SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Kar) 50

IN THE HIGH COURT OF KARNATAKA AT BENGALURU
VIBHU BAKHRU, CJ, C.M.POONACHA, J.
Dinesh M. S/o Shri G. Muniswamy – Appellant
Versus
M/s Provident Housing Ltd. – Respondent
Writ Appeal No. 1243 of 2024
Decided On : 06-01-2026

Advocates Appeared:
For the Appellant : Dinesh M. [Party-In-Person]
For the Respondents: Joseph Anthony, Rajashekar K.

The court determined that unresolved factual disputes regarding project completion and jurisdiction require the Developer to pursue statutory remedies rather than direct writ petitions.

Headnote:(A) Karnataka Real Estate (Regulation and Development) Act, 2016 - Section 3 - Appeal against writ petition involving jurisdiction of KRERA over a completed project - Appellant claimed Developer failed to deliver possession as per agreement - KRERA directed compensation and execution of sale deed, which was challenged by Developer - Court upheld that Developer's claim of project completion prior to Act commencement was not substantiated. (Paras 3, 5, 24)

(B) Jurisdiction of KRERA - The issue was whether the Developer was exempt from registration under the Act due to completion certificate being obtained post-implementation of Section 3, impacting the enforceability of the order for compensation. (Paras 3, 9, 25)

(C) Appellate Process - Court noted that disputed questions remain, emphasizing that statutory remedies should be exhausted through an appeal rather than direct writ applications. (Paras 25, 26)

Facts of the case:
Appellant booked a flat in 'The Tree by Provident' project in 2015, paid Rs.55,27,569/-, but possession was delayed beyond the agreed date of July 2017, leading to KRERA's order that the Developer contested.

Findings of Court:
The Single Judge's order favoring the Developer lacked examination of disputed factual material, making the order unsustainable.

Issues: Whether the project was ongoing under the Act and the jurisdiction of KRERA regarding completed projects claimed exempt by Developer.

Ratio Decidendi: The court ruled that unresolved factual disputes regarding project completion necessitate appellate review, reaffirming statutory processes should precede judicial interventions in such instances.

Result: Appeal allowed, impugned order set aside.

Table of Content
1. details of the appeal and prior ruling (Para 1 , 2 , 5)
2. arguments regarding exemption from registration (Para 3 , 6 , 8 , 10)
3. court's interpretation of project completion and krera's order (Para 4 , 7 , 9)
4. definitions related to ongoing projects under the act (Para 11 , 12 , 21)
5. evidence presented regarding project readiness (Para 18 , 20)
6. court's decision on the sustainability of the ruling and statutory remedies (Para 24 , 25)
7. final ruling of the appeal and directive for further appeal process (Para 26 , 27)

JUDGMENT :

VIBHU BAKHRU, C.J.

1. The appellant has filed the present appeal impugning a judgment dated 15.06.2023 [the impugned order] passed by the learned Single Judge in Writ Petition No. 15133/2020 (GM-RES).

2. Respondent No.1, M/s. Provident Housing Limited [The Developer] had filed the said writ petition impugning an order dated 28.05.2020, passed by the Karnataka Real Estate Regulatory Authority [KRERA], whereby it was directed to pay compensation at the rate of 2% of the amount paid by the appellant from April, 2017 till delivery of possession. Additionally, KRERA also directed the Developer to execute the sale deed in respect of the flat in question within a period of one month and also to pay the cost quantified at Rs.5,000/-. The said order was passed pursuant to the complaint filed by the appellant alleging failure on the part of the Developer to register the project named ‘The Tree by Provident’ and deliver possession of the apartment booked by the appellant in the said project.

3. The Developer had challenged the said order on the ground that KRERA did not have any jurisdiction to pass the said order. It claimed that the project in question (The Tree by Provident) which is located at Herohalli Village, Yeshwantpura Hobli, Bangalore North Taluk, was a completed project (not an ongoing project) and therefore was exempted from registration under the Karnataka Real Estate (Regulation and Development) Act, 2016 [the Act]. The Developer claimed that it had obtained the completion certificate/occupancy certificate prior to Section 3 the Act coming into force and thus was exempt under Rule 4 of the Karnataka Real Estate (Regulation and Development) Rules, 2017 [the Rules]. The Developer further claimed that the complaint made by the appellant under Section 31 of the Act, was not maintainable.

4. The Developer had applied for occupancy certificate on 10.04.2017 and the same was granted on 12.12.2017. The learned Single Judge held that although the said certificate was issued after 01.05.2017, it would relate back to the date of application, that is 10.04.2017. Since Section 3 of the Act, which provides for registration of projects, came into effect from 01.05.2017, the same would be inapplicable for the project in question. Accordingly, the order dated 28.05.2020 passed by KRERA was set aside.

5. The appellant had booked a residential flat in the project in question ('The Tree by Provident') on 23.01.2015 and he paid the booking amount of Rs.2,00,000/- (Rupees Two Lakhs only). Thereafter, on 11.02.2015, the appellant and the Developer entered into a Sale Agreement and Construction Agreement and the appellant paid the entire agreed sale consideration amount of Rs.55,27,569/- (Rupees Fifty-five lakhs Twenty-seven thousand Five hundred and Sixty-nine only) in terms of the said agreement. The appellant claims that in terms of the agreement, the Developer was required to complete the project and construction on or before 30.07.2017, however, it failed to do so. Aggrieved by the same, the appellant preferred a complaint (CMP/191025/0004556) before the KRERA, which was allowed in terms of the order dated 28.05.2020.

6. The Developer had resisted the said complaint on several grounds including that, it was not liable to pay any compensation since it was exempted from registration under Rule 4(1)(iv) of the Rules.

7. The learned KRERA did not accept the said contention. It found that the project was not

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top