SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Telangana) 2039

HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD
MOUSHUMI BHATTACHARYA, GADI PRAVEEN KUMAR, JJ.
Union of India and others – Appellants
Versus
M/s. Modern Engineering Works and Another – Respondents 
Civil Miscellaneous Appeal No.620 of 2019
Decided On : 12-12-2025

Advocates Appeared:
For the Appellants : Mrs. L. Pranathi Reddy, the learned Standing Counsel.
For the Respondents: Mr. Prasad Rao Vemulapalli, learned counsel.

Arbitrability of claims hinges on adherence to procedural agreements; claimants can seek interest despite contractual prohibitions, reflecting arbitral authority.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 34 and 37 - Appeal against dismissal of petition to set aside arbitral award - Issues of arbitrability of claims based on No Claim Certificate and Excepted Matters under GCC, and entitlement to interest under Clause 16(2) of GCC were discussed - Arbitrator held claims maintainable and awarded Rs.86,22,337/- with interest @ 18% - Trial Court upheld the decision, leading to this appeal. (Paras 1-47)

(B) Arbitrability - Claims falling under 'Excepted Matters' are non-arbitrable unless specific procedural requirements are followed; reliance should not unilaterally restrict weaker party's rights. (Paras 19-25)

(C) Interest - Arbitrator has discretion to award interest notwithstanding Clause 16(2) of GCC, reflecting commercial practices and legitimate claims, despite previous prohibitions. (Paras 27-34)

Findings of Court:
Award was well-reasoned and not subject to interference based on factual disputes.

Issues: Whether claims were arbitrable, whether the No Claim Certificate barred arbitration, and entitlement to interest were principal questions.

Ratio Decidendi: The court affirmed that adherence to arbitrable procedures is crucial, and that mere reliance on contractual clauses was insufficient to obstruct arbitration.

Result: Appeal dismissed.

Table of Content
1. factual background of arbitration appeal (Para 1 , 2 , 3 , 4)
2. arguments against arbitrability and interest claims (Para 6 , 7)
3. contentions on no claim certificate and arbitration scope (Para 8 , 11 , 12)
4. scope of excepted matters in arbitration context (Para 18 , 19 , 22 , 24)
5. discussion on interest claims under gcc (Para 27 , 28 , 30 , 33 , 35)
6. authority of arbitrator to grant interest (Para 29 , 32 , 34 , 36)
7. legal precedents on interest and arbitrability (Para 41 , 42 , 43)
8. final judgment on merit and process (Para 44 , 46)
9. conclusion and dismissal of the appeal (Para 47 , 48)

JUDGMENT:

Moushumi Bhattacharya, J.

1. The present Appeal has been filed challenging the order dated 22.10.2018 passed by the I Additional Chief Judge, City Civil Court, Secunderabad (‘Trial Court’), dismissing the petition filed by the appellants under section 34 of The Arbitration and Conciliation Act, 1996 (‘the 1996 Act’) for setting aside the Award dated 24.04.2013. The present Appeal has been filed under section 37 of the said Act.

2. The appellants before this Court were the respondents in the arbitration. The respondent No.1/Contractor in the Appeal was the Claimant in the arbitration. The learned Arbitrator is arrayed as the respondent No.2 in the present Appeal.

3. The respondent No.1/Contractor had raised six claims in the arbitration for the work done in accordance with the Agreement dated 09.03.1994, which was for conversion of Hubli – Londa Section from Meter Gauge to Board Gauge between Dharwad and Mugad Reach – II and execution of miscellaneous works between Dharwad and Mugad Stations. The six claims related, inter alia, to (i) difference in rates payable for excess quantities executed by the respondent No.1/Contractor beyond 25% of the agreed quantities along with additional items, (ii) payment for Earth work deducted towards subsidence allowance, (iii) reimbursement of charges and commission paid to the financiers on the amounts borrowed, (iv) reimbursement of expenditure incurred in continuing overheads and (v) establishments from 01.05.1995 to 31.03.1997 on account of delay in finalisation of bills, (vi) reimbursement of loss of business and profit thereon, interest @ 18% from 01.04.1997 to 01.09.2001 on the total claim amount along with yearly rests.

4. The learned Arbitrator, a retired Judge of this Court, held that the claims of the respondent No.1/Contractor were maintainable and deserved to be allowed. The Arbitrator allowed Claim Nos.1, 2, 4 and 6 in part awarding a total amount of Rs.86,22,337/- and interest @ 18% per annum for the pre-reference period, pendente lite, and from the date of Award to the date of payment.

5. The Trial Court dismissed the appellant’s petition by the impugned order dated 22.10.2018, inter alia, the ground that the Award had been passed after due consideration of the issues raised by the parties and there was no scope for interference in the reasons given by the Arbitrator. The appellant has filed the present Appeal challenging the impugned order dated 22.10.2018.

6. Learned Standing Counsel for the Central Government appearing for the appellants submits that the Trial Court should have set aside the Arbitral Award dated 24.04.2013 since the claims raised by the respondent No.1 were not arbitrable as per Clause 63 of The General Conditions of Contract, 1989 (‘GCC’) which covers the matters deemed as ‘Excepted matters’. Counsel submits that under Clause 63, all disputes and differences arising out of the Contract, regardless of the time at which the dispute was raised and even after termination of the Contract shall be referred by the Contractor to the Railways and the latter shall make and notify its decision within a reasonable period of time. The decision given by the Railways shall be final and binding on the Contractor. Counsel submits that Clause 63 mentions specific Clauses of the GCC covering the disputes raised by the Contractor. Consequentially, the learned Arbit

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top