IN THE HIGH COURT OF KARNATAKA AT BENGALURU
M. NAGAPRASANNA, J.
M/s. Nestoya Homes Pvt. Ltd., Represented By Its Authorised Signatory Mr. Vijay Kumar R. – Petitioner
Versus
M/s. Orchids Elite Developers Pvt. Ltd., Represented By Its Director and Anr. – Respondents
Writ Petition No.21496 of 2023 (GM - RES)
Decided On : 05-07-2024
| Table of Content |
|---|
| 1. facts surrounding the project initiation and developer's failure. (Para 3 , 4) |
| 2. arguments regarding investment and project completion. (Para 5 , 6 , 7) |
| 3. details on project registration and authority's actions. (Para 9 , 10) |
| 4. court's analysis on authority's compliance with the statute. (Para 11 , 12) |
| 5. conclusion dismissing the writ petition. (Para 14) |
ORDER :
M. NAGAPRASANNA, J.
The petitioner-M/s Nestoya Homes Private Limited is before this Court calling in question an order dated 03-08-2023 passed by the Karnataka Real Estate Regulatory Authority, Bengaluru (‘the Authority’ for short) in CMP/201224/0007319 allowing the complaint filed by the 2nd respondent/Hanging Gardens Nagawara Flat Owner’s Co-operative Societies Limited (hereinafter referred to as ‘the Society’ for short).
2. Heard Sri Anil Ramachandra, learned counsel appearing for petitioner, Sri K.R. Krishnamurthy, learned counsel appearing for respondent No.1 and Sri Arjun Rao, learned counsel appearing for respondent No.2.
3. Facts, in brief, germane are as follows:-
The petitioner claims to be a Company registered under the provisions of the Companies Act, 2013. M/s Orchids Elite Developers Private Limited (hereinafter referred to as ‘the Developer’ for short) is the 1st respondent and the 2nd respondent is the Society. The issue commences from a project that was sought to be initiated by the Developer for an apartment complex by name ‘Hanging Gardens’. The project was initiated by the Developer on 10-03-2011 and commencement certificate was issued on 3-07-2014. Since the project was incomplete as on the date of commencement of the Real Estate (Regulation and Development) Act, 2016 (hereinafter referred to as ‘the Act’ for short), the target completion of the project was restructured to 30-06-2020 pursuant to registration of the project before the Authority. The project was required to be developed into a residential apartment unit consisting of 120 flats which was revised to 132 flats. There was no progress in the project since mid 2016 and the overall project was only complete up to 50%.
4. The Developer, in order to facilitate entire control of the project, proposed to the petitioner to take over the project in the name of partnership firm consisting of the petitioner and the Developer as partners. Induced by the offer made by the Developer to the petitioner, the petitioner sought to take over the project. But the project did not get complete. The Society then knocks at the doors of the Authority by filing the impugned proceedings against the Developer. An order is made on 03-08-2023 permitting remainder of the construction to be taken over by the 2nd respondent/Society in terms the Act. This has driven the petitioner before this Court in the subject petition.
5. The learned counsel appearing for the petitioner would vehemently contend that the petitioner has invested several crores in the subject project, as there is an agreement between the Developer and the petitioner. It had filed an application before the Authority to implead itself as a party respondent. The Authority without answering the said application, has permitted the 2nd respondent to continue with the construction. Therefore, the petitioner becomes an aggrieved party to challenge the order of the Authority before this Court. He would submit that if 4 to 6 months time is granted, the petitioner would complete the project and hand it over to the Society. Even the Society has to take up the construction which the petitioner itself will do. He would seek quashment of the order of the Authority and permit completion of the project by the petitioner.
6. Per contra, the learned counsel for the 1st respondent/Developer would submit that there is a dispute between the petitioner and the Developer. The very agreement between the two is a product of forgery. Criminal case is registered against the petitioner by the Developer alleging cheating and forgery. Therefore, the Developer is in the same
The court upheld the authority's decision to allow a housing society to take over a lapsed real estate project, prioritizing home buyers' interests over private disputes.
Projects receiving partial occupancy certificates prior to enactment are exempt from certain provisions of Real Estate (Regulation and Development) Act.
The main legal point established in the judgment is that the delay in completion of the project was not attributable to the Lucknow Development Authority or the State Government, and further extensio....
The Real Estate (Regulation and Development) Act mandates registration for ongoing projects, where completion certificates are absent, emphasizing consumer protection in real estate transactions.
The main legal point established in the judgment is the requirement for proper inspection and adherence to legal requirements by the competent authorities in issuing occupancy certificates for real e....
The court determined that unresolved factual disputes regarding project completion and jurisdiction require the Developer to pursue statutory remedies rather than direct writ petitions.
The court affirmed that ongoing real estate projects must be registered under RERA to protect allottee interests, regardless of title transfer.
The main legal principle established in the judgment is the interpretation and application of the definition of 'ongoing project' under Rule 2(h) of the Uttar Pradesh Real Estate (Regulation and Deve....
RERA applies to ongoing projects regardless of completion status, ensuring consumer protection and allowing for grievances to be raised under its provisions.
The completion certificate issued must be strictly in accordance with the sanctioned plan and specifications, and the responsibilities of the promoter include providing and maintaining essential serv....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.