IN THE HIGH COURT OF JUDICATURE AT BOMBAY
M.S. SONAK, KAMAL KHATA, JJ.
Rafique Rahemtullah Kabani - Petitioner
Versus
The Assistant Engineer & Designated Officer & Ors. - Respondents
Writ Petition No. 3616 of 2018
Decided On : 11-09-2024
Maharashtra - MRTP Act - Sections 53 - The court interpreted Section 53 of the MRTP Act, emphasizing the illegality of constructions beyond approved plans and the necessity of compliance with municipal regulations, leading to the dismissal of the petition.
Fact of the Case:
The Petitioner challenged a notice from the BMC for the removal of illegally constructed floors in a building, arguing violations of natural justice and improper service of notices.
Finding of the Court:
The court found that the constructions from the 2nd to the 8th floor were unauthorized and illegal, with no valid permissions or approvals, and that the BMC acted within its jurisdiction in issuing the removal notice.
Issues: Whether the BMC's notice for demolition of unauthorized constructions violated principles of natural justice and whether the constructions could be regularized.
Ratio Decidendi: The court held that the absence of permissions for the constructions rendered them illegal, and the BMC was justified in taking action against such violations, dismissing claims of natural justice breaches.
Result: The Writ Petition is dismissed with costs of Rs.50,000/- payable to the BMC.
JUDGMENT :
M.S. Sonak, J.
1. Heard Mr Bhushan Joshi, learned counsel for the Petitioner, Mr Rajshekhar Govilkar learned Senior Advocate with Ms Sujata Puri and Ms Shaba Khan, instructed by Mr S.K. Sonawane, learned counsel for BMC (1st and 2nd Respondents) and Mr Mandar Soman with Mr Divakar Rai for the 5th Respondent. The 3rd and 4th Respondents, though duly served, were absent.
2. Rule. The Rule is made returnable immediately at the request of and with the consent of the learned counsel for the parties.
3. The Petitioner challenges notice No.CE/4362/BSII/AH dated 12th June 2018 under Section 53 of the Maharashtra Regional and Town Planning Act, 1966 (“MRTP Act”) by the Brihanmumbai Municipal Corporation (“BMC”) for the removal of the structure viz. (i) work carried out beyond the approved plan, i.e. 4th floor to 8th floor, (ii) work carried out beyond the approved plan i.e. 2nd floor to 8th floor Phase 1.
4. The Petitioner, in the alternate, prays that the direction be issued to the BMC not to implement its above notices under Section 53 of the MRTP Act until the competent authority decides on the 5th Respondent’s application for regularisation in respect of the structures forming the subject matter of the impugned notices.
5. Mr Joshi submitted that the impugned notices, though served on the owner/developer and the 5th Respondent (Society), were not served upon each of the occupants of the premises, which are now ordered to be demolished and removed. He, therefore, submitted that this would amount to a breach of the principles of natural justice, and the impugned notices may be set aside on this ground.
6. Without prejudice, Mr Joshi submitted that the show cause notice dated 12th September 2017 referred only to the six specific but alleged illegalities listed in the Schedule to this notice. However, the impugned notice/speaking order dated 12th June 2018 inter alia refers to the structure/building from the 2nd to the 8th floor. He, therefore, submitted that the final order dated 12th June 2018 travels beyond the show cause notice dated 12th September 2017, and again, for this reason also, there is a breach of the principles of natural justice and fair play.
7. Finally, Mr Joshi submits that this Court, in its order dated 7th June 2017 disposing of Writ Petition No.56 of 2017 instituted by the 5th Respondent (Society), had only directed action against the V. C. Fitness Centre (as described in Exhibit “B” to this Petition) at the entrance of the building and some other structures specified in the said Writ Petition. Therefore, when the BMC officials inspected the building, they were required to focus only on the illegalities referred to in Exhibit “B” to the said Petition or other structures forming the subject matter of Writ Petition No.56 of 2017. He submitted that action against the 2nd to 8th floor of the building was neither sought nor formed the subject matter of Writ Petition No.56 of 2017. Therefore, he submitted that the BMC’s impugned action transgresses this Court’s order dated 7th June 2017 in Writ Petition No.56 of 2017.
8. Mr Joshi submitted that the impugned notices/speaking order must be set aside for all the above reasons.
9. Mr Soman, learned counsel for the 5th Respondent (Society), also strongly supported Mr Joshi’s contentions. He submitted that the Society’s Writ Petition No.56 of 2017 had no concern with the 2nd to 8th floor. This Petition only concerned V. C. Fitness Centre and possibly the other structures referred to in the show cause notice dated 12th September 2017 issued by the BMC. He submitted, therefore, that the impugned notices/speaking order, to the extent they directed the removal/demolition of the 2nd to 8th floor, was improper and even illegal.
10. Mr Soman submitted that the BMC had committed contempt of this Court by not faithfully implementing this Court’s order dated 7th June 2017 in Writ Petition No.56 of 2017 instituted by the 5th Respondent (Society) because no action was taken against the i
Royal Paradise Hotel (P) Ltd. vs. State of Haryana
Dipak Kumar Mukherjee vs. Kolkata Municipal Corporation and Ors.
The court established that unauthorized constructions cannot be regularized and that compliance with municipal regulations is mandatory for legality.
The court established that unauthorized constructions in eco-sensitive areas cannot be regularized post facto, and the right to seek regularization is not available to those who violate planning laws....
Municipal authorities must act promptly against unauthorized constructions, as they violate planning laws and undermine public interest.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.