IN THE HIGH COURT OF KARNATAKA AT BENGALURU
M. Nagaprasanna, J.
M/s. Provident Housing Limited – Petitioner
Versus
Karnataka Real Estate Regulatory Authority and Ors. – Respondents
Writ Petition No.18448 OF 2021 (GM – RES)
Decided On : 02-01-2023
Fact of the Case:
The petitioner challenged an order passed by the Karnataka Real Estate Regulatory Authority directing refund to a complainant who sought redressal for non-repayment of part of an amount withheld by the developer.Finding of the Court:
The court found that as per Rule 4 of the Rules made under the Act, projects which had received partial occupancy certificates prior to the Act coming into force were exempt from its applicability. Therefore, it held that the complaint before the Authority was not maintainable.Issues:
Whether the complaint before the Authority was maintainable? Whether the order passed by the Authority is tenable in law?Ratio Decidendi:
The court held that since the project had lost its ongoing status before the Act came into force due to issuance of partial occupancy certificates, as per Rule 4 exemption provision, any order passed by the Authority was without jurisdiction.Final Decision:
The writ petition was allowed; judgment/order dated September 30th,2020 passed by Karnataka Real Estate Regulatory Authority stood quashed; and amount in deposit before this Court shall be refunded to petitioner forthwith.ORDER :
The petitioner-M/s Provident Housing Limited is before this Court calling in question order dated 30-09-2020 passed by the 1st respondent/Karnataka Real Estate Regulatory Authority (‘Authority’ for short).
2. Brief facts that lead the petitioner to this Court in the subject petition, as borne out from the pleadings, are as follows :-
The petitioner is a Company incorporated under the Companies Act, 1956 and is engaged in the business of real estate development. The petitioner advertises a project i.e., apartment complex in the name and style of “Provident Sunworth” in Sy.Nos.1 to 26 of Venkatapura Village, Kengeri Hobli, Bangalore. The 2nd respondent registers his interest by an application pursuant to the advertisement requesting the petitioner to allot an apartment in the project. On consideration of the application, the petitioner is allotted a flat bearing No.SUN-II-5G-506 on the fifth floor to the 2nd respondent by way of execution of an agreement to sell.
3. The 2nd respondent who is the applicant before the 1st respondent entered into a sale agreement with the petitioner for purchase of flat on 10-09-2014 and a construction agreement on the same day comes into effect. This was on the basis of a commencement certificate that was issued by the Bangalore Development Authority (‘BDA’ for short) in respect of the purchase in favour of the petitioner. It is averred that clause 1 of the construction agreement obliged the petitioner to hand over possession of the flat allotted to the 2nd respondent on or before 31-07-2016 with the extended period of 6 months from the date of commencement certificate which would be up to January 2017 subject to the condition that there was no delay or default in payment of installments to the project by the 2nd respondent and in any event which would be force majeure.
4. The petitioner submits an application to the BDA on 21-10-2015 for grant of partial occupancy certificate in respect of the project which was scrutinized and the same was granted by the BDA on 18-11-2015. The petitioner later makes another application on 28-03-2017 to the BDA for a second partial occupancy certificate. It is the averment in the petition that when things stood thus, negotiations and discussions were held between the petitioner and the 2nd respondent and later the petitioner gave its willingness to execute the sale deed and hand over possession of flat No.506 pursuant to the said partial occupancy certificate. On 14-05-2017, it appears, the 2nd respondent seeks to cancel the agreement that was entered into between him and the petitioner, on the ground that there was information to him that the land had not been legally acquired by the petitioner for construction of the Apartment complex. It was alleged in the communication that the petitioner had not produced any letter from the competent authority with respect to acquisition of land and the petitioner had not replied to all those queries which were intermittently raised by the 2nd respondent. The petitioner acceded to the request of the 2nd respondent and cancelled the agreement and the allotment made in favour of the 2nd respondent and also refunded a sum of Rs.17,85,212/-on 04-12-2017 after deduction of cancellation charges and applicable taxes.
5. Long after receipt of the said amount, the 2nd respondent knocks at the doors of the 1st respondent/Authority by registering a complaint seeking refund of an amount of Rs.6,84,494/-along with interest. On receipt of the notice, the petitioner appears to have filed its objections with regard to maintainability of the complaint before the 1st respondent and its entertainment by the Authority. Notwithstanding the objections with regard to maintainability, the Authority passes the impugned order, on the complaint so made by the 2nd respondent, on 30-09-2020 directing refund of Rs.6,84,494/-to the 2nd respondent within 60 days from 30-09-2020, failing which, it would carry interest at 2% per month. It is this order that
Projects receiving partial occupancy certificates prior to enactment are exempt from certain provisions of Real Estate (Regulation and Development) Act.
The main legal principle established in the judgment is the interpretation and application of the definition of 'ongoing project' under Rule 2(h) of the Uttar Pradesh Real Estate (Regulation and Deve....
The RERA Act applies to ongoing real estate projects, and the Act's provisions protect the rights of stakeholders, including home buyers and promoters.
The court clarified that the Completion Certificate's issuance date is crucial in determining a project's ongoing status under RERA, emphasizing the conjunctive reading of statutory provisions.
The court determined that unresolved factual disputes regarding project completion and jurisdiction require the Developer to pursue statutory remedies rather than direct writ petitions.
The Real Estate (Regulation and Development) Act mandates registration for ongoing projects, where completion certificates are absent, emphasizing consumer protection in real estate transactions.
The existence and date of issuance of occupancy certificates are critical in determining whether a real estate project is ongoing under the RERA.
The court affirmed that ongoing real estate projects must be registered under RERA to protect allottee interests, regardless of title transfer.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.