Where to File Complaint Against Builder for BBA and Zonal Plan Violations Under RERA?

Choosing Between the RERA Authority and Adjudicating Officer for BBA and Zonal Plan Breaches

Homebuyers who discover that a promoter has breached the Buyer-Builder Agreement (BBA), deviated from sanctioned plans, or violated zonal regulations often face a practical dilemma: should the complaint be filed before the RERA Authority or before the Adjudicating Officer? Section 31 of the Real Estate (Regulation and Development) Act, 2016, permits an aggrieved person to approach either forum, but the correct choice can determine whether the complaint survives at first hearing. Understanding the statutory division of functions between these two bodies is essential before initiating proceedings.

The Short Answer: Approach the RERA Authority First

A complaint alleging violation of BBA terms and zonal plans should generally be filed before the Real Estate Regulatory Authority, not the Adjudicating Officer. The Authority is the primary forum empowered to determine breaches of the Act, the rules, and the regulations. Only after the Authority has found a breach may the question of compensation be referred to the Adjudicating Officer under Section 71.

This division of labour is not merely procedural. Courts have repeatedly cautioned that when an Adjudicating Officer assumes the role of the Authority, it exceeds its jurisdiction and its orders may be quashed 2023 0 Supreme(Guj) 371 and 2021 0 Supreme(Bom) 804.

Why the Authority Holds the Primary Jurisdiction

The Authority enjoys wide-ranging statutory powers covering the full spectrum of violations:

Section 31(1) expressly provides that any aggrieved person may file a complaint with the Authority or the adjudicating officer, as the case may be, for any violation or contravention of the provisions of the Act or the rules and regulations made thereunder, against any promoter, allottee, or real estate agent 2025 0 Supreme(P&H) 12 and 2025 0 Supreme(P&H) 1002. In the case of sanctioned building plans and layout deviations, the Authority is the body equipped to investigate and direct remedial action 2025 0 Supreme(P&H) 1002 and 2026 Supreme(Online)(Gau) 6987.

The Adjudicating Officer's Narrow Mandate: Compensation Only

The Adjudicating Officer, appointed under Section 71(1), exists for one specific purpose — adjudging compensation under Sections 12, 14, 18, and 19 of the Act 2003 0 Supreme(Bom) 1358 and 2021 0 Supreme(Bom) 804. Key features of this limited role include:

  1. The Authority decides all questions of breach of the Act, Rules, and Regulations, and then refers the compensation question to an Adjudicating Officer on its panel, who decides the matter preferably within 60 days 2021 8 Supreme 15.
  2. These compensation provisions do not impose any liability on the allottee to pay compensation, nor do they confer any right on the promoter to claim compensation from an allottee 1974 0 Supreme(SC) 388.
  3. The power exercised by the Adjudicating Officer is non-delegable — it cannot be exercised by any member or officer of the Authority under Section 81 2021 8 Supreme 15.

Judicial decisions have enforced this boundary strictly. In one matter, the court held that the Adjudicating Officer exceeded its jurisdiction by assuming the Authority's role of restoring possession, since only the Authority could pass such orders under the complaint procedure in Form-A 2023 0 Supreme(Guj) 371. Similarly, where an Adjudicating Officer entertained a complaint concerning a project that did not require registration, the High Court quashed the order, reaffirming that registration determinations lie solely with the Authority 2021 0 Supreme(Bom) 804.

Refund Versus Compensation: Two Distinct Claims

The Act treats refund of the amount and compensation as two distinct components that an aggrieved allottee may claim, each with its own enquiry and mechanism under the Act 2021 8 Supreme 15. Refund and breach-related directions are matters for the Authority, while monetary compensation for loss flows through the Adjudicating Officer once the breach is established.

Notably, Section 71 also permits a complainant to withdraw a complaint pending before the Authority and refile it before the Adjudicating Officer in matters governed by Sections 12, 14, 18, and 19 — an option, though not the default route 2021 0 Supreme(SC) 23.

The Bar on Civil Court Jurisdiction

Reinforcing the RERA mechanism as the proper forum, Section 79 bars civil courts from entertaining suits where the Authority or Tribunal can determine the issue 2025 Supreme(Online)(Bom) 6175. Where disputes involve complex questions of fact and law — such as contested BBAs — High Courts typically direct parties to pursue the statutory appellate route before the Appellate Tribunal rather than invoking writ jurisdiction A) Real Estate (Regulation and Development) Act, 2016 - Section 18 and Section 43(5).

Practical Limitations to Keep in Mind

  • For unregistered projects incapable of registration under Section 3(2), the RERA framework may not apply, and remedies may lie outside RERA 2024 0 Supreme(Bom) 1089.
  • Complaints by persons who are not allottees, promoters, real estate agents, or registered voluntary consumer associations may fall outside Section 31's scope — for instance, landowners have been held not to be allottees under Section 2(d) 2026 0 Supreme(Bom) 427 and 2026 Supreme(Online)(Gau) 6987.
  • Non-registration of a project by the promoter does not, by itself, defeat an allottee's complaint; the Authority retains jurisdiction 2025 0 Supreme(P&H) 12.

Recommended Course of Action

  1. File first before the RERA Authority, framing the complaint under Section 31 and alleging violations of the Act's provisions, including BBA breaches and zonal/sanctioned plan deviations.
  2. Do not file directly before the Adjudicating Officer for breach determination; the Authority must first find the violation.
  3. Seek compensation through referral — once the Authority finds a breach, it will refer the compensation claim to the Adjudicating Officer under Section 71 2021 8 Supreme 15.
  4. Ensure the complainant qualifies as an aggrieved person — typically an allottee, promoter, real estate agent, or registered consumer association 2026 0 Supreme(Bom) 427.

Key Takeaways

The scheme of the RERA Act creates a two-tier adjudicatory structure: the Authority decides breaches of the Act, Rules, Regulations, BBAs, and zonal/sanctioned plan violations, while the Adjudicating Officer's jurisdiction is confined to compensation under Sections 12, 14, 18, and 19. Blurring this line can render an order vulnerable to being quashed. Filing the BBA and zonal plan complaint before the RERA Authority in the first instance is therefore the generally correct and strategically sound approach. This article reflects general legal information based on statutory provisions and precedents and should not be treated as advice for any specific matter.

#RERA #BuilderBuyerAgreement #RealEstateDispute #HomebuyerRights #ZonalPlanViolation
Chat Download
Chat Print
Chat R ALL
Landmark
Strategy
Argument
Risk
Chat Voice Bottom Icon
Chat Sent Bottom Icon
SupremeToday Portrait Ad
whatsapp-icon Back to top