SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Rajiv Sahai Endlaw, Amit Bansal, JJ.
C & C Constructions Ltd. - Appellant
Versus
Ircon International Ltd. - Respondent
FAO(OS) (COMM) 36 of 2021
Decided On : 01-03-2021




The court upheld the finality of the arbitral award, emphasizing limited grounds for interference under Section 37 of the Arbitration and Conciliation Act, reaffirming that claims barred by contract terms do not necessitate an opportunity to lead evidence.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 37 - Application under Section 34 dismissed - Appellant challenged arbitral award that denied claims under Clause 49.5 of General Conditions of Contract - Court finds no grounds for setting aside the award - Scope of interference under Section 37 is limited compared to Section 34. (Paras 3-18)

(B) Principles of Natural Justice - No absolute entitlement to lead evidence - Dismissal of claims not in violation of natural justice if claims were evidently barred. (Paras 8-9)

Facts of the case:
The appellant appealed against the dismissal of their application to set aside an arbitral award that denied 15 claims for damages based on a contractual clause limiting liability for delays.

Findings of Court:
Claim barred under the contract, and no violation of principles of natural justice found in summary dismissal.

Issues: Whether claims were maintainable despite Clause 49.5 and if the Arbitral Tribunal denied principles of natural justice.

Ratio Decidendi: The claims were inherently barred by the terms of the contract; summary dismissal did not infringe on principles of natural justice.

Result: Appeal dismissed.

Table of Content
1. the application under section 34 challenges an arbitral award. (Para 3 , 4)
2. appellant contends claims were wrongly dismissed under clause 49.5. (Para 5 , 6 , 7)
3. court's analysis on natural justice and its application. (Para 8 , 9 , 11)
4. debate on validity and implications of clause 49.5. (Para 10 , 12 , 13 , 14)
5. scope of the court's interference under section 37 is limited. (Para 16)
6. appeal dismissed with no further grounds for interference. (Para 17 , 18)

JUDGMENT

[VIA VIDEO CONFERENCING]

Rajiv Sahai Endlaw, J.

CM No.8193/2021 (for exemption)

1. Allowed, subject to just exceptions and as per extant rules.

2. The application is disposed of.

FAO(OS) (COMM) No.36/2021

3. This appeal under Section 37 of the Arbitration and Conciliation Act, 1996 impugns the judgment/order dated 15th December, 2020 of the Commercial Division of this Court of dismissal of application of the appellant under Section 34 of the said Act.

4. The application under Section 34 of the Act, being OMP(COMM) No.566/2020, was filed with respect to arbitral award dated 21st December, 2019 (of three Arbitrators, with the appellant and the respondent having nominated one Arbitrator each and the third Arbitrator having been appointed by this Court) of dismissal, in exercise of powers under Section 16 of the Act, of all the claims of the appellant.

5. It is the contention of the counsel for the appellant that the Arbitral Tribunal, on an application under Section 16 of the Act having been preferred by the respondent, has summarily dismissed all the 15 monetary claims for recovery of compensation/damages, of the appellant against the respondent, with respect to the Contract for `Construction of Road Over Bridges (ROBs) & its approaches as per Specifications, Drawing & Design, Maintaining all Quality Control Standards etc. complete under ROB Cluster Package in Lieu of various LCs at Jaipur' entered into by the respondent with the appellant.

6. The counsel for the appellant has drawn our attention to Clause 49.5 of the General Conditions of Contract, invoking which the application under Section 16 of the Act was filed by the respondent. As per the said clause, in the event of any failure or delay on the part of the respondent or the engineer in fulfilling their obligations under the contract, such failure or delay on the part of the respondent or the engineer was not to in any way affect or vitiate the contract or alter the character thereof or entitle the appellant to damages or compensation therefor except that the engineer shall grant such extension or extensions of time to complete the work as in his opinion was reasonable. It was the plea of the respondent in its application under Section 16 of the Act, that all the 15 monetary claims of the appellant were barred and/or not maintainable under Clause 49.5 of the General Conditions of Contract.

7. The counsel for the appellant has contended that the Arbitral Tribunal ought to have granted the appellant an opportunity to prove that the claims of the appellant were not barred by Clause 49.5 of the General Conditions of Contract. Attention is drawn to Clause 49.4 of the General Conditions of Contract which deals with delays not due to employer/contractor but on the part of the third parties or on the part of the Court orders. The contention of the counsel for the appellant is that all the 15 claims of the petitioner fall under Clause 49.4. On further enquiry, as to under which clause of Section 34 of the Arbitration Act the appellant justifies setting aside of the award, it is contended that the claim of the appellant falls under Section 34 (b)(ii), whereunder an arbitral award is liable to be set aside if is in conflict with the public policy of India. It is argued that opportunity to lead evidence is the public policy of India and summary dismissal of claims under Section 16 , as barred by Clause 49.5, is in denial of principles of natural justice.

8. Though according to us there is

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top