2023 Supreme(SC) 882

SUPREME COURT OF INDIA
Dr. Dhananjaya Y. Chandrachud, CJI., Pamidighantam Sri Narasimha, J.B. Pardiwala, JJ.
Sushil Raghav – Appellant
Versus
Union of India & Ors. – Respondents
Civil Appeal No. 1629 of 2022
Decided On : 20-02-2023

Advocates Appeared:
Mr. Akash Vashishtha, Advocate, Ms. Neelam Singh, Advocate, for the Appellant; Ms. Aishwarya Bhati, ASG, Mr. Gurmeet Singh Makker, Advocate, Ms. Ruchi Kohli, Advocate, Ms. Swarupma Chaturvedi, Advocate, Mr. Manvendra Singh Rathore, Advocate, Dr. Arun Kumar Yadav, Advocate, Mrs. Niranjana Singh, Advocate, Mr. Avijit Roy, Advocate, Mr. Pradeep Misra, Advocate, Mr. Daleep Dhyani, Advocate, Mr. Suraj Singh, Advocate, for the Respondent.

The National Green Tribunal has the power under Section 25 to ensure compliance with its orders, and the absence of sewerage facilities is an important aspect that would merit the exercise of powers by the Tribunal under Section 25.

Headnote:

NGT - Environmental Law - The National Green Tribunal exercised its power under Section 25 to ensure compliance with its order to prevent discharge of untreated sewage and effluent, setting aside the Tribunal's observation that there was no case for executing the earlier order under Section 25 and restoring the execution application to the file of the National Green Tribunal.

Fact of the Case:

The appellant sought remedial action to prevent untreated sewage and effluent being discharged in storm water drains in a specific area. The Tribunal had issued an order with directions to address the issue.

Finding of the Court:

The Tribunal observed that the request made in the execution application went beyond what was stated in the order and suggested seeking remedy under Section 26. The court found that the Tribunal's observation that there was no case for executing the earlier order under Section 25 was misconceived and set aside the impugned order, restoring the execution application to the file of the National Green Tribunal.

Issues: The main issue was the exercise of power by the Tribunal to ensure compliance with its order to prevent discharge of untreated sewage and effluent, and the interpretation of Sections 25 and 26 of the National Green Tribunal Act 2010.

Ratio Decidendi: The Tribunal has the power under Section 25 to ensure compliance with its orders, and the absence of sewerage facilities is an important aspect that would merit the exercise of powers by the Tribunal under Section 25. The power to levy a penalty under Section 26 may not necessarily sub-serve the purpose of addressing the discharge of untreated sewage and effluent.

Final Decision: The appeal was allowed, the impugned order was set aside, and the execution application was restored to the file of the National Green Tribunal for further consideration under Section 25 to effectuate the original order.

ORDER

1. The appellant instituted OA No 68 of 2021 before the National Green Tribunal ['NGT'] for the purpose of seeking remedial action to prevent untreated sewage and effluent being discharged in the storm water drains in Karkarmodel, situated in Municipal Corporation Ward No 43 at Sahibabad in Ghaziabad.

    2. In its order dated 19 March 2021, the Tribunal noted that the issue had already been dealt with by it in an earlier order dated 27 January 2021 (Manoj Mishra vs Union of India and Others - OA No 6/2012). OA No 6 of 2012 related to remedial action required to prevent pollution of the river Yamuna and the drains and tributaries connected in Delhi, Haryana and Uttar Pradesh. In its order dated 19 March 2021, the Tribunal adopted various directions which are extracted below:

      '1. Independent assessment of flow in all the drains reaching Yamuna be undertaken within next two months and thereafter submit action plan for setting up STPs to bridge the gap with definite and monitorable timelines.

      2. Out of 427 MLD of treatment capacity in Sahibabad and Loni STPs with only 80 MLD capacity are compliant to standards. A direction to UP Jal Nigam, Ghaziabad MDA and Ghaziabad Municipal Corporations to upgrade/ rehabilitate the STPs to meet revised environmental standards of TSS/BOD:10/10 mg/L within next two years and the authorities being directed to submit Action plan to achieve this within next three months.

      3. Stoppage of all sewage from sewered areas of Sahibabad Banthala and Indira Puri as per the Action Plan prepared by the State Government by December 20.

      4. Implementation of Septage management by December 20 in all areas which are not sewered.

      5. UPSIIDC be directed to ensure setting up CETPs and ensure their proper functioning. UPPCB be directed to put in place policy for realizations in case the industries failed to pay. As requested by the UPPCB the arrears of unpaid EC be directed to be realized as arrears of land revenue.

      6. The YMC is unable to comment on the omnibus compendium submitted for NMCG funding pertaining to Phyto and Bio remediation. However, when approved the drains which are polluting the Sahibabad and its tributary drains need to be taken up if feasible. The reply of UP on in-situ bio/phyto remediation is vague and does not inspire confidence about the seriousness of the intent.

      7. A direction is required to be given to the UP Irrigation Engineer in Chief and the Principal Secretary Irrigation relating to the inordinate delay in paying DDA for undertaking the rejuvenation of the flood plains on the UP side as a deposit work which was promised on several occasions but has not made any headway in the last 7 months when one months time had been sought.

    3. The appellant moved an execution application, EA No 33 of 2021, seeking execution of the order dated 19 March 2021. By the impugned order, the Tribunal has observed that the request made in the application 'goes beyond what has been said in the order of the Tribunal dated 19 March 2021' and even otherwise, if there was a breach of the order of the Tribunal, the appellant would have to seek the remedy under Section 26 of the National Green Tribunal Act 2010. The Tribunal did not find that there was any case for taking recourse to its power under Section 25 for executing the order.

    4. The NGT has power under Section 25 to execute its orders as decrees of a civil court. Section 26 is comprised in Chapter IV which deals with the penalty for failure to comply with the orders of the Tribunal.

    5. The grievance of the appellant is that the power to impose a penalty under Section 26 will not redress the substratum or the grievance which is the discharge of untreated sewage and effluent and the absence of a sewerage system.

    6. We are of the considered view that the observation of the Tribunal that there was no case for executing the earlier order under Section 25 is misconceived. The Tribunal is entrusted with the wholesome power to ensure that its orders are complied with. The abse

    Click Here to Read the rest of this document
    1
    2
    3
    4
    5
    6
    7
    8
    9
    10
    11
    SupremeToday Portrait Ad
    supreme today icon
    logo-black

    An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

    Please visit our Training & Support
    Center or Contact Us for assistance

    qr

    Scan Me!

    India’s Legal research and Law Firm App, Download now!

    For Daily Legal Updates, Join us on :

    whatsapp-icon Back to top