IN THE HIGH COURT AT CALCUTTA
MOUSHUMI BHATTACHARYA, J.
M/s. Navkar Global Infra – Petitioner
Versus
Damodar Valley Corporation – Respondent
W.P. (A) Nos. 27132, 27137 of 2022
Decided On : 19-05-2023
Constitution of India,1950 - Article 12 - Contract/Tender – Rejection of the Techno- Commercial Bid on the ground of being “Non Compliant - Whether petitioner was at all eligible to participate in Tender parameters - Held, affidavit filed by DVC shows that the petitioner failed to furnish details of similar or completed works of the financial parameters mentioned in clause 5.01 of the NIT. The insufficiency of the documents includes the petitioner’s disclosing the Letter of Intent without submitting documents of completion or the value of the work actually completed. In other cases where the petitioner has disclosed Letters of Intent along with work done supported by certificates of completion, the documents do not indicate segregation of the value of work in relation to similar nature of work. DVC has also given instances of requesting submission of appropriate documents from the petitioner’s employer Tata Project Limited but did not receive any response from the petitioner’s employer as to the value of work which could be categorised as transportation which was the requirement of the NIT. Moreover, the purchase orders submitted by the petitioner for different items of work done are less than the minimum financial requirement in clause 5.01 - Writ Petition Dismissed.
JUDGMENT :
MOUSHUMI BHATTACHARYA, J.
1. The writ petitions involve similar facts and have been filed against the Damodar Valley Corporation. Both the writ petitions are being disposed of by the judgment. A few of the dates are different; the facts and dates in WPA 27132 of 2022 are being mentioned in the judgment.
2. The petitioner participated in a Tender floated by the respondent Damodar Valley Corporation for empanelment of transportation agencies for evacuation of ash from ash ponds of Durgapur Steel Thermal Power Station of DVC. The Tender was dated 9.9.2022. The petitioner has challenged the rejection of the petitioner’s techno-commercial bid on 1.12.2022 on the ground of being “Non Compliant.”
3. At the time of moving the matter the petitioner’s grievance was that the petitioner’s bid was admitted by the Tender Evaluation Committee on the same day i.e. 1.12.2022 at 2:04 pm but was rejected 11 minutes later at 2:15 pm.
4. The petitioner was granted interim protection by an order dated 9.12.2022 noting the narrow-margin of 11 minutes and directing DVC to keep any further evaluation of the Tender in abeyance until the matter is heard out on the returnable date. The interim order was extended thereafter. Affidavits are now complete in the matter.
5. Learned counsel appearing for the petitioner submits that the petitioner was eligible under the Tender conditions and the techno-commercial bid submitted by the petitioner was rejected without application of mind and for extraneous considerations. Counsel puts emphasis on the margin of 11 minutes between the petitioner’s bid being accepted at 2:04pm on 1.12.2022 but thereafter being rejected at 2:15 pm on the same day. Counsel places documents to show that the reason given for the impugned rejection, namely, “Techno Commercially Non Compliant” is not a ground of rejection contemplated in the Notice Inviting Tender. Counsel submits that the petitioner had submitted all documents as required by the NIT and no reasons have been given in support of the impugned rejection.
6. Learned counsel appearing for the respondent DVC submits that the scope of work in the NIT, namely, evacuation of ash from ash ponds of the Durgapur Steel Thermal Power Station of DVC and nuisance-free transportation along with disposal of the ash in designated places outside the plant boundary requires uninterrupted and continuous operation. Counsel submits that DVC is seriously prejudiced by the operation of the interim order. Counsel seeks to dislodge the allegation of the 11 minutes margin by stating that the bids were opened on 17.10.2022 and the Tender Inviting Authority informed the petitioner on 1.12.2022 of the impugned rejection. Counsel submits that the impugned decision is fundamentally different from administrative orders issued by the authorities in the general running of the Government and that the decision taken in the present matter is in the realm of contracts. Counsel submits that the authority is not required to give a reasoned order as long as the rejection does not suffer from any irregularity. Counsel places the affidavit filed on behalf of DVC to submit that the petitioner’s techno-commercial bid was rejected for justifiable reasons.
7. Upon considering the material on record in connection with the submissions made on behalf of the parties, the Court arrives at the following findings.
8. Although the primary contention at the time of interim relief was the 11 minutes difference in the admission and rejection of the petitioner’s techno commercial bid, a closer look at the documents reveals otherwise. The petitioner’s bid was opened on 17.10.2022 along with the bids of other bidders who have participated in the tender. A host of correspondence followed thereafter including on 15.11.2022, 17.11.2022, 24.11.2022, 28.11.2022 and 29.11.2022. The correspondences are part of the affidavit filed by the DVC. The correspondence show that DVC sought for clarifications on the documents submitted by the writ pe
A.K.K. Nambiar vs. Union of India
Bharat Singh vs. State of Haryana
Jagdish Mandal vs. State of Orissa
Mohindhr Singh Gill vs. Chief Election Commissioner; New Delhi
National High Speed Rail Corporation Limited vs. Montecarlo Limited
SupremeToday
Judicial review in tender matters limited to arbitrariness or mala fides; courts defer to authority's bid compliance assessment, refusing substitution unless perverse.
In tender matters, judicial review is limited; courts defer to tender authority's bid responsiveness assessment unless arbitrary, mala fide or perverse, prioritizing public interest in infrastructure....
The court emphasized the limited scope of judicial review in tender matters, the importance of punctilious and rigid enforcement of tender terms, and the uniform application of tender requirements to....
The court emphasized the need for restraint and deference to the tendering authority's interpretation of tender documents, especially in technical matters, and highlighted the importance of public in....
The court affirmed that the interpretation of tender conditions by the authority is paramount, and minor technical deficiencies do not justify judicial intervention.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.