SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Bom) 291

IN THE HIGH COURT OF BOMBAY AT GOA
SUMAN SHYAM, J.
State of Goa - Appellant
Versus
M/s. U. P. State Bridge Corporation Ltd. - Respondent
Appeal Under Arbitration Act No. 6 of 2022
Decided On : 27-02-2026

Advocates:
Advocate Appeared:
For the Appellant :Mr. Manish Salkar, Government Advocate
For the Respondent:Mr. Shivan Desai, Advocate with Ms. Maria Cotta Viegas, Advocate

Arbitral proceedings pre-1996 Act governed by 1940 Act; no Section 12 disclosure duty; party-nominated arbitrator's known prior ties do not vitiate unanimous three-member award absent proven bias.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 12, 13, 34, 37 and 85(2)(a) - Arbitration Act, 1940 - Section 85(2)(a) of 1996 Act provides that proceedings commenced before its force governed by 1940 Act unless parties agree otherwise - No such agreement; thus no duty on arbitrator to disclose circumstances under Section 12(1) giving rise to justifiable doubts as to independence - Party-nominated arbitrator's alleged prior association known to objecting party beforehand, no objection raised timely - Challenge to arbitrator rejected by tribunal; unanimous award by three-member tribunal with neutral chairman neutralizes any perceived bias - Objection under Section 34 rightly rejected; no interference under Section 37. (Paras 10-15, 19-25, 29-30)

(B) Arbitration - Party-nominated arbitrator in three-member tribunal - Prior employment or consultancy with nominating party, if known, does not ipso facto indicate bias vitiating award, especially when counterbalanced by other members' unanimity - Test of reasonable apprehension of bias not met absent demonstrable prejudice. (Paras 15, 27-29, 31)

(C) Limitation Act, 1963 - Sections 5 and 14 - Applicable to condone delay in Section 34 objections post-Supreme Court directive, but merit-based rejection upheld on grounds above.

Facts of the case:
Contract for bridge construction awarded; span collapsed during execution; disputes referred to three-member arbitral tribunal per contract clause - one nominee each from parties, neutral chairman - Award passed unanimously in favour of contractor including payments, interest, insurance direction - Objections under Section 34 rejected as time-barred initially, revived per Supreme Court order allowing limitation exclusion, then rejected on merits including bias plea.

Findings of Court:
1996 Act inapplicable to pre-existing proceedings; no disclosure violation; no vitiating bias; award unassailable.

Issues: Whether 1996 Act governs proceedings commenced under 1940 Act; duty to disclose under Section 12; vitiation of unanimous award by alleged bias of party nominee.

Ratio Decidendi: Absent agreement, 1996 Act excludes applicability to prior-commenced proceedings; known associations waive disclosure need; three-member unanimity precludes bias inference, limiting judicial interference per Section 5. Result : Appeal dismissed.

Table of Content
1. contract award, bridge collapse, arbitration initiation, award, prior proceedings. (Para 1)
2. appellant alleges arbitrator bias due to prior contractor ties. (Para 2 , 3 , 4 , 5)
3. respondent invokes waiver, estoppel; unanimous award unvitiated. (Para 6 , 7 , 8 , 9)
4. known facts negate disclosure duty; tribunal balance neutralizes bias. (Para 10 , 11 , 12 , 13 , 14 , 15)
5. 1996 act inapplicable to pre-commencement proceedings. (Para 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24)
6. no evidence or reasonable apprehension of actual bias. (Para 25 , 26 , 27 , 28)
7. party-nominated former employees permissible in tribunals. (Para 29 , 30 , 31 , 32)
8. limited judicial interference; appeal dismissed. (Para 33 , 34 , 35 , 36 , 37 , 38 , 39)

JUDGMENT :

SUMAN SHYAM, J.

1.This Appeal preferred by the State of Goa, under Section 37 of the Arbitration and Conciliation Act, 1996, (hereinafter referred to as ‘the Act of 1996’), is directed against the Judgment and Order dated 22.02.2016, passed by the learned Principal District Judge (PDJ), North Goa, in Arbitration and Conciliation Petition No. 2 of 2012, rejecting the objection filed by the Appellant under Section 34 of the Act of 1996. This case has a chequered history. Therefore, in order to appreciate the legal issues involved in the matter, it would be necessary to briefly narrate the facts and circumstances giving rise to the filing of the Appeal.

(i) It appears from the record that the State of Goa had floated a tender inviting bids for construction of the new Mandovi Bridge on NH-17. On evaluation of the bids, the contract was awarded to the Respondent-Corporation pursuant where to, a contract was signed by and in between the parties. Although copy of the contract Agreement is not available on record, yet, it appears from the material on record that the Contract Agreement was signed on 21.02.1987. The bridge was eventually opened for the public on 23.07.1992. However, Span 11 of the bridge had collapsed on 14.10.1990 when the same was still under construction. During the execution of the contract, sudden disputes and differences arose by and between the parties. Therefore, in view of Clause 67 of the Agreement dated 21.02.1987 containing the Arbitration Clause, the disputes were referred to Arbitration.

(ii) As per the Arbitration Agreement, the Arbitral Tribunal was required to be constituted by a Committee of three Members of Arbitrators out of which, one Arbitrator each, was required to be nominated by each of the contracting parties, whereas the Chairman was to be nominated by the Director General (Road Development), Ministry of Surface and Transport, Government of India. Accordingly, the claimant-contractor i.e. the Respondent herein, had nominated Shri Shitala Sharan, as its nominee in the Arbitral Tribunal, whereas the Appellant had nominated Shri N. N. Shrikhande. Shri H. R. Bapu Satyanarayana was nominated on 21.07.1993 as the Chairman of the three Member Panel. In this manner, the three Member Arbitral Tribunal was constituted.

(iii) On 09.01.1996, an objection was filed before the Arbitral Tribunal by the Appellant raising question pertaining to appointment of Shri Shitala Sharan as an Arbitrator nominated by the Respondent, on the ground that his neutrality and independence was under cloud. Although there is no order of the Tribunal on the said objection available on record, yet, it is the admitted position of fact that the Arbitral Tribunal had rejected the objection on 16.01.1996, where- after, the Arbitration proceedings had proceeded. Eventually, on 08.08.1997, an Arbitral Award was passed by the Tribunal. The operative part of the Arbitral Award dated 08.08.1997 is re-produced herein below for ready reference :

“i) a) We award that the Respondent i.e. the State of Goa represented by the Executive Engineer, Works Division VII (NH), Panaji, Goa to pay to the Claimant M/s. U.P. State Bridge Corporation Ltd. the amount of

• Rs.1,31,73,200/- (Rupees One Crore Th

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top