SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1994 Supreme(SC) 458

SUPREME COURT OF INDIA
M.N.Venkatachaliah, C.J.I., K.Ramaswamy, J.
Union Of India
Versus
Jain Associates
Case No. : 2507-08 of 1994
Date of Decision : 4/19/94
Advocates Appeared: Das K.R. : Gupta D.P. : Rangaswamy Radha : Rao C.V.Subba : Sharma T.C. : Sorabjee Soli J. : Srimathy D. : Varma V.K.

Advocates:
C.V.SUBBA RAO, D.P.GUPTA, D.Srimathy, K.R.Das, Radha Rangaswamy, SOLI J.SORABJI, T.C.SHARMA, V.K.VARMA

Headnote:

Civil Procedure Code - Section 34 - Delay is condoned - Against original judgment - Contractor laid his claim – Claim of compensation - same principle was reiterated in - Section 29 of Act empowers court that where the award is for payment of money, to grant reasonable rate of interest on principal amount adjudged and confirmed in decree only from date of the decree. Section 34 Civil Procedure Code empowers court where there is a decree for payment of money to grant interest and future, till the date of - Since Section 29 of the Act enables the court to grant interest on principal amount adjudged in the award and confirmed in the decree only from the date of the decree, it carries a negative import with it that the court has no power to grant interest - High court, therefore, was not right in granting interest which the arbitrator himself had not granted – Held, In this court finding that the contract in question was illegal and prohibited by law and consequently award made under arbitration clause this court held that award was one and inseparable from rest of disputes covered by it and the disputes might not have legally and validly been referred whole award was rightly set aside - In this court found that it was impossible to sever the award since the arbitrator had committed not a mere error of fact or law in reaching its conclusion, the entire award was set aside - In this court held that where a severable part of an award cannot be given effect to for a lawful reason, there is no bar to enforce the part to which effect could be justly given - Same principle was reiterated in Upper Ganges Valley Electricity Supply Co - Electricity Board holding that the mere error which occurred in the award of the umpire relating to matter which is distinct and separate from rest of award part which is invalid being severable from that which is valid, there was no justification for setting aside the entire award - IT is clear from above facts and legal position that the arbitrator committed misconduct in non-application of his mind in deciding claims 11 and 12 - It being a non-speaking award, it is difficult to find whether he had applied his judicious mind in deciding which of the two claims the respondent would be entitled to, in particular, on the finding of High court in this behalf – Therefore award in respect of claims 11 and 12 is set aside - Order of the High court to award stands set aside. Since the counter-claim was not considered the matter requires determination - Accordingly rejection of the counter-claim would be treated as a nil award of the counter-claim and for the above reasons it stands set aside and the matter is remitted to be adjusted afresh of the High court granting interest is also set aside – Appeal allowed

Judgment

K. RAMASWAMY, J

(1) SPECIAL leave granted.

(2) THE respondent had entered into a contract on 7/1/1983 to construct 13 units of Type-V Quarters at the estimated cost of Rs. 27,34,000.00. He was to complete the construction and hand over possession on 13/8/1984. Despite extension of the time on 7 occasions, finally up to 30/6/1988, the construction was not completed resulting in termination of the contract. As up to 34th bill the appellant paid to the respondent a sum of Rs. 24,34,100.91 ps. towards the executed work. The contractor laid proceedings under Section 20 of the Arbitration Act, 1940 (for short the Act) for reference to arbitrate the disputes. The joint arbitrators appointed thereon entered upon reference on 10/4/1989 and nominated Mr A. Biswas, the second respondent as an umpire. Since the joint arbitrators could not make and publish the award within the time, the umpire was called upon to enter upon the reference. Accordingly on 25/4/1990 the umpire had entered upon the reference and made an interim award on 26/7/1990 for a sum of Rs. 6,02,000.00. The contractor laid his claim for a sum of Rs. 37,37,885.00. The appellant laid counter-claim for Rs. 9,49,701.50 ps. On 3/9/1990 the appellant requested the umpire to consider the counter-claim. On 4/9/1990, the umpire refused to consider the counter-claim on the ground of belated counter-claim. On request the time to make and publish the award was extended up to 31/1/1991. The umpire held finally sitting on 19-12-1990 (it is disputed across the bar by the contractor) and he made the award on 24/12/1990 for a sum of Rs. 24,18,320.00 in favour of the contractor. The umpire also awarded interest at 18% up to 10/4/1989 and post-award interest. He did not grant any pendente lite interest. The appellant challenged the award on diverse grounds under S. 30 and 33 of the Act. Ultimately the division bench of the Calcutta High court in Appeal No. 453 of 1991 dated 16/9/1992 confirmed the award for a sum of Rs 20,07,320.00 and awarded pendente lite interest. On a review, it was held by an order dated 4/2/1993 that the bench committed mistake in thinking that the umpire granted pendente lite interest and is a mistake of fact and law but had confirmed the pendente lite interest on its power. Thus these two appeals, with a delay of 137 days in filing the appeal against original judgment. The delay is condoned.

(3) THE learned Solicitor General contended that the division bench having held that the umpire committed illegality in awarding damages twice over on claims II and 12, though the contractor was entitled to damages only in respect of one claim, committed manifest error of law in upholding the entire award. The fact that the umpire had committed illegality in awarding damages twice over would indicate his non-application of judicious mind to the claims in an objective manner. In a non-speaking award it is difficult to decide how he adjudged the claims. Thereby he committed misconduct which entails the setting aside of the award as a whole and the doctrine of severability becomes inapplicable to the facts of this case. His next contention was that under clause 62 of the general conditions, certain matters were to be finally determined by the Railways and the arbitrator lacked jurisdiction to decide these claims and thereby the award gets vitiated by manifest illegality on its face. There was sufficient time for the arbitrator, even after the extended time to make the award in respect of the counter-claim. But was not done, which would also prove the non-application of judicious mind in an objective and dispassionate manner and thereby the award gets vitiated by misconduct committed by the umpire. The 3rd contention is that the court lacked power to award pendente lite interest by operation of Section 29 of the Act. Shri Soli Sorabjee, the learned Senior Counsel for the respondent-contractor contended inter alia that though the award is a













Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top