IN THE HIGH COURT OF CALCUTTA
Shekhar B. Saraf, J.
Mono Orion Foods India Limited – Petitioner
Versus
Syndicate Realtyinfra Private Limited – Respondent
G.A. No. 1 of 2021 & C.S. No. 165 of 2021
Decided On : 23-12-2021
Specific Relief Act, 1963 - Section 14 (b) and 14(3)(c)(i) - Indian Contract Act, 1872 - Section 55 - Agreement for Development Agreement for Development - Essence of contract – Suit for specific performance of a registered development – Contractual obligations – Claiming damages and compensation - Whether time is of essence of development agreement entered into by both parties – Petitioner incurred amount on account of the development work of subject premises along with amount towards security deposit against said development agreement between parties - As per accounts of petitioner, only in financial year 2018-2019 a cost of around was incurred by petitioner towards construction of the said premises - The work was being performed by petitioner till the demise of its nominee and/or director - Sanction plan for development of premises was granted on 2016 and same was due to expire on November 17, 2021 - Taking this into consideration petitioner was allowed an ad-interim order restraining respondent from creating any third party rights in respect of subject premises on November 16, 2021 and the same has been extended from time to time, lastly extended till December 31, 2021.
Finding of the court : As per Clause 3.2, agreement for development of the suit premises will remain in force till the time entire construction is completed. One may also refer to Clause 6.4 which contemplates that time period for identification of allocation may also be extended based on a mutual agreement between the parties - Development agreement is obviously a commercial contract that is to give benefit to both the parties especially since the developer gets a portion of the developed land and has option to sell and make profits from the same. In such an event, if a person is allowed to wriggle out of the contract at the very end, the entire purpose of the contract is frustrated. The new provisions of the Specific Relief Act, 1963 clearly delineates procedure to be followed by a court when allowing for specific performance of a contract. In my view, if this particular agreement is not allowed to be specifically performed, irreparable loss and injury would be a result of the same. Just because damages can be computed in the form of money spent by developer, it does not mean that specific performance cannot be given. Umpteen judgments of Hon'ble Supreme Court have highlighted this point and one need not go further into the same. Furthermore, the submissions with regard to Section 14(b) and 14(c) have already been discussed and rejected by me at paragraph 26 hereinabove. The judgments cited by the defendant/respondent have been distinguished by me on facts and on law and are clearly inapplicable to the present case.
Result : Application is allowed
JUDGMENT :
Shekhar B. Saraf, J.
Facts:
1. The plaintiff/petitioner has instituted the present suit being CS No. 165 of 2021, inter-alia, for specific performance of a registered development agreement entered into with the defendant/respondent on August 17, 2015 in respect of premises no. 1, Upper Wood Street, Kolkata, pursuant to which a Power of Attorney was given in favour of the Petitioner’s nominee Mahesh Kumar Agarwal (now deceased) on the same day i.e. August 17, 2015 for obtaining necessary sanctions and approvals from the KMC as well as other authorities for the purpose of carrying out the development work. This interlocutory application being G.A. No. 1 of 2021 has been filed for seeking a new Power of Attorney in favour of new Nominee of the plaintiff company and some other reliefs.
2. The petitioner incurred Rs. 5,70,33,888.90/- on account of the development work of the subject premises along with a sum of Rs. 5,00,00,000/- towards the security deposit against the said development agreement between the parties. As per accounts of the petitioner, only in the financial year 2018-2019 a cost of around Rs. 1,79,00,000/- was incurred by the petitioner towards construction of the said premises. The work was being performed by the petitioner till the demise of its nominee and/or director Mr. Mahesh Kumar Agarwal on April 3, 2020. Sanction plan for the development of the premises was granted on November 18, 2016 and the same was due to expire on November 17, 2021. Taking this into consideration the petitioner was allowed an ad-interim order restraining the respondent from creating any third party rights in respect of the subject premises on November 16, 2021 and the same has been extended from time to time, lastly extended till December 31, 2021.
Arguments:
3. Mr. Ranjan Bachawat, Senior Advocate appearing for the plaintiff argues that defendant is contractually obligated for specific performance of a registered development agreement dated August 17, 2015. It is the case of the petitioner that despite repeated reminders to the respondents/defendant to issue a fresh power of attorney in favour of the petitioner’s nominee, the respondent has failed and/or neglected to carry out its reciprocal obligation under the terms of the contract. It is further argued by the counsel for the petitioner that the Agreement for Development dated August 17, 2015 (hereinafter referred to as “the development agreement”) was never terminated. He further submits that the conduct of the parties shows that the contract still continues.
4. The petitioner avers that time is never the essence of contract in case of immovable property unless expressly provided by the parties to a contract. The petitioner places reliance on M/s. Hind Construction Contractors –v-State of Maharashtra reported in (1979) 2 SCC 70 to contend that the question whether or not time was of the essence of the contract would essentially be a question of the intention of the parties to be gathered from the terms of the contract. Thereafter, the petitioner states that the intention of the parties was to not make time the essence of the contract. Thus, the principle as laid down in the case of Hind Construction (supra) squarely applies.
5. Further, Mr. Bachawat, argues that specific performance in respect of contracts is no longer discretionary post the amendment of Specific Relief Act, 1963 and the same is governed by the new amended provisions of the Specific Relief Act, 1963. He relies on B. Santoshshamma and Another –v-D. Sarala and Another decided on September 18, 2020 in Civil Appeal Nos. 3574-3577 of 2009 to contend that the power of the Court to direct specific performance of an agreement may have been discretionary earlier but such power could not be arbitrary and it has to be exercised in accordance with sound and reasonable judicial principles. Another submission made by the petitioner is with regard to share in the contractual building i.e. 35% which he is entitled to as per Cla
Ambalal Sarabhai Enterprise Ltd. v. KS Infrapace LLP Limited & Anr.
Dorab Cawasji Warden v. Coomi Sorab Warden
Ferrodous Estates Pvt. Ltd. v. P. Gopiram (Dead) & Ors
Indira Kaur v. Sheo Lal Kapoor
Jamshed Khodaram Irani v. Burjorji Dhunjibhai
Jiwan Lal (Dr) v. Brij Mohan Mehra
Kalidas Ghosh v. Mugneeram Bangur and Co.
Keshavalal Lallubhai Patel v. Lalbhai Trikumlal Mills Ltd.
M/s. Hind Construction Contractors v. State of Maharashtra
Mademsetty Satyanarayana v. G. Yelloji Rao
S.V. Sankaralinga Nadar v. P.T.S. Ratnaswami Nadar
Saradamani Kandappan v. S. Rajalakshmi & Ors
Point of Law : An agreement for sale of immovable property purchaser can no longer take shelter under the principle that time is not of essence in performance of contracts relating to immovable prope....
In a contract for sale of immovable property, failure to perform within the stipulated time renders the suit for specific performance time-barred under the Limitation Act, as readiness and willingnes....
The main legal point established in the judgment is the requirement to prove readiness and willingness to perform essential terms of the contract within a reasonable time, the significance of the tim....
The court held that time is of the essence in contracts for the sale of land, and undue delay in filing for specific performance can negate entitlement to relief.
The main legal point established in the judgment is that the specific performance of an agreement of sale may be justified by the obligation to perform certain actions beyond the payment of considera....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.