SUPREME COURT OF INDIA
B.R. GAVAI, K.V. VISWANATHAN, JJ.
Benzo Chem Industrial Private Limited – Appellant
Versus
Arvind Manohar Mahajan & Ors. – Respondents
Civil Appeal No(s). 9202-9203 of 2022
Decided On : 27-11-2024
JUDGMENT
B.R. GAVAI, J.
1. These appeals challenge the orders passed by the National Green Tribunal (NGT) dated 29.08.2022 and 22.11.2022.
2. Vide the first order dated 29.08.2022 penalty is imposed on the appellant for non-compliance with the environment requirement. By the second order dated 22.11.2022, the review application has been rejected.
3. Heard Shri A.N.S. Nadkarni, learned senior counsel for the appellant, Shri Feroze Ahmad, learned counsel for Respondents No.1 to 13 and Shri Mukesh Verma, learned counsel for the Maharashtra Pollution Control Board.
4. Shri Nadkarni, learned senior counsel, submits that the order passed by the learned NGT depicts total nonapplication of mind. It is submitted that though the reports of the Maharashtra Pollution Control Board (MPCB) as well as National Environmental Engineering Research Institute (NEERI) found that there are no non-compliances, the learned NGT records to the contrary. It is further submitted that the methodology of imposing penalty of Rs.25 Crores on the ground that the operative revenue of the appellant ranges from 100 Crores to 500 Crores is totally unknown to the canons of law.
5. This is the third matter today in which we are considering the orders passed by the learned NGT, which depicts total violation of principles of natural justice and lack of due consideration.
6. Learned NGT in its order in para 13 observed thus:-
7. The appellant has placed on record reports of the inspections conducted by the MPCB for the period between 2011 to 2020. Not only that but under the orders of the NEERI, which is a premier institution insofar as environment sciences is concerned, has also found that the unit of the appellant was compliant with environment requirements and there was not a single non-compliance.
8. In the light of these findings in the report, the observations of the learned NGT that the unit has been non- compliant right from the year 2010 is totally untenable. The further observations of the learned NGT that the report of the NEERI of June 2019 also shows that the violations continues, is also contrary to the records. The report of the MPCB, which is placed at page No.349 of the paperbook would reveal otherwise.
9. Shri Verma, learned counsel appearing for the MPCB, also submits that in view of the inspection reports of the MPCB, he was not in a position to counter the claim of the appellant that there were no violation.
10. We could have allowed the appeal on this short ground, however, the further part of the order i.e. paragraph 15 makes an interesting reading. The learned NGT held that the appellant is liable to pay environmental damages. However, while computing the said damages, the only methodology that has been adopted by the learned NGT is that as per the information which is available in the public domain the revenue range of the appellant is between 100 Crores to 500 Crores. It is therefore found that the penalty of Rs.25 Crores would be commensurated with the revenue. Firstly, there is a vast difference between 100 Crores and 500 Crores. Secondly, if the learned NGT had relied on the information available in the pub
The court emphasized that penalties for environmental non-compliance must be based on sound legal principles and supported by evidence, ensuring adherence to natural justice.
The court emphasized the necessity of adhering to principles of natural justice, ruling that failure to provide a hearing before determining environmental compensation invalidated the original order.
The court affirmed that environmental compensation must be proportionate to project size, asserting that the 'polluter pays' principle justifies significant fines for regulatory violations, despite t....
The court held that penalties against public officials for violating tribunal orders must be supported by evidence of willful misconduct, and officials without sufficient authority cannot be penalize....
The NGT must adhere to principles of natural justice and cannot abdicate its adjudicatory role to committees; fair hearing is essential in decisions regarding environmental compensations.
Environmental compensation determination must accurately reflect individual contributions, and proceedings under PMLA require registered complaints for scheduled offences.
(1) Observance of Principles of Natural Justice by NGT is mandatory.(2) Recommendations made by an Expert Committee are not binding on NGT – They are only by way of assistance to enable NGT to arrive....
Principles of natural justice must be followed in administrative decisions, granting parties the right to contest allegations, particularly when sanctions affect them materially.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.