IN THE HIGH COURT OF JUDICATURE AT BOMBAY ORDINARY ORIGINAL
SOMASEKHAR SUNDARESAN, J.
Hindustan Petroleum Corporation Limited - Petitioner
Versus
G.R. Engineering Private Limited - Respondent
ARBITRATION PETITION NO. 984 of 2018
Decided On : 18-06-2025
| Table of Content |
|---|
| 1. challenge to arbitral award on contractual disputes. (Para 1 , 2 , 3) |
| 2. claims for liquidated damages need to prove actual loss. (Para 4 , 29 , 30) |
| 3. criteria for withholding payment based on compliance with contract. (Para 6 , 7 , 8 , 9 , 10) |
| 4. no arbitrary decisions regarding contractual obligations require clarity. (Para 18 , 32 , 34) |
| 5. setting aside portions of the award and upholding legitimate claims. (Para 69 , 70) |
JUDGEMENT:
Context and Background:
1. This Petition under Section 34 of the Arbitration and Conciliation Act, 1996 (“the Act”) challenges an arbitral award dated May 2, 2018 (“Impugned Award”) passed in favour of the Respondent, G.R. Engineering Private Limited (“GRE”) by an arbitral tribunal allowing a claim against the Petitioner, Hindustan Petroleum Corporation Ltd. (“HPCL”).
2. HPCL invited bids and awarded GRE a contract to construct twelve “mounded bullets” to store liquified petroleum gas at HPCL’s refinery at Mahul (“Project”). Specific elements of the mounded bullets were to conform to the usage of reinforced cement concrete (“RCC”) of “M30 grade”. The Project was to be completed by December 5, 2007 but was completed on February 2, 2010. Disputes and differences between the parties arose out of HPCL computing liquidated damages in the payments due on invoices raised by GRE. HPCL also withheld various other amounts on the payments made to GRE, which led to the arbitration proceedings.
3. The Impugned Award holds in GRE’s favour on various counts. The Learned Arbitral Tribunal held that the amount withheld by HPCL on account of Civil Works (Rs. 1,99,07,227); under-insurance (Rs. 25,64,026); Customs Duty variation (Rs. 86,38,491.50); Service Tax (Rs. 3,08,85,583); normalising ‘Dished Ends’ (Rs. 5,00,000); and liquidated damages (Rs. 5,83,67,973) ought not to have been withheld. The Impugned Award directed the payment of such sums by HPCL to GRE. The Impugned Award also awarded interest at the rate of 7% per annum from the date of filing of the claim (September 6, 2012) until the date of actual payment.
4. The core challenge to the Impugned Award is based on alleged perversity in the findings on the following counts, namely:-
(a) Manner of dealing with the facts relating to the Civil Works, with particular regard to consideration of a report by an expert not introduced by HPCL as a witness, as also the contention that disputes relating to Civil Works was not arbitrable;
(b) Denial of Liquidated Damages in the teeth of the contract between the parties; and (c) Manner of dealing with the claims in relation to under-insurance, service tax and Customs Duty.
5. Each of these heads is dealt with below. I have heard, at length, Mr. Zal Andhyarujina, Learned Senior Counsel on behalf of HPCL and Mr. Haresh Jagtiani, Learned Senior Counsel on behalf of GRE, and examined the record with their assistance, bearing in mind the scope of Section 34 of the Act.
Withholding on Civil Works:
6. HPCL withheld an amount of Rs. 1.99 crores on the premise that the Civil Works carried out did not conform to the M30 standard. HPCL’s challenge to the Impugned Award in this regard can be summarised thus:-
(a) Various government agencies are entitled to inspect the Project and point out discrepancies in the execution, and recommend recoveries. HPCL is entitled to effect withholding of amounts. In such event, under Clause 8.b of the General Conditions of Contract (“GCC”), GRE is not entitled to raise any dispute. According to HPCL, the withholding was done pursuant to the recommendation of its own vigilance department, which is a “government agency”. Therefore, this facet of the matter was not arbitrable. HPCL finds fault with the Learned Arbitral Tribunal having rejected an application under Section 16 of the Act in this regard;
(b) In the course of the arbitration, a report dated May 18, 2009 prepared by one Prof. R.S. Jangid of IIT, Mumbai (“Jangid Report”) was relied upon by GRE and the Learned Arbitral Tribunal took it on
Kailash Nath Associates vs. DDA
Gayatri Balasamy vs. M/s ISG Novasoft Technologies Limited
L&T Ltd. Commissioner, Central Excise and Customs Kerala vs. L&T Ltd. –
AI
Liquidated damages require proof of actual losses; insufficient reasoning in arbitral decisions can render findings arbitrary.
Arbitration Award - An Award however can be interfered with if it is found to be vulnerable under any of the grounds in Section 34 including being in contravention with the fundamental policy of Indi....
Liquidated damages must be genuinely reflective of actual loss; their retention without proof of damage is unjustified under relevant contract provisions.
The court affirmed the limited scope of review under Section 34 of the Arbitration and Conciliation Act, emphasizing respect for arbitral awards unless stark violations of public policy or procedural....
Arbitral tribunals have discretion over fact-finding, and courts should not re-evaluate evidence unless decisions violate public policy or involve patent illegality.
The court emphasized that for liquidated damages to be enforceable, the claimant must prove actual loss and the clause must represent a genuine pre-estimate of damages.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.