SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(Cal) 804

IN THE HIGH COURT AT CALCUTTA
SABYASACHI BHATTACHARYYA, J.
M/s. Greentech Environ Management Private Limited and another – Appellants
Versus
The State of West Bengal and others – Respondent
WPA No. 18204 of 2023
Decided on : 08-08-2023

Advocates:
Advocate Appeared:
For the Appellant : Ms. Reshmi Ghosh, Mr. Soumya Sarkar Chini
For the Respondent: Mr. Jayanta Samanta, Ms. Arpita Mandal, Mr. Sirsanya Bandopadhyay, Mr. Avishek Guha, Ms. Akansha Chopra

A certificate issued by authorities “To Whom It May Concern” is obviously a general certificate addressed to the world at large and speaks for itself.

Headnote:

ESTOPPEL - CERTIFICATE ISSUED BY AUTHORITIES - KMDA - CANCELLATION OF CERTIFICATE - KOLKATA MUNICIPAL CORPORATION - KMDA issued a certificate to the petitioners certifying the completion of bioremediation of legacy waste. Later, KMDA cancelled the certificate on the grounds of misuse by the petitioners. The court held that the certificate was not a credential or completion certificate and that the KMDA was justified in cancelling the same to avoid misuse.

Fact of the Case:

The petitioners, a company dealing with bio-remediation and biomining of municipal and legacy waste, participated in a tender floated by KMDA and were awarded work contracts for bio-mining of legacy waste and land-reclamation of dumpsites. After performing the work for some time, KMDA issued a certificate certifying the completion of bioremediation of legacy waste quantity of 6.10 Lakh Metric Tons. However, KMDA later issued a show-cause notice to the petitioners as to why the certificate would not be cancelled. The petitioners gave a written reply to the show-cause, but KMDA revoked the certificate and requested the petitioners to return the original certificate within seven days.

Finding of the Court:

The court held that the petitioners did not have any statutory or Constitutional right to have a certificate issued in their favour. The court also held that the certificate was not a credential or completion certificate and that the KMDA was justified in cancelling the same to avoid misuse.

Issues: 1. Whether the petitioners had any statutory or Constitutional right to have a certificate issued in their favour? 2. Whether the certificate issued by KMDA was a credential or completion certificate? 3. Whether the KMDA was justified in cancelling the certificate?

Ratio Decidendi: 1. The petitioners did not have any statutory or Constitutional right to have a certificate issued in their favour. 2. The certificate issued by KMDA was not a credential or completion certificate. 3. The KMDA was justified in cancelling the certificate to avoid misuse.

Final Decision: The court disposed of the petition without interfering with the impugned order cancelling the certificate-in-dispute. However, it was made clear that the certificate shall be treated to be valid, for whatever it is worth, in respect of tenders where the petitioners have already participated by production of the said certificate.

JUDGMENT :

Sabyasachi Bhattacharyya, J:-

1. The petitioner no. 1-company deals with bio-remediation and biomining of municipal and legacy waste. The petitioner no. 2 is its director.

2. The petitioner no. 1 participated in a tender floated by the Kolkata Metropolitan Development Authority (KMDA) and turned out successful. Consequently, the petitioner no. 1 was awarded work contracts in respect of several districts, all dated February 17, 2021. The work contracts pertain to bio-mining of legacy waste and land-reclamation of dumpsites utilizing scientific method. The petitioner no. 1 is still working under the said contracts.

3. After performing the work for some time, on September 6, 2021, a certificate was issued by the Chief Engineer, Sewerage, Drainage and Solid Waste Management Sector, KMDA. The said document certified, inter alia, that the petitioner no. 1 had successfully completed bioremediation of legacy waste quantity of 6.10 Lakh Metric Tons “up to 31.07.2021” at the sites across West Bengal, as mentioned therein. It was further stated that the certificate-issuing authority was satisfied with the performance of the petitioner no. 1 “so far”.

4. However, on June 23, 2023, the respondents issued a show-cause notice to the petitioner as to why the said certificate would not be cancelled.

5. The petitioners gave a written reply to the show-cause on June 26, 2023.

6. However, the respondents, vide communication dated July 27, 2023, revoked the certificate and requested the petitioners to return the original certificate within seven days.

7. Being thus aggrieved, the petitioners have preferred the present challenge.

8. Learned counsel for the petitioners argues that valuable rights flowing from the certificate have accrued in favour of the petitioners and the respondents cannot, unilaterally, withdraw such rights. The respondents, it is argued, are also barred by the principle of Estoppel.

9. It is contended that the grounds cited in the show cause notice are not valid in law. Moreover, the impugned cancellation of the certificate is devoid of reasons. In such context, learned counsel appearing for the petitioners cites Assistant Commissioner, Commercial Tax Department, Works Contract and Leasing, Kota Vs. Shukla and Brothers, reported at (2010) 4 SCC 785.

10. Learned counsel next argues that the respondents themselves issued the credential certificate upon completion of a substantial portion of the work by the petitioners in respect of several districts. Even now, the respondents do not dispute the veracity of the facts stated in the certificate. Hence, the impugned cancellation is bad in law and ought to be set aside.

11. It is alleged that the impugned order is violative of Article 19 of the Constitution of India.

12. Learned counsel for the respondent-authorities contends that the petitioners do not have any statutory or Constitutional right to have a certificate issued in their favour. Although the respondents initially issued the certificate-in-dispute, the same was being misused by the petitioners. Learned counsel denies that the certificate was a “completion” certificate or a “credential” certificate. However, the petitioners have been rampantly using the said certificate as credential/completion certificate for participating in other tenders before several authorities in different states.

13. It is contended that the petitioners, on the basis of the certificate, have been claiming around that the same was a credential certificate and should be treated as proof of completion of work by the petitioners under the tender floated by the present respondents.

14. Queries were raised by such other tendering authorities in several states as to the credibility of the said certificate issued by the respondents, for which the latter”s goodwill is suffering.

15. For example, it is submitted, tendering authorities from Cuttack sought to clarify doubts regarding the certificate, which was produced by the petitioners in a tender floated by the sa

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top