What Causes Time to Be Set at Large in Construction Contracts and Why Employers Lose Damages Claims
A recurring dispute in construction projects is the question: in a construction contract, when is ? The answer matters enormously, because once time is set at large, the employer may lose the right to altogether — often the most valuable remedy available for delayed completion.
The Core Concept of
describes the situation where the original contractual ceases to be enforceable. Instead of being bound to complete by a fixed date, the contractor's obligation is replaced by an implied duty to complete the works within a
AHMAD ZAKI SDN BHD vs SEACERA CERAMICS SDN BHD - 2018 MarsdenLR 2794
Kining Exeton Sdn Bhd vs Majlis Perbandaran Kuantan and another - 2026 MarsdenLR 265536
.Time typically becomes at large in two main scenarios:
- by the employer that cause delay not covered by an (EOT) provision.
- Failure of the — such as an architect or superintending officer (SO) — to properly grant an where the delay warrants one.
The Behind the Doctrine
The doctrine is rooted in the : an employer cannot enforce a if, by their own act or omission, they prevented the contractor from meeting it. As the principle is commonly expressed, the employer cannot hold the contractor to a specified , if the employer has by act or omission prevented the contractor from completing by that date, and in that case the obligation to complete by the specified date is replaced by an implied obligation to complete within a
AHMAD ZAKI SDN BHD vs SEACERA CERAMICS SDN BHD - 2018 MarsdenLR 2794
.This reflects a basic fairness rule — no party should profit from its own wrong. Courts have applied the same logic where a lessor's non-disclosure of material site defects caused construction delays, holding that the party responsible for the delay could not then invoke delay penalties 2026 0 Supreme(Bom) 245.
Failure to Grant Extensions of Time
The most common trigger in practice is misadministration of the EOT machinery. The in Soh Beng Tee & Co Pte Ltd v Fairmount Development Pte Ltd2007 3 SLR 86 confirmed that time may be set at large due to where there is no contractual provision governing the situation or where the architect fails to properly grant an under the contract
MYGLAM SDN BHD vs MALAYSIAN TIMBER COUNCIL & ANOTHER CASE (ENCL 1) - 2023 MarsdenLR 917
. Where the SO improperly refuses an EOT in circumstances that warrant one, time for completion is set at largeMYGLAM SDN BHD vs MALAYSIAN TIMBER COUNCIL & ANOTHER CASE (ENCL 1) - 2023 MarsdenLR 917
.Failure to respond to EOT applications within the contractual timeframe can produce the same result
Majlis Bandaraya Pulau Pinang vs Sagamuda Civil Sdn Bhd - 2025 MarsdenLR 282094
, as can unconscionable refusal of a legitimate extension MYS0000002935.Departure from the Contractual Mechanism
Courts have also found where both parties, through their conduct, abandon the contract's extension procedure. In a dispute over the Chennai Airport metro station, repeated of time led the court to conclude that the parties had departed from the contractual EOT mechanism — time was set at large, the withheld from the contractor had to be refunded, and withheld amounts released 2020 0 Supreme(Mad) 32.
The Consequence for
(LAD) at a daily or weekly rate must run from a definite date. If the contractual has ceased to be the proper and no mechanism exists to substitute a new one, there is in such a case no date from which can run and the right to will have gone
THAMESA DESIGNS SDN BHD & ORS vs KUCHING HOTELS SDN BHD - 1993 MarsdenLR 909
. Arbitral and judicial decisions reflect the same reasoning: once time is set at large, the question of imposing did not arise 2002 0 Supreme(Del) 4, and LAD clauses may be invalidated because LDs are enforced by reference to a stipulated that can no longer be adhered to due to the employer's 2020 0 Supreme(Mad) 32.In practical terms, once time is at large the contractor still must finish within a — but where that reasonable period falls is a question of evidence, and courts have struggled to fix it where the evidence is insufficient
LA LEISURE PTY LTD vs SABRECRAFT MARINE SDN BHD & ORS
LA LEISURE PTY LTD vs SABRECRAFT MARINE SDN BHD & ORS
.The Important Limitation: Robust EOT Clauses
Time will not automatically be set at large. In , the held that by an employer do not set if the contract provides for extensions of time in respect of those very events
ESSTAR VISION SDN BHD vs KUPPS & SACHS (M) SDN BHD
. clauses historically exist precisely so as to obviate the consequence of time being set at large, since it would be inequitable to allow an employer to impose for delays the employer itself caused 2020 0 Supreme(Mad) 32.The practical focus, therefore, is usually on whether:
- The contract contains an express covering the delaying event.
- The architect or exercised (or failed to exercise) that power correctly.
Practical Takeaways for Contractors and Employers
- Contractors facing LD claims should first check whether an covers the delay and whether the administrator properly exercised it; if not, a time-at-large argument may defeat the LD claim entirely.
- Employers and administrators should process EOT applications diligently and within contractual timelines — silence or improper refusal risks setting and extinguishing LD rights
Majlis Bandaraya Pulau Pinang vs Sagamuda Civil Sdn Bhd - 2025 MarsdenLR 282094
. - Both parties should avoid informal, repeated that depart from the contractual mechanism, as this conduct itself can set 2020 0 Supreme(Mad) 32.
Key Takeaways
Time is at large when the becomes unenforceable — generally because of employer not covered by an EOT provision, or because the failed to properly grant an . The effect is that the fixed gives way to an implied obligation to complete within a , and can no longer run because there is no definite date from which to calculate them
THAMESA DESIGNS SDN BHD & ORS vs KUCHING HOTELS SDN BHD - 1993 MarsdenLR 909
AHMAD ZAKI SDN BHD vs SEACERA CERAMICS SDN BHD - 2018 MarsdenLR 2794
. However, a properly drafted and properly administered will usually prevent time from being set at largeESSTAR VISION SDN BHD vs KUPPS & SACHS (M) SDN BHD
. This article is general information about construction law principles and not specific legal advice; outcomes depend on the exact contract wording and facts of each case. #TimeAtLarge #ConstructionLaw #ExtensionOfTime #LiquidatedDamages #PreventionPrinciple