SUPREME COURT OF INDIA
Dipankar Datta, Vijay Bishnoi, JJ.
M/S. Rhythm County – Appellant
Versus
Satish Sanjay Hegde & Ors. – Respondents
Civil Appeal No. 7187 of 2022
With
M/S Key Stone Properties – Appellant
Versus
Shashikant Vithalkamble & Ors. – Respondents
Civil Appeal No. 7974 of 2022
Decided On : 30-01-2026
| Table of Content |
|---|
| 1. overview of civil appeals' origin (Para 1 , 2 , 3) |
| 2. details of environmental violations by rhythm and keystone (Para 4 , 5 , 6 , 8 , 9) |
| 3. contentions of the appellants regarding statutory compliance (Para 12 , 13) |
| 4. defense of ngt's findings as based on substantial evidence (Para 15 , 16) |
| 5. jurisprudence guiding ngt's powers and compensation mandates (Para 18 , 19 , 20 , 21 , 22 , 23) |
| 6. application of environmental compensation standards in judicial precedents (Para 28 , 29 , 30 , 31) |
| 7. implications of previously established legal precedents on current case (Para 32 , 33 , 34 , 35 , 36 , 37) |
| 8. summary of the court's decisions and order conclusions (Para 46 , 47 , 48 , 49) |
JUDGMENT :
DIPANKAR DATTA, J.
THE APPEALS
1. The present civil appeals arise out of disposal of two separate original applications by the National Green Tribunal, Western Zone Bench, Pune1[NGT] , involving similar facts and circumstances. The orders of disposal are of varying dates. We propose to decide these appeals by this common judgment and order.
2. The lead appeal has been filed by the project proponent, i.e., M/s. Rhythm County2[RHYTHM], challenging the order dated 22.08.2022 passed by the NGT in Original Application No. 14 of 2021 (WZ). Vide the impugned order, the NGT held that RHYTHM had violated the environmental norms and carried out construction without obtaining Environmental Clearance3[EC], for which it was liable in a sum of Rs. 5,00,00,000/- as compensation. Appellant was, accordingly, directed to pay such compensation within two months to the Maharashtra Pollution Control Board4[MPCB].
3. The connected appeal is filed by another project proponent, i.e., M/s. Key Stone Properties5[KEYSTONE]. It challenges the order dated 01.09.2022 passed by the NGT on Original Application No. 13/2021. Vide the impugned order, the NGT held that KEYSTONE had violated the environmental norms, including raising construction without obtaining requisite permissions. Like RHYTHM, KEYSTONE was directed to pay compensation in a sum of Rs. 4,47,42,188/- within two months to the MPCB.
FACTUAL MATRIX
4. The facts, which would be germane for the disposal of the present appeals, are adumbrated as follows:
a. Appellant RHYTHM, a partnership firm, undertook a residential and commercial construction project titled “Rhythm County” at Autade Handewadi, Pune, within the jurisdiction of the Pune Metropolitan Regional Development Authority6[PMRDA]. The project was granted EC on 27.11.2017 under the Environmental Impact Assessment7[EIA] Notification, 20068[Notification], permitting a total built-up area of 1,45,682.28 square metres. Upon issuance of requisite certificates, the construction commenced in 2018.
b. RHYTHM asserts that construction initially proceeded in conformity with the EC and the sanctioned plans. On 31.01.2020, however, Maharashtra Pollution Control Board9[MPCB] issued a show-cause notice alleging that construction had commenced without securing valid statutory consents. This was followed by an order dated 06.07.2020 whereby the MPCB refused Consent-to-Establish10[CTE] under the Water (Prevention and Control of Pollution) Act, 197411[Water Act] and the Air (Prevention and Control of Pollution) Act, 198112[Air Act], citing excess construction beyond the sanctioned area and the absence of revalidated consent. A stop-work direction was also issued on the same date.
c. Disputing these allegations, on 18.07.2020, RHYTHM applied for modification of the EC before the State Level Environment Impact Assessment Authority13[SEIAA], Maharashtra. While that application remained pending for consideration, the first respondent, a local resident of the area, approached the NGT by instituting O.A. No. 14 of 2021 (WZ), alleging that RHYTHM had undertaken substantial construction activity without valid EC and in disregard of statutory safeguards under the environmental laws.
d. In the proceedings before the NGT on 08.06.2021, a Joint Committee was constituted t
M/s. Goel Ganga Developers India Pvt. Ltd. v. Union of India
Kantha Vibhag Yuva Kohli Samaj Parivartan Trust & Ors. v. State of Gujarat & Ors.
DPCC v. Lodhi Property Co. Ltd.
Mantri Techzone Pvt. Ltd. v. Forward Foundation & Ors.
Deepak Nitrite Ltd. v. State of Gujarat & Ors.
Benzo Chem Industrial Pvt. Ltd. v. Arvind Manohar Mahajan & Ors.
Vellore District Environment Monitoring Committee v. District Collector, Vellore
Research Foundation for Science (18) v. Union of India
The court affirmed that environmental compensation must be proportionate to project size, asserting that the 'polluter pays' principle justifies significant fines for regulatory violations, despite t....
The Rajasthan State Pollution Control Board lacks authority to impose environmental compensation without legislative backing and established procedures. Judicial pronouncements dictate the need for s....
The Rajasthan State Pollution Control Board cannot impose Environmental Compensation without legislative authority, necessitating subordinate legislation for its calculation and imposition.
The National Green Tribunal retains exclusive jurisdiction to assess environmental compensation, and its orders cannot be stayed by writ jurisdiction.
The NGT must adhere to principles of natural justice and cannot abdicate its adjudicatory role to committees; fair hearing is essential in decisions regarding environmental compensations.
The court emphasized that penalties for environmental non-compliance must be based on sound legal principles and supported by evidence, ensuring adherence to natural justice.
(1) Observance of Principles of Natural Justice by NGT is mandatory.(2) Recommendations made by an Expert Committee are not binding on NGT – They are only by way of assistance to enable NGT to arrive....
Environmental compensation must adhere to principles of natural justice and proportionality, ensuring that penalties correlate with actual damage and supported by robust evidence.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.