manufacturer. Reliance is placed upon the correspondence between the parties to show that the terms and conditions of the Chinese vendors (hereinafter 'the vendors') were provided by the respondent to the petitioner. It is submitted that clause 12.1 of the VA relied upon by the arbitrator deals with liability of petitioner towards employees and not with the nature of relationship between the parties and it was wrongly recorded that there was a principal to principal relationship between the parties.
3.1 It is argued that the arbitrator relying on clause 14.10 concluded that all prior discussions, negotiations and agreements were superseded by the VA, if this is taken to its logical end the PO no longer existed and consequently no liability could be casted upon the petitioner.
3.2 The averment is that some of the components were to be procured from the vendors identified by the respondent and the advance amount was to be paid by the respondent for these procurements. On failure of the respondent to make hundred percent advance payment the components could not be procured and the switch
Prakash Atlanta (JV) v. National Highways Authority of India
Ramesh Kumar Jain v. Bharat Aluminium Company Limited (BALCO)
Parsa Kente Collieries Limited. v. Rajasthan Rajya Vidyut Utpadan Nigam Limited
AI
The court upheld the arbitrator's decision, affirming that the interpretation of contractual obligations did not warrant judicial interference under Section 34 of the Arbitration Act.
The interpretation of contractual clauses by an Arbitrator cannot be interfered with unless it is unreasonable or against settled legal principles.
The court affirmed that limited judicial review under Section 34 of the Arbitration Act does not allow for re-evaluation of arbitration awards unless they are demonstrably perverse, illegal, or devoi....
The court affirmed that arbitral awards may only be set aside under specific grounds stated in Section 34, emphasizing judicial restraint from reevaluating evidence or merits beyond legal provisions.
The court upheld the Arbitrator's findings that the rescission of the contract was unjust and delays were primarily attributable to the petitioner, affirming the award under Section 34 of the Arbitra....
An arbitral award may be set aside if it ignores the express terms of the governing agreement or imposes obligations not agreed upon, constituting a patent illegality.
The court affirmed that the lack of explicit contract terms for advance payments and preconditions led to a ruling of breach by the appellant, validating the Arbitral Tribunal's awards for excess pur....
The court emphasized that an arbitral award must be reasoned and address core contractual issues, with judicial intervention restricted to cases of patent illegality under Section 34 of the Arbitrati....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.