IN THE HIGH COURT OF KARNATAKA AT BENGALURU
K.V. ARAVIND, J.
Thomas Chandy S/o Late Shri Kora Chandy - Appellant
Versus
State Bank of India, Rep. by its Chief Manager - Respondent
Writ Petition No. 22638 of 2015
Decided On : 02-05-2025
| Table of Content |
|---|
| 1. writ petition against bank's demand (Para 1 , 2) |
| 2. details of penalty demand and responses (Para 3) |
| 3. petitioner's arguments on contractual obligations (Para 4 , 5 , 6) |
| 4. respondent's defense regarding contract enforcement (Para 7 , 8 , 9) |
| 5. court's overview of loan terms and conditions (Para 10 , 11 , 12) |
| 6. overview of court's reasoning on contract frustration (Para 13 , 14) |
| 7. court's direction on arbitrary demands by the bank (Para 15 , 16) |
| 8. judicial review applicability in contractual disputes (Para 17 , 18 , 19 , 20) |
| 9. final declaration of the court's view on the demand (Para 21) |
| 10. order concluding the judgment (Para 22) |
ORDER :
1. The instant writ petition is directed against the communication dated 12.02.2015 issued by the respondent-Bank, whereby the petitioner has been called upon to remit a sum of Rs.92,88,300/- towards interest and penalty, allegedly on account of violation of the terms and conditions of the loan agreement.
2. The case of the petitioner is that he is a medical practitioner by profession. With the intention of constructing a residential house, the petitioner purchased Site No.12 (Old No.10/A), Magrath Road, Ashok Nagar, Bangalore, from one Vikram Malhotra under a registered Sale Deed dated 30.08.2002. In order to finance the said purchase, the petitioner approached the respondent-Bank for a loan. Upon consideration of the application of the petitioner, the respondent-Bank sanctioned a sum of Rs.1.50 Crore, with interest as agreed between the parties, for the purchase of the schedule property.Thereafter, the petitioner commenced construction of a building on the said property.
2.1 One Mr. Asha John Divianathan impleaded the petitioner in RFA No.1001/2001 and sought a temporary injunction restraining the petitioner from alienating the property or proceeding with construction thereon. This Court, by order dated 07.04.2005, granted an interim injunction restraining the petitioner from putting up any construction. The said RFA pertained to a challenge to the gift deed executed in favour of the petitioner’s vendor, namely, Vikram Malhotra. The said gift deed, which related to the schedule property purchased by the petitioner, was challenged by Mr. R.P. David. By judgment and order dated 01.10.2009, this Court upheld the validity of the gift deed and, consequently, the sale deed executed in favour of the petitioner. Aggrieved by the said judgment, Mr. Asha John Divianathan preferred Special Leave Petition No.31217/2009 before the Hon’ble Supreme Court, wherein, by order dated 04.12.2009, the Hon’ble Court directed that status quo be maintained by the parties. The petitioner’s application seeking vacation of the interim order came to be rejected. Upon grant of special leave, the matter came to be numbered as Civil Appeal No.9546/2010. During the pendency of the said appeal, the petitioner filed an application seeking early hearing, citing contractual obligations.
3. The respondent-Bank, by communication dated 29.09.2014, demanded a sum of Rs.9,28,300/-, being 2% penalty, on the ground that the petitioner had failed to commence construction within the agreed period. In response, the petitioner submitted a detailed reply dated 10.11.2014, drawing the attention of the respondent-Bank to the status quo order passed by the Hon’ble Supreme Court and asserting that the non-commencement of construction was due to circumstances beyond his control. The petitioner further contended that the delay did not amount to a violation of the terms and conditions of the loan agreement. Notwithstanding the same, the respondent-Bank issued a demand notice dated 27.11.2014, calling upon the petitioner to remit a sum of Rs.9,28,300/-. The petitioner, once again, submitted a reply dated 06.02.2015, reiterating the compelling reasons for the delay in commencement of construction. However, the respondent-Bank, by final communication dated 12.02.2015, insisted upon payment of Rs.9,28,300/-, disregarding the petitioner’s e
Boothalinga Agencies vs. V.T.C. Poriaswami Nadar
Basavalingappa Mamle Desai vs. Siddalingappa
Shanti Vijay and Co. vs. Princess Fatima Fouzia
Union of India and Others v. Puna Hinda
M.P. Power Management Company Limited v. Sky Power Southeast Solar India Private Limited and Others
The court held that a bank's demand for additional interest on a loan cannot be enforced if the borrower did not provide the required undertaking, rendering the contract effectively frustrated due to....
Additional premium demand for construction delay under lease held arbitrary where caused by statutory approvals, late commencement certificates, and extra built-up area without timeline; applicable s....
Banks must ensure fair market valuations in auctions of mortgaged properties to protect borrowers' rights, and not depress values arbitrarily which would lead to undue prejudice.
Supplementary lease deeming additional built-up area integral with no time limit overrides original four-year completion clause for composite construction; penalty demands arbitrary, illegal; payment....
Penalty for construction delay under lease quashed due to delays from court stay, statutory approvals, additional area; writ maintainable for arbitrary state action; 6-year extension non-discriminato....
Lease penalty for construction delay invalid where lessor nondiscloses material site defects, supplementary deed removes time limit for additional built-up area, delays due to approvals/statutory fac....
The court established that no writ could be issued under Article 226 of the Constitution to compel the bank to remedy a breach of contract in a non-statutory contract, unless there was a public inter....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.