IN THE HIGH COURT AT CALCUTTA
SABYASACHI BHATTACHARYYA, J.
Damodar Valley Corporation - Petitioner
Versus
BLA Projects Pvt. Ltd. - Respondent
AP-COM No. 231 of 2024
Decided On : 13-08-2024
Arbitration - Challenge to Award - Arbitration and Conciliation Act, 1996 - Sections 34, 21(3) - The court upheld the arbitrator's decision, emphasizing the limited grounds for setting aside an award under Section 34, particularly post-2015 amendments, and clarified the definitions of corrupt and fraudulent practices in contract execution.
Fact of the Case:
The petitioner challenged an arbitral award favoring the claimant, arguing that the award contradicted the contract terms, particularly regarding termination due to alleged corrupt practices and the handling of claims related to coal quality.
Issues: Whether the arbitrator acted with patent illegality in holding the termination of the contract as unlawful and whether the claims awarded were justified.
Ratio Decidendi: The court reiterated that under Section 34 of the Arbitration and Conciliation Act, the merits of the arbitrator's decision cannot be re-evaluated, and the definitions of corrupt and fraudulent practices pertain to the procurement process, not contract execution.
Result: The challenge under Section 34 of the Arbitration and Conciliation Act is dismissed, affirming the arbitral award.
JUDGMENT :
Sabyasachi Bhattacharyya, J.
1. The present challenge under Section 34 of the Arbitration and Conciliation 1996 (hereinafter refer to as “the 1996 Act) has been preferred against the award dated August 14, 2021 passed in an arbitral proceedings between the parties. BLA Projects Private Limited (the respondent herein) was the claimant. Out of the seven heads of claim, four were allowed by the learned arbitrator. Counter claims on two counts made by the Damodar Valley Corporation (DVC), the respondent before the learned arbitrator and the petitioner herein, were turned down.
2. Learned counsel for the petitioner argues that the award is contrary to the terms of the contract. As per the contract, DVC was entitled to terminate the contract if the claimant/BLA indulged in corrupt and fraudulent practices. The relevant clauses relating to termination were Clause 15 of the General Terms and Conditions, Clause 17 of the General Conditions of Contract (GCC), Clause 14 of the Annual Rates Contract (ARC) and Clause 24.2.1 of the Additional/Special Conditions of Contract.
3. It is argued that all the clauses are almost identical and permit termination in the event of corrupt or fraudulent practices in executing the contract. Some of the said clauses also contemplate termination at the sole discretion of the DVC, albeit with a 60 days' prior notice. It is argued that the learned arbitrator erred in holding that "corrupt" and "fraudulent" practice were intended to cover malpractice indulged in by the contractor in the matter of procurement of the contract only and not activity in performance of the contract. Thus, the other conditions of contract were overlooked by the learned arbitrator.
4. In the present case, the first notice of termination was issued, after which the matter came up to this Court and upon a direction being passed by this Court, a hearing was given to both sides and a reasoned order was passed by the Executive Director of the DVC. The said reasoned order granted liberty to the DVC to issue termination notice. In pursuance thereof, the termination notice was issued, contemplating forthwith termination.
5. It is argued that the learned arbitrator failed to take into consideration all the provisions of termination under the agreement between the parties and stuck to Clause 24.2.1 only, thus rendering the award contrary to the terms of the contract and violative of Section 21(3) of the 1996 Act.
6. Learned counsel for the petitioner next argues that the claimants/respondent indulged in corrupt and fraudulent practice. The relevant documents show that fraud was perpetuated by the BLA (claimant). The unloaded coal was contaminated with mud. The contaminated coal was loaded at the siding. The defence taken by the claimant was heavy rain, due to which the coal allegedly got mixed with the mud and soil at the loading point (kaccha point). Thus, inferior quality of coal was mixed with extraneous materials, which was admitted by the claimant, thus making the claimant liable for termination of its contract. It is argued that contamination of coal is an admitted fact in the reply dated June 5, 2018 by the claimant to the show- se notice dated June 2, 2018 and even in the statement of claims and the cross-examination of the Claimant's Witness (CW).
7. With regard to claim nos.1 and 2, pertaining to the Running Account (RA) bills, the learned arbitrator erroneously directed payment of such bills since the BLA had indulged in a corrupt and fraudulent practice. Under Clause 13 of the Annual Rates Contract, the DVC is, in fact, entitled to impose penalty for carrying stones, shortages and in respect of quantity etc, which was required to be adjusted from the running bills.
8. Further, the Engineer-in-Charge of the DVC was to pass the bills after scrutiny and final bill was to be made payable only after the reconciliation of the bills, outstanding penalties etc. at the end of the contract period. The running bills in the present case were
A.E.G. Carapiet Vs. A.Y. Derderian
A.T. Brij Paul Singh Vs. State of Gujarat
Mohd. Salamatullah Vs. Govt. Of A.P.
MSK Projects (I) (JV) Ltd. Vs. State of Rajasthan
Ssangyong Engineering & Construction Co. Ltd. v. National Highway Authority of India (NHAI)
Associate Builders v. Delhi Development Authority
Indian Oil Corporation. Ltd. v. Amritsar Gas Service and Others
Patel Engineering Ltd. v. North Eastern Electric Power Corporation. Ltd
The court emphasized that the grounds for challenging an arbitral award are limited, particularly post-2015 amendments, and clarified the definitions of corrupt and fraudulent practices in the contex....
The Court emphasized the limited scope of jurisdiction under Section 34 of the Act and the need for evidence to support claims for loss of profit.
Point of law: Arbitration Award - It must clearly be understood that when a court is applying the "public policy" test to an arbitration award, it does not act as a court of appeal and consequently e....
The limited grounds for interference with an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996, emphasize the concept of patent illegality and the criteria for setting asi....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.