HIGH COURT MALAYA KUALA LUMPUR
KHARISMA WIRA SDN BHD – Appellant
Versus
KETUA SETIAUSAHA KEMENTERIAN PERTAHANAN MALAYSIA & ORS – Respondent
[Orginating Summons No: WA-21NCC-5-11-2022]
Key Points: - (!) (!) (!) - (!) (!) - (!) (!) - (!) (!) - (!) (!) - (!) (!) - (!) (!) - (!) (!) - (!) (!)
| Table of Content |
|---|
| 1. injunctions sought under arbitration act. (Para 1 , 2) |
| 2. background of the contract and related disputes. (Para 3 , 4 , 5 , 6 , 7) |
| 3. plaintiff argues bad faith in bond call. (Para 8) |
| 4. defendants contest injunction application. (Para 9 , 10) |
| 5. legal foundation for interim measures under arbitration act. (Para 11 , 12 , 13 , 14 , 15) |
| 6. court's jurisdiction to grant injunction against government. (Para 16 , 17 , 18) |
| 7. legal provisions against granting injunctions to government. (Para 19 , 20 , 21 , 22 , 23) |
| 8. court's interpretation of binding authority. (Para 24 , 25 , 26) |
| 9. court adheres to precedent despite evolving law. (Para 27 , 28 , 29) |
| 10. court dismisses os due to lack of jurisdiction. (Para 30 , 31) |
| 11. unconscionability not established; contractual disputes remain. (Para 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39) |
| 12. public interest favors government's duty performance. (Para 40 , 41 , 42 , 43 , 44 , 45 , 46) |
| 13. judgment concludes with dismissal of plaintiff's claims. (Para 47) |
Introduction
[1] This Amended Originating Summons ("OS") was filed on 17 November 2022 by the Plaintiff against the Defendants for interim measures as follows pursuant to s 11 Arbitration Act 2005 as the contract between the parties contains an Arbitration Agreement:
1.1 An injunction to restrain Defendants from claiming the full or partial amount of the Performance Bonds below until disposal of the Arbitration proceeding:
a. Bank Guarantee No 08136160262 for Bon Pelaksanaan (Kontrak/ Bekalan/ Perkhidmaan) amounting RM398,500.00 dated 29 November 2016 through Bank Islam Malaysia Berhad ("Contract Performance Bond"); and
b. Bank Guarantee No 08136160266 for Bon Pelaksanaan (Kontrak/ Bekalan/ Perkhidmatan) amounting to RM3,000,000.00 dated 5 December 2016 through Bank Islam Malaysia Berhad ("Performance Bond for Advance Payment") issued.
(collectively "the Performance Bonds")
1.2 An injunction to restrain Defendants from receiving the proceeds of the Performance Bonds from Bank Islam Malaysia Berhad until the disposal of the Arbitration proceeding together with costs.
[2] I had on 17 April 2023 dismissed the OS with costs to the 4th Defendant and given broad reasons for my decision. This judgment contains the full reasons for my decision.
Background
[3] The background facts are culled from the affidavits and submissions of the parties.
[4] The Plaintiff and the Government of Malaysia, the 4th Defendant herein had entered into a Contract dated 27 March 2017 ("the Contract") for the supply, delivery, testing and commissioning of 2 units of Air Droppable Rescue and Survival System (ADRSS) ("the Articles") for the benefit of the 3rd Defendant "berdasarkan kepada kadar harga dan deskripsi yang dinyatakan di dalam Jadual No 1 syarat-syarat kontrak dengan mengikut spesifikasi kerajaan seperti di Jadual 2A kepada Kontrak ini berdasarkan Pesanan Rasmi yang dikeluarkan oleh Kerajaan mengikut Klausa 8 dan menyediakan latihan dan dokumentasi berkenaan tatacara pengoperasian dan selenggaraan bagi Artikel mengikut terma dan syarat Kontrak ini".
[5] The agreed contract period was for two (2) years starting on 24 November 2018 ending 23 November 2020. Clause 32 of the Contract provides that all disputes between the parties not resolved amicably shall be referred to arbitration.
[6] Two (2) Final Acceptance Tests ("FAT") were conducted for the Articles. It was alleged by the Government that both Tests failed. The Contract was terminated on 7 March 2022 under cl 28 of the conditions of contract. Following the termination of the Contract on 7 March 2022, the 3rd Defendant issued a Notice of Liquidated & Ascertained Damages ("Notice of LAD Claim") on 22 August 2022, and by letter dated 14 November 2022, called on the Performance Bonds.
[7] The Plaintiff swiftly responded by filing this OS.
Plaintiff's Case
[8] The Plaintiff argued that the call on the Performance Bonds is made in bad faith, unfair and unconscionable due to:
8.1 Wrongful Termination
SPM Membrane Switch Sdn Bhd v. Kerajaan Negeri Selangor
Government of Malaysia v. Lim Kit Siang
Tan Bun Teet & Ors v. Menteri Sains, Teknologi Dan Innovasi Malaysia & Ors
Sumatec Engineering & Construction Sdn Bhd v. Malaysian Refining Company Sdn Bhd
Esso Petroleum Malaysia Inc v. Kago Petroleum Sdn Bhd
Ranhill E&C Sdn Bhd v. Thyssenkrupp Industries (M) Sdn Bhd & Anor
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.