SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Bom) 1253

IN THE HIGH COURT OF JUDICATURE AT BOMBAY ORDINARY ORIGINAL 
SOMASEKHAR SUNDARESAN, J.
Hindustan Petroleum Corporation Limited - Petitioner 
Versus 
G.R. Engineering Private Limited - Respondent 
ARBITRATION PETITION NO. 984 of 2018
Decided On : 18-06-2025

Advocates:
Advocate Appeared:
For the Appellant :Mr. Zal Andhyarujina Sr. Advocate a/w Mr. Vijay Purohit, Ms. Ishani Khanwilkar, Ms. Nitika Bangera, vis. Niyati Bogayta i/b P & A Law Offices Adv. For the Respondent: Mr. Haresh Jagtiani, Sr. Adv. a/w Mr. Suprabh Jain, Mr. Pushpvijay Kanoji, Mr. Pranay Kamdar i/b Suprabh Jain

Liquidated damages require proof of actual losses; insufficient reasoning in arbitral decisions can render findings arbitrary.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Challenge to arbitral award - Contract for construction - Contractual obligations regarding liquidated damages, insurance, and customs duty - The Court held that the Tribunal's findings on civil works and insurance were tenable, while the assessment of liquidated damages lacked sufficient reasoning. (Paras 1, 68)

(B) Liquidated Damages - Requirement to prove actual losses - Tribunal found no evidence of proven losses; hence, denied HPCL's claim for liquidated damages. (Paras 30, 36)

Facts of the case:
The case involved a dispute over an arbitral award favoring G.R. Engineering regarding claims for payment withheld by Hindustan Petroleum Corporation Limited. Specific issues related to delayed project completion, insurance non-compliance, and liquidated damages were under contention. (Paras 2-5)

Findings of Court:
The Court found that while the Tribunal’s decisions on civil works and insurance claims were justified, its dismissal of the liquidated damages claim was arbitrary due to inadequate reasoning. (Paras 1, 68)

Issues: Whether the withholding of amounts for liquidated damages was justified, and whether the Tribunal's rationale was adequate. (Paras 26, 36)

Ratio Decidendi: The Court emphasized that liquidated damages must correspond with proven losses, which the Tribunal failed to establish, leading to an arbitrary decision. (Paras 30, 36)

Result: The petition was partly allowed; the element of liquidated damages was set aside for lack of reasoning while upholding other aspects of the award.

Table of Content
1. challenge to arbitral award on contractual disputes. (Para 1 , 2 , 3)
2. claims for liquidated damages need to prove actual loss. (Para 4 , 29 , 30)
3. criteria for withholding payment based on compliance with contract. (Para 6 , 7 , 8 , 9 , 10)
4. no arbitrary decisions regarding contractual obligations require clarity. (Para 18 , 32 , 34)
5. setting aside portions of the award and upholding legitimate claims. (Para 69 , 70)

JUDGEMENT:

Context and Background:

1. This Petition under Section 34 of the Arbitration and Conciliation Act, 1996 (“the Act”) challenges an arbitral award dated May 2, 2018 (“Impugned Award”) passed in favour of the Respondent, G.R. Engineering Private Limited (“GRE”) by an arbitral tribunal allowing a claim against the Petitioner, Hindustan Petroleum Corporation Ltd. (“HPCL”).

2. HPCL invited bids and awarded GRE a contract to construct twelve “mounded bullets” to store liquified petroleum gas at HPCL’s refinery at Mahul (“Project”). Specific elements of the mounded bullets were to conform to the usage of reinforced cement concrete (“RCC”) of “M30 grade”. The Project was to be completed by December 5, 2007 but was completed on February 2, 2010. Disputes and differences between the parties arose out of HPCL computing liquidated damages in the payments due on invoices raised by GRE. HPCL also withheld various other amounts on the payments made to GRE, which led to the arbitration proceedings.

3. The Impugned Award holds in GRE’s favour on various counts. The Learned Arbitral Tribunal held that the amount withheld by HPCL on account of Civil Works (Rs. 1,99,07,227); under-insurance (Rs. 25,64,026); Customs Duty variation (Rs. 86,38,491.50); Service Tax (Rs. 3,08,85,583); normalising ‘Dished Ends’ (Rs. 5,00,000); and liquidated damages (Rs. 5,83,67,973) ought not to have been withheld. The Impugned Award directed the payment of such sums by HPCL to GRE. The Impugned Award also awarded interest at the rate of 7% per annum from the date of filing of the claim (September 6, 2012) until the date of actual payment.

4. The core challenge to the Impugned Award is based on alleged perversity in the findings on the following counts, namely:-

(a) Manner of dealing with the facts relating to the Civil Works, with particular regard to consideration of a report by an expert not introduced by HPCL as a witness, as also the contention that disputes relating to Civil Works was not arbitrable;

(b) Denial of Liquidated Damages in the teeth of the contract between the parties; and (c) Manner of dealing with the claims in relation to under-insurance, service tax and Customs Duty.

5. Each of these heads is dealt with below. I have heard, at length, Mr. Zal Andhyarujina, Learned Senior Counsel on behalf of HPCL and Mr. Haresh Jagtiani, Learned Senior Counsel on behalf of GRE, and examined the record with their assistance, bearing in mind the scope of Section 34 of the Act.

Withholding on Civil Works:

6. HPCL withheld an amount of Rs. 1.99 crores on the premise that the Civil Works carried out did not conform to the M30 standard. HPCL’s challenge to the Impugned Award in this regard can be summarised thus:-

(a) Various government agencies are entitled to inspect the Project and point out discrepancies in the execution, and recommend recoveries. HPCL is entitled to effect withholding of amounts. In such event, under Clause 8.b of the General Conditions of Contract (“GCC”), GRE is not entitled to raise any dispute. According to HPCL, the withholding was done pursuant to the recommendation of its own vigilance department, which is a “government agency”. Therefore, this facet of the matter was not arbitrable. HPCL finds fault with the Learned Arbitral Tribunal having rejected an application under Section 16 of the Act in this regard;

(b) In the course of the arbitration, a report dated May 18, 2009 prepared by one Prof. R.S. Jangid of IIT, Mumbai (“Jangid Report”) was relied upon by GRE and the Learned Arbitral Tribunal took it on

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top